SBEQ2523 LOSS & EXPENSE

SBEQ2523 LOSS & EXPENSE

University

15 Qs

quiz-placeholder

Similar activities

Standard of Professional Practice

Standard of Professional Practice

University

10 Qs

Quiz on Quantity Surveying

Quiz on Quantity Surveying

University

10 Qs

Key Players in Construction

Key Players in Construction

University

10 Qs

FBC: Introduction to FBC

FBC: Introduction to FBC

University

12 Qs

L1: Overview of Building Science & Services I

L1: Overview of Building Science & Services I

University

10 Qs

Week3_Q1_Time Terms in Construction Project

Week3_Q1_Time Terms in Construction Project

University

15 Qs

BIM Intern learning session

BIM Intern learning session

University

11 Qs

BQS601 INTRODUCTION

BQS601 INTRODUCTION

University

12 Qs

SBEQ2523 LOSS & EXPENSE

SBEQ2523 LOSS & EXPENSE

Assessment

Quiz

Architecture

University

Easy

Created by

FARRAH A

Used 1+ times

FREE Resource

15 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

1. What is the main objective of awarding loss and expense under construction contracts?

A) To penalize the employer

B) To ensure early completion

C) To restore the contractor to the financial position they would have been in but for the delay

D) To cover all contractor’s profit margins

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

2. Which law in Malaysia codifies the principle on damages as outlined in Hadley v Baxendale?

A) Arbitration Act 2005

B) Contracts Act 1950, Section 74

C) Specific Relief Act 1950

D) Evidence Act 1950

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

3. What was held in Fateh Construction v Maharani Specialist Hospital regarding loss claims?

A) Contractors are entitled to claims without evidence

B) Contractors must prove actual loss and demonstrate mitigation

C) Employers are not liable for prolongation cost

D) Claims can be based on estimated figures alone

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

4. Under which standard form clause can a contractor claim for loss and expense in PAM 2006?

A) Clause 44

B) Clause 20

C) Clause 24

D) Clause 10

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Sunissa v Kerajaan Malaysia, what did the court emphasize regarding notice?

A) Late notice is acceptable

B) Verbal notice is sufficient

C) Notice is not required

D) Timely written notice is mandatory as a condition precedent

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

6. What must a contractor prove to succeed in a prolongation cost claim?

A) Delay only

B) Financial loss only

C) Both critical delay and associated financial loss

D) Early completion and loss of opportunity

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

7. In Croudace v London Borough of Lambeth, the court held that:

A) The employer can reject a claim without consequences

B) The architect's failure to assess a valid claim can make the employer liable

C) Only arbitration can resolve disputes

D) Contractors cannot claim claim-preparation costs

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?