Construction Project Life Cycle - Assignment

Construction Project Life Cycle - Assignment

Professional Development

6 Qs

quiz-placeholder

Similar activities

Project Management Module

Project Management Module

Professional Development

10 Qs

Research Quiz

Research Quiz

Professional Development

10 Qs

Quiz Lesson 3 - Topic G (Quality)

Quiz Lesson 3 - Topic G (Quality)

Professional Development

10 Qs

Project Management (Week 4)

Project Management (Week 4)

Professional Development

8 Qs

Quiz Lesson 3 - Topic A (Planning Projects)

Quiz Lesson 3 - Topic A (Planning Projects)

Professional Development

8 Qs

Procurement 10 soal (Chapter 12)

Procurement 10 soal (Chapter 12)

Professional Development

10 Qs

LO2 Project Life Cycles Quiz

LO2 Project Life Cycles Quiz

Professional Development

10 Qs

Test Planning

Test Planning

Professional Development

10 Qs

Construction Project Life Cycle - Assignment

Construction Project Life Cycle - Assignment

Assessment

Quiz

Professional Development

Professional Development

Hard

Created by

Afghanistan Center

FREE Resource

6 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During which phase of the construction project life cycle is a risk/benefit analysis typically performed to assess project viability?

Detailed Scope (Define)

Feasibility (Appraise)

Procurement

Commissioning and Startup

Answer explanation

The Feasibility (Appraise) stage focuses on evaluating project viability through a risk/benefit analysis conducted by the owner.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following activities occurs during the Concept (Select) phase of the Front-End Planning Phase?

Selecting contractors

Formalizing in-depth scope definition

Developing project execution plan and identifying stakeholders

Executing the foundation work

Answer explanation

The Concept phase includes developing the overall project strategy and identifying key stakeholders, along with preliminary planning.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the main objective of the Detailed Scope (Define) phase?

Sourcing materials for execution

Inspecting the final deliverable

Finalizing goals and formalizing scope, resources, and budget

Identifying construction contractors

Answer explanation

The Detailed Scope (Define) phase involves confirming project goals and detailing scope, resource needs, and budget requirements.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What marks the start of the Execution Phase in the construction project life cycle?

Finalized project charter

Fully designed project

Stakeholder approval of WBS

Completion of commissioning activities

Answer explanation

The Execution Phase begins with the Detailed Design stage, where the project is fully designed in preparation for procurement and construction.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which activity is typically associated with the Procurement phase?

Performing risk analysis

Constructing the foundation

Elaborating contracts and sourcing materials

Approving final design documents

Answer explanation

The Procurement phase includes selecting contractors, developing contracts, and sourcing required construction materials.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following occurs during the Handover Phase?

Inspecting end deliverables and startup procedures

Creating WBS and preliminary schedule

Identifying project team roles and stakeholders

Executing work according to plan

Answer explanation

The Handover Phase includes Commissioning and Startup, where the final deliverables are inspected and turned over to the owner or operational team.