PE Exam Reference Quiz

PE Exam Reference Quiz

University

93 Qs

quiz-placeholder

Similar activities

COMPETENCY 8

COMPETENCY 8

University

90 Qs

TRY OUT PCK MATEMATIKA

TRY OUT PCK MATEMATIKA

University

90 Qs

Statistics Review A: Descrip Stat, Test Design, Lin Reg

Statistics Review A: Descrip Stat, Test Design, Lin Reg

9th Grade - University

95 Qs

untitled

untitled

8th Grade - University

98 Qs

Revision Maths

Revision Maths

2nd Grade - University

88 Qs

Cset 2

Cset 2

University

98 Qs

Discrete Mathematics (Finals)

Discrete Mathematics (Finals)

University

90 Qs

Final Exam Math 95 Fall 2023

Final Exam Math 95 Fall 2023

University

92 Qs

PE Exam Reference Quiz

PE Exam Reference Quiz

Assessment

Quiz

Mathematics

University

Easy

Created by

rey moralde

Used 4+ times

FREE Resource

93 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

For any proposed bridge site, the topographic and river surveys should be extended from the centerline of the bridge at least

100 to 200 upstream only

100 to 200 downstream only

100 to 200 upstream and downstream

300 m upstream and downstream

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the simplest type of superstructure of a concrete bridge with a limited span of 8 meters?

Reinforced concrete slab

Concrete plank deck

Girder and slab superstructure

Beam or Plank Bridge

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of these is not classified as a type of caisson foundation?

Pneumatic foundation

Box caisson

Open caisson

Hydraulic caisson

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following documents is not necessary at the project site?

Bill of quantities

Plans

General specification

Feasibility study

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

An asphalt cement can be a good bituminous binder material for item

306

308

310

311

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

The following reasons may cause the granting of contract time extension with the exception of one:

Exceptionally adverse climate conditions

Excusable failure of contractor to provide equipment and man power

Causes beyond the control of contractor

Causes of which government is not directly responsible

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the allowable variance from the original unit price, so that a contract will be entitled to contract price escalation?

Less than 2 %

Less than 5 %

More than 5 %

Less than 3 %

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?