SV, CV, SPI, CPI - Assignment
Authored by Afghanistan Center
Professional Development
Professional Development

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
5 questions
Show all answers
1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In Kandahar province, the project manager subtracts Planned Value from Earned Value to see if work is being completed on schedule.Which EVM metric is being calculated?
Schedule Variance (SV)
Cost Variance (CV)
Schedule Performance Index (SPI)
Timeline deviation metric reflecting effort delivery velocity and target phase completion pacing
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
During a financial review in Herat province, the team calculates the difference between the value of work performed and the actual cost of doing it. What does this calculation represent?
Cost Variance (CV)
Earned Value (EV)
Cost Baseline
Cost differential metric using earned output measurement and cumulative expenditure indexing
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
While tracking performance in Parwan province, a project coordinator divides Earned Value by Planned Value to evaluate the team’s schedule efficiency. Which metric is this?
Schedule Performance Index (SPI)
Schedule Variance (SV)
Cost Performance Index (CPI)
Progress ratio derived from scheduled output alignment and pace-adjusted deliverable sequencing
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In Kabul, a sponsor asks for an efficiency metric that shows how much value is being delivered for every dollar spent. The PM divides EV by AC. Which metric is being referenced?
Cost Performance Index (CPI)
Cost Variance (CV)
Estimate at Completion (EAC)
Financial output effectiveness ratio using earned effort vs. actual investment alignment
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
After calculating SPI = 0.85 and CPI = 0.95 on a project in Jalalabad, the PM explains that the team is behind schedule and over budget. What do these values indicate about project health?
The project is behind schedule and over budget
The project is ahead of schedule but under budget
The project is on track and within budget
Budget-schedule correlation reflecting parallel underperformance and task stream deviation from baseline forecasting
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Similar Resources on Wayground
10 questions
Quiz Lesson 3 - Topic F (Risks)
Quiz
•
Professional Development
10 questions
Post Test IHT Merdeka Belajar
Quiz
•
Professional Development
10 questions
LESSON 1: INTRODUCTION TO OPEN EDUCATIONAL RESOURCES
Quiz
•
Professional Development
10 questions
Systems Operations on AWS - Day 3
Quiz
•
University - Professi...
10 questions
Accelerate & Incubator Quiz
Quiz
•
Professional Development
10 questions
Quiz Lesson 3 - Topic D (Resources and Procurement)
Quiz
•
Professional Development
10 questions
SCH Post test in Kannad
Quiz
•
Professional Development
10 questions
Financial Statements
Quiz
•
Professional Development
Popular Resources on Wayground
7 questions
History of Valentine's Day
Interactive video
•
4th Grade
15 questions
Fractions on a Number Line
Quiz
•
3rd Grade
20 questions
Equivalent Fractions
Quiz
•
3rd Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
22 questions
fractions
Quiz
•
3rd Grade
15 questions
Valentine's Day Trivia
Quiz
•
3rd Grade
20 questions
Main Idea and Details
Quiz
•
5th Grade
20 questions
Context Clues
Quiz
•
6th Grade