10 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

During a project kickoff in Kabul, the team conducts brainstorming and interviews with key stakeholders to document uncertainties that could impact project objectives.Which process is being performed?

Identify Risks

Perform Qualitative Risk Analysis

Plan Risk Responses

Monitor Risks

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Herat province, a project manager uses a probability and impact matrix to prioritize risks based on how likely they are to occur and how much they could affect the project. What risk process is being used?

Perform Qualitative Risk Analysis

Perform Quantitative Risk Analysis

Monitor Risks

Plan Risk Responses

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Nangarhar province, the team runs simulations to predict the project's cost range and timeline based on risk scenarios. They use data models and decision trees. Which process does this describe?

Perform Quantitative Risk Analysis

Identify Risks

Monitor Risks

Control Schedule

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Samangan province, a project manager prepares strategies for high-priority risks. For example, one threat will be transferred via contract, and an opportunity will be shared with a partner NGO. Which process is being executed?

Plan Risk Responses

Implement Risk Responses

Monitor Risks

Perform Qualitative Risk Analysis

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In India, a project team activates a planned backup vendor after a key supplier fails to deliver. This action follows a predefined contract set during risk planning. Which risk process is taking place?

Implement Risk Responses

Plan Procurement Management

Monitor Risks

Control Procurements

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Balkh province, the project manager regularly reviews the risk register, checks effectiveness of risk responses, and updates risks based on new conditions. Which process is being conducted?

Monitor Risks

Perform Qualitative Risk Analysis

Control Quality

Validate Scope

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In Daykundi province, a risk event occurred despite mitigation. The team immediately activates the fallback plan while escalating unresolved issues. What type of planning is this?

Fallback Plan

Risk Avoidance

Risk Acceptance

Risk Identification

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?

Discover more resources for Professional Development