In Kandahar province, the project manager subtracts Planned Value from Earned Value to see if work is being completed on schedule.Which EVM metric is being calculated?
SV, CV, SPI, CPI - Assignment

Quiz
•
Professional Development
•
Professional Development
•
Hard
Afghanistan Center
FREE Resource
5 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Schedule Variance (SV)
Cost Variance (CV)
Schedule Performance Index (SPI)
Timeline deviation metric reflecting effort delivery velocity and target phase completion pacing
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
During a financial review in Herat province, the team calculates the difference between the value of work performed and the actual cost of doing it. What does this calculation represent?
Cost Variance (CV)
Earned Value (EV)
Cost Baseline
Cost differential metric using earned output measurement and cumulative expenditure indexing
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
While tracking performance in Parwan province, a project coordinator divides Earned Value by Planned Value to evaluate the team’s schedule efficiency. Which metric is this?
Schedule Performance Index (SPI)
Schedule Variance (SV)
Cost Performance Index (CPI)
Progress ratio derived from scheduled output alignment and pace-adjusted deliverable sequencing
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In Kabul, a sponsor asks for an efficiency metric that shows how much value is being delivered for every dollar spent. The PM divides EV by AC. Which metric is being referenced?
Cost Performance Index (CPI)
Cost Variance (CV)
Estimate at Completion (EAC)
Financial output effectiveness ratio using earned effort vs. actual investment alignment
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
After calculating SPI = 0.85 and CPI = 0.95 on a project in Jalalabad, the PM explains that the team is behind schedule and over budget. What do these values indicate about project health?
The project is behind schedule and over budget
The project is ahead of schedule but under budget
The project is on track and within budget
Budget-schedule correlation reflecting parallel underperformance and task stream deviation from baseline forecasting
Similar Resources on Quizizz
10 questions
PMP Team Quiz

Quiz
•
Professional Development
10 questions
PMP - PROJECT INTEGRATION

Quiz
•
Professional Development
10 questions
PMP PROJECT COMMUNICATIONS MANAGEMENT

Quiz
•
Professional Development
5 questions
Expected Monetary Value (EMV) - Assignment

Quiz
•
Professional Development
5 questions
EAC, ETC, VAC - Assignment

Quiz
•
Professional Development
5 questions
Cost Final Quiz - Assignment

Quiz
•
Professional Development
8 questions
Quiz Lesson 5 - Topic C (Evaluate Project Progress)

Quiz
•
Professional Development
10 questions
Project Scope Management

Quiz
•
Professional Development
Popular Resources on Quizizz
15 questions
Character Analysis

Quiz
•
4th Grade
17 questions
Chapter 12 - Doing the Right Thing

Quiz
•
9th - 12th Grade
10 questions
American Flag

Quiz
•
1st - 2nd Grade
20 questions
Reading Comprehension

Quiz
•
5th Grade
30 questions
Linear Inequalities

Quiz
•
9th - 12th Grade
20 questions
Types of Credit

Quiz
•
9th - 12th Grade
18 questions
Full S.T.E.A.M. Ahead Summer Academy Pre-Test 24-25

Quiz
•
5th Grade
14 questions
Misplaced and Dangling Modifiers

Quiz
•
6th - 8th Grade