1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
During which phase of the construction project life cycle is a risk/benefit analysis typically performed to assess project viability?
Detailed Scope (Define)
Feasibility (Appraise)
Procurement
Commissioning and Startup
Answer explanation
The Feasibility (Appraise) stage focuses on evaluating project viability through a risk/benefit analysis conducted by the owner.
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following activities occurs during the Concept (Select) phase of the Front-End Planning Phase?
Selecting contractors
Formalizing in-depth scope definition
Developing project execution plan and identifying stakeholders
Executing the foundation work
Answer explanation
The Concept phase includes developing the overall project strategy and identifying key stakeholders, along with preliminary planning.
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the main objective of the Detailed Scope (Define) phase?
Sourcing materials for execution
Inspecting the final deliverable
Finalizing goals and formalizing scope, resources, and budget
Identifying construction contractors
Answer explanation
The Detailed Scope (Define) phase involves confirming project goals and detailing scope, resource needs, and budget requirements.
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What marks the start of the Execution Phase in the construction project life cycle?
Finalized project charter
Fully designed project
Stakeholder approval of WBS
Completion of commissioning activities
Answer explanation
The Execution Phase begins with the Detailed Design stage, where the project is fully designed in preparation for procurement and construction.
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which activity is typically associated with the Procurement phase?
Performing risk analysis
Constructing the foundation
Elaborating contracts and sourcing materials
Approving final design documents
Answer explanation
The Procurement phase includes selecting contractors, developing contracts, and sourcing required construction materials.
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following occurs during the Handover Phase?
Inspecting end deliverables and startup procedures
Creating WBS and preliminary schedule
Identifying project team roles and stakeholders
Executing work according to plan
Answer explanation
The Handover Phase includes Commissioning and Startup, where the final deliverables are inspected and turned over to the owner or operational team.
Similar Resources on Wayground
10 questions
Project Stakeholder Management

Quiz
•
Professional Development
10 questions
SG20_Test_S9_CH8&11 Quality & Risk

Quiz
•
Professional Development
10 questions
Communication & Interpersonal Skills at Work

Quiz
•
Professional Development
10 questions
PROJECT RISK MANAGEMENT

Quiz
•
Professional Development
8 questions
Quiz Lesson 5 - Topic E (Manage Project Changes)

Quiz
•
Professional Development
10 questions
Deloitte- Position Vs Interest- Meaningful Conversations

Quiz
•
Professional Development
10 questions
Final Quiz - Assignment

Quiz
•
Professional Development
8 questions
Quiz Lesson 6 - Topic B (Benefits Realization)

Quiz
•
Professional Development
Popular Resources on Wayground
10 questions
Lab Safety Procedures and Guidelines

Interactive video
•
6th - 10th Grade
10 questions
Nouns, nouns, nouns

Quiz
•
3rd Grade
10 questions
9/11 Experience and Reflections

Interactive video
•
10th - 12th Grade
25 questions
Multiplication Facts

Quiz
•
5th Grade
11 questions
All about me

Quiz
•
Professional Development
22 questions
Adding Integers

Quiz
•
6th Grade
15 questions
Subtracting Integers

Quiz
•
7th Grade
9 questions
Tips & Tricks

Lesson
•
6th - 8th Grade