D32 quiz of the day

D32 quiz of the day

University

25 Qs

quiz-placeholder

Similar activities

Diabetes & Renal Disease

Diabetes & Renal Disease

University

20 Qs

Conservation of Mass (Thermodynamics)

Conservation of Mass (Thermodynamics)

University

20 Qs

ccrn 3151 sec 1

ccrn 3151 sec 1

University

20 Qs

Tht mata, anemia, kulit, perhitungan dosis, farmakokinetik

Tht mata, anemia, kulit, perhitungan dosis, farmakokinetik

University

20 Qs

QUIZ 4 : TOPIC 10 [STANDARD COSTING & VARIANCE ANALYSIS]

QUIZ 4 : TOPIC 10 [STANDARD COSTING & VARIANCE ANALYSIS]

1st Grade - University

20 Qs

Dynamics | Physics

Dynamics | Physics

11th Grade - University

20 Qs

Penilaian Agama Islam K13 ( Kelas VI )

Penilaian Agama Islam K13 ( Kelas VI )

1st Grade - University

20 Qs

unit 1 force analysis

unit 1 force analysis

University

25 Qs

D32 quiz of the day

D32 quiz of the day

Assessment

Quiz

Education

University

Easy

Created by

WINCENTRE CLASSES

Used 2+ times

FREE Resource

25 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What is the measuring unit for site clearance?
Running meter
Each

Answer explanation

Site clearance is measured in square meters (m²) as it involves clearing area on the ground.

2.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

How many modular bricks are required for 1 m³ of brickwork?
400
500
600
550

Answer explanation

As per data book, 500 modular bricks are needed for 1 m³ of brickwork.

3.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

How many laterite stones are required for 1 m³ of wall?
50
55
60
65

Answer explanation

According to the data book, 60 laterite stones are needed for 1 m³ of masonry.

4.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What is the painting coefficient for a panelled door per side?
1.3
1.2
0.5
2.0

Answer explanation

Painting coefficient for a panelled door is 1.3 for each side.

5.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What is the dry volume of mortar for 1 m³ of brick masonry?
0.25 m³
0.30 m³
0.45 m³
0.15 m³

Answer explanation

Dry volume of mortar required is 0.30 m³ for every 1 m³ of brick masonry.

6.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What is the weight of cement needed for 1 m³ of PCC in 1:3:6 mix?
228 kg
330 kg
137 kg
432 kg

Answer explanation

228 kg of cement is required for 1 m³ of PCC in 1:3:6 mix.

7.

MULTIPLE CHOICE QUESTION

1 min • 1 pt

What is the standard deduction rule for plastering openings up to 0.5 m²?
No deduction
One side deducted
Both sides deducted
Double area deducted

Answer explanation

Openings up to 0.5 m² are not deducted from plastering measurement.

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?