Lesson-5 Support Project Team Performance
Authored by sudiyuwono wowo
Professional Development
Professional Development
23 Questions

AI Actions
Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...
Content View
Student View
1.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Which of the following represents a risk?
We have determined that our schedule is not going to meet the required deadline.
Due to a higher inflation rate, it is possible that future commodity prices will be 3 to 7% higher over the next 2 years, thus increasing the cost of the project.
There are not enough resources to complete the work on time.
The change in the prime rate has caused our funding source to be unable to provide the money we need in the upcoming project phase.
2.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
The product owner is unavailable to decide about a product feature. What is this considered?
Work request
Impediment
Backlog refinement
Priority
3.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Which of the following is a technique used by project teams to bring everyone together on a set reoccurring basis to share what may be blocking or impeding their work or plans?
Daily standup meeting
Iteration review
Retrospective
Project kickoff
4.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
Which of the following is the best example of a blocker?
The team cannot decide when to schedule the next iteration review.
The demonstration is not ready for the iteration review.
Clearance from another team to use content for the demo won’t be ready within the current iteration.
The demonstration fails in front of the product owner during the iteration review.
5.
MULTIPLE CHOICE QUESTION
1 min • 1 pt
What is the aim of a retrospective?
To blamestorm problems
To identify who is not helping on the team
To look back at all the work that was not completed
To identify what went well and what can be improved
6.
MULTIPLE SELECT QUESTION
1 min • 1 pt
Which two of the following are types of project metrics that may be appropriate for a given project? (Choose two)
Percentage of work completed
Defects
Subcontractor approvals
Process compliance
7.
MULTIPLE SELECT QUESTION
1 min • 1 pt
Which two of the following are objectives for running a retrospective? (Choose two)
Provide the stakeholders access to the team
Generate insights
Agree to one to two experiments to try to improve team performance
Get feedback on the product
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?
Similar Resources on Wayground
18 questions
CTO Plywood
Quiz
•
Professional Development
20 questions
Microsoft Excel
Quiz
•
KG - Professional Dev...
20 questions
LATIHAN SOAL 5 UP PPG PAUD 2021
Quiz
•
Professional Development
20 questions
Intro to UNCLOS
Quiz
•
Professional Development
21 questions
Class 7 review
Quiz
•
Professional Development
20 questions
AWS Most Popular Services
Quiz
•
Professional Development
18 questions
Change Management & Project Management PELINDO
Quiz
•
Professional Development
20 questions
Quiz 3 - SharePoint
Quiz
•
Professional Development
Popular Resources on Wayground
5 questions
This is not a...winter edition (Drawing game)
Quiz
•
1st - 5th Grade
25 questions
Multiplication Facts
Quiz
•
5th Grade
10 questions
Identify Iconic Christmas Movie Scenes
Interactive video
•
6th - 10th Grade
20 questions
Christmas Trivia
Quiz
•
6th - 8th Grade
18 questions
Kids Christmas Trivia
Quiz
•
KG - 5th Grade
11 questions
How well do you know your Christmas Characters?
Lesson
•
3rd Grade
14 questions
Christmas Trivia
Quiz
•
5th Grade
20 questions
How the Grinch Stole Christmas
Quiz
•
5th Grade