MGT1201 Chapter 5

MGT1201 Chapter 5

University

20 Qs

quiz-placeholder

Similar activities

PA5 - Resistencia de Materiales (Minas)

PA5 - Resistencia de Materiales (Minas)

University

16 Qs

Be / Past Tense

Be / Past Tense

12th Grade - University

18 Qs

FINANCIAL MANAGEMENT

FINANCIAL MANAGEMENT

12th Grade - University

20 Qs

Kuiz PA 1 Sem 1 2021/22

Kuiz PA 1 Sem 1 2021/22

University

15 Qs

CSS- Quiz 2

CSS- Quiz 2

University

20 Qs

Kinship and Family in Borneo

Kinship and Family in Borneo

University

20 Qs

KuiZ ET622

KuiZ ET622

University

20 Qs

Purification & Types of water

Purification & Types of water

1st Grade - Professional Development

15 Qs

MGT1201 Chapter 5

MGT1201 Chapter 5

Assessment

Quiz

Other

University

Practice Problem

Easy

Created by

Khaiziliyah binti Khalid @ Khalil undefined

Used 4+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

20 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

10 mins • 1 pt

What is the primary purpose of defining "out of scope" items in a project?

To expand project deliverables

To prevent scope creep and manage stakeholder expectations

To increase the project budget

To eliminate the need for a WBS

2.

MULTIPLE CHOICE QUESTION

10 mins • 1 pt

Which element of the Triple Constraint is most directly impacted if a stakeholder requests additional features mid-project?

Time

Cost

Scope

Quality

3.

MULTIPLE CHOICE QUESTION

10 mins • 1 pt

In a WBS, a "work package" represents:

The final project report

The smallest assignable unit of work

A stakeholder meeting

A risk mitigation plan

4.

MULTIPLE CHOICE QUESTION

10 mins • 1 pt

Which estimation technique involves team members voting on task durations using cards?

Delphi

Timeboxing

Poker Planning

Top-down

5.

MULTIPLE CHOICE QUESTION

10 mins • 1 pt

A milestone in project management signifies:

A deliverable handed to the client

A checkpoint marking phase completion

A risk event

A budget revision

6.

MULTIPLE CHOICE QUESTION

10 mins • 1 pt

The "Validate Scope" process ensures:

All team members are paid on time

Deliverables meet agreed-upon criteria

The project budget is doubled

Stakeholders avoid all meetings

7.

MULTIPLE CHOICE QUESTION

10 mins • 1 pt

Which tool would best help visualize the hierarchy of deliverables in a project?

Gantt chart

Deliverable Structure Chart

Risk register

MOV statement

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?