SV, CV, SPI, CPI - Assignment

SV, CV, SPI, CPI - Assignment

Professional Development

5 Qs

quiz-placeholder

Similar activities

EAC, ETC, VAC - Assignment

EAC, ETC, VAC - Assignment

Professional Development

5 Qs

EVM Basic Terminology

EVM Basic Terminology

Professional Development

5 Qs

SG20_Test_S5_CH6 Schedule

SG20_Test_S5_CH6 Schedule

Professional Development

10 Qs

Project Management

Project Management

Professional Development

10 Qs

Quiz Lesson 5 - Topic C (Evaluate Project Progress)

Quiz Lesson 5 - Topic C (Evaluate Project Progress)

Professional Development

8 Qs

Atoha PMP lesson 14

Atoha PMP lesson 14

Professional Development

10 Qs

15a. PED - Plant Establishment Management

15a. PED - Plant Establishment Management

Professional Development

10 Qs

Expected Monetary Value (EMV) - Assignment

Expected Monetary Value (EMV) - Assignment

Professional Development

5 Qs

SV, CV, SPI, CPI - Assignment

SV, CV, SPI, CPI - Assignment

Assessment

Quiz

Professional Development

Professional Development

Hard

Created by

Afghanistan Center

FREE Resource

5 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Kandahar province, the project manager subtracts Planned Value from Earned Value to see if work is being completed on schedule.Which EVM metric is being calculated?

Schedule Variance (SV)

Cost Variance (CV)

Schedule Performance Index (SPI)

Timeline deviation metric reflecting effort delivery velocity and target phase completion pacing

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During a financial review in Herat province, the team calculates the difference between the value of work performed and the actual cost of doing it. What does this calculation represent?

Cost Variance (CV)

Earned Value (EV)

Cost Baseline

Cost differential metric using earned output measurement and cumulative expenditure indexing

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

While tracking performance in Parwan province, a project coordinator divides Earned Value by Planned Value to evaluate the team’s schedule efficiency. Which metric is this?

Schedule Performance Index (SPI)

Schedule Variance (SV)

Cost Performance Index (CPI)

Progress ratio derived from scheduled output alignment and pace-adjusted deliverable sequencing

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Kabul, a sponsor asks for an efficiency metric that shows how much value is being delivered for every dollar spent. The PM divides EV by AC. Which metric is being referenced?

Cost Performance Index (CPI)

Cost Variance (CV)

Estimate at Completion (EAC)

Financial output effectiveness ratio using earned effort vs. actual investment alignment

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

After calculating SPI = 0.85 and CPI = 0.95 on a project in Jalalabad, the PM explains that the team is behind schedule and over budget. What do these values indicate about project health?

The project is behind schedule and over budget

The project is ahead of schedule but under budget

The project is on track and within budget

Budget-schedule correlation reflecting parallel underperformance and task stream deviation from baseline forecasting