Unit 6: Operating Guidelines

Unit 6: Operating Guidelines

University

58 Qs

quiz-placeholder

Similar activities

2425_ÔN TẬP TIN HỌC 9

2425_ÔN TẬP TIN HỌC 9

9th Grade - University

54 Qs

Chương 2_Mạng máy tính và Internet

Chương 2_Mạng máy tính và Internet

University

60 Qs

Câu hỏi về lập trình

Câu hỏi về lập trình

10th Grade - University

62 Qs

Câu hỏi trắc nghiệm về Quản lý Dự án

Câu hỏi trắc nghiệm về Quản lý Dự án

University

54 Qs

Ôn tập TK HĐT(60 câu đầu)

Ôn tập TK HĐT(60 câu đầu)

University

61 Qs

Tin 4 phần 3

Tin 4 phần 3

University

54 Qs

TIN6_ÔN TẬP HKI_2425

TIN6_ÔN TẬP HKI_2425

6th Grade - University

60 Qs

Từ câu 61-120 Câu hỏi nghiệp vụ CT 40

Từ câu 61-120 Câu hỏi nghiệp vụ CT 40

University

60 Qs

Unit 6: Operating Guidelines

Unit 6: Operating Guidelines

Assessment

Quiz

Computers

University

Medium

Created by

Khoi huy

Used 2+ times

FREE Resource

58 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is a Change Control System?

A system for monitoring project progress

A system for managing changes to project deliverables and documentation

A system for managing project team members

A system for approving project budgets

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the primary purpose of a Change Control System?

To ensure that the project is completed on time

To ensure that the project stays within budget

To manage changes to project deliverables and documentation

To manage the project team's performance

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is not typically a part of a Change Control System?

A formal process for submitting change requests

A process for reviewing and approving changes

A system for tracking changes to project deliverables and documentation

A process for assigning blame for project delays

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the recommended time to establish a change control policy?

During the execution phase

During the planning phase

During the monitoring and controlling phase

During the closing phase

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Who evaluates changes that impact stakeholders and the project?

The project manager

The change control board

The project sponsor

The project team

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the purpose of establishing an emergency decision-making authority?

To speed up the change control process

To avoid involving stakeholders in the decision-making process

To ensure that decisions can be made promptly when necessary

To bypass the change control board

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the purpose of maintaining a change control log?

To track all changes that have been approved

To track all changes that have been requested

To track all changes that have been rejected

To track all changes that have been implemented

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?