Search Header Logo

SBEQ2523 LOSS & EXPENSE

Authored by FARRAH A

Architecture

University

Used 1+ times

SBEQ2523 LOSS & EXPENSE
AI

AI Actions

Add similar questions

Adjust reading levels

Convert to real-world scenario

Translate activity

More...

    Content View

    Student View

15 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

1. What is the main objective of awarding loss and expense under construction contracts?

A) To penalize the employer

B) To ensure early completion

C) To restore the contractor to the financial position they would have been in but for the delay

D) To cover all contractor’s profit margins

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

2. Which law in Malaysia codifies the principle on damages as outlined in Hadley v Baxendale?

A) Arbitration Act 2005

B) Contracts Act 1950, Section 74

C) Specific Relief Act 1950

D) Evidence Act 1950

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

3. What was held in Fateh Construction v Maharani Specialist Hospital regarding loss claims?

A) Contractors are entitled to claims without evidence

B) Contractors must prove actual loss and demonstrate mitigation

C) Employers are not liable for prolongation cost

D) Claims can be based on estimated figures alone

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

4. Under which standard form clause can a contractor claim for loss and expense in PAM 2006?

A) Clause 44

B) Clause 20

C) Clause 24

D) Clause 10

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Sunissa v Kerajaan Malaysia, what did the court emphasize regarding notice?

A) Late notice is acceptable

B) Verbal notice is sufficient

C) Notice is not required

D) Timely written notice is mandatory as a condition precedent

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

6. What must a contractor prove to succeed in a prolongation cost claim?

A) Delay only

B) Financial loss only

C) Both critical delay and associated financial loss

D) Early completion and loss of opportunity

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

7. In Croudace v London Borough of Lambeth, the court held that:

A) The employer can reject a claim without consequences

B) The architect's failure to assess a valid claim can make the employer liable

C) Only arbitration can resolve disputes

D) Contractors cannot claim claim-preparation costs

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?