CM Revision End Test Chapter 1.4 CPN and 1.5 Gantt Chart

CM Revision End Test Chapter 1.4 CPN and 1.5 Gantt Chart

Vocational training

8 Qs

quiz-placeholder

Similar activities

Industry bodies

Industry bodies

KG - University

13 Qs

Contract admin week 3. Tendering

Contract admin week 3. Tendering

University

12 Qs

3 Drawings (2365 Unit 203)

3 Drawings (2365 Unit 203)

KG - University

6 Qs

[WEEK 9] LET'S SQUEEZE THE QUIZ

[WEEK 9] LET'S SQUEEZE THE QUIZ

University

10 Qs

110 Contract Quiz

110 Contract Quiz

University

10 Qs

SSD Quiz. Plans with Scott 2.0

SSD Quiz. Plans with Scott 2.0

8th Grade

10 Qs

MEMANTAU KEMAJUAN KERJA

MEMANTAU KEMAJUAN KERJA

KG - University

10 Qs

testing

testing

University

4 Qs

CM Revision End Test Chapter 1.4 CPN and 1.5 Gantt Chart

CM Revision End Test Chapter 1.4 CPN and 1.5 Gantt Chart

Assessment

Quiz

Construction

Vocational training

Easy

Created by

Siti Norbazilah Bazz

Used 1+ times

FREE Resource

8 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the function of the Critical Path Network analysis?

A.    To prevent major accidents from happening to the construction project.

B.    To ensure that the employers pay the contractors in a regular manner.

C.    To make sure that all the contractors are following proper guidelines.

D.    To identify the critical activities from all the operations and activities in a project.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Media Image

With regards to Critical Path Network analysis, in the following figure (figure 1), task B depends upon task A. What type of diagram is shown on figure 1?

A.    Network diagram

B.    Activity-on-Arrow diagram

C.    Activity-on-Nodes diagram

D.    Activity label arrow diagram

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is a reason why planning in advance of the construction project has been rapidly developing?

A.    Fluctuating oil prices

B.    Increasing global warming

C.    Increase in work competition

D.    Larger and more complex projects

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the definition of the Method Statement?

A.    The statement lists the financial breakdown of the activity.

B.    The statement arranges ideas of how contracts are executed.

C.    The statement clarifies the organisational chart of the project.

D.    The document lists down the contractors and labourers of the activity.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In creating Bar/Gantt Charts, what do we mean by the term “Work Schedule”?

A.    A time framework for the project plan.

B.    A method to select a suitable contractor.

C.    A document used to verify any payments.

D.    A system used to monitor workers’ attendance.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In the Bar/Gantt Chart, what does the use of different colours represent?

A.    To ensure that the contractors remain competent.

B.    To identify the tasks of contractors and subcontractors.

C.    To allow comparison between scheduled and built progress.

D.    To prevent any construction accidents from occurring on site.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the most widely accepted method of presenting technically the work schedule activities sequence and time duration information?

A.    Layout Diagram

B.    Bar or Gantt Chart

C.    Sales invoice document

D.    Tender information billing

8.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In terms of construction, why do we need to prepare the Method Statement?

A.    To give a suitable level of production flow.

B.    To gauge the bonus for the workers’ salary.

C.    To list properly the work organisational chart.

D. To select the most appropriate sub-contractors.