Management Procurement and Divided Contract Systems Worksheet

Management Procurement and Divided Contract Systems Worksheet

University

16 Qs

quiz-placeholder

Similar activities

Week 12 quiz CC & P

Week 12 quiz CC & P

University

15 Qs

Revolutions: Themes and Impacts Quiz

Revolutions: Themes and Impacts Quiz

10th Grade - University

11 Qs

FBC: Windows

FBC: Windows

University

12 Qs

Chapter 6: Energy and Matter Review

Chapter 6: Energy and Matter Review

University

20 Qs

Hot Water - PPT 4 - Instantaneous hot water heaters

Hot Water - PPT 4 - Instantaneous hot water heaters

12th Grade - University

21 Qs

Week 2 IMC Australian economy and construction

Week 2 IMC Australian economy and construction

University

15 Qs

UTS K3 Konstruksi

UTS K3 Konstruksi

University

15 Qs

Understanding the RIBA Design Stages

Understanding the RIBA Design Stages

University

20 Qs

Management Procurement and Divided Contract Systems Worksheet

Management Procurement and Divided Contract Systems Worksheet

Assessment

Quiz

Construction

University

Practice Problem

Medium

Created by

RYAN SUN

Used 5+ times

FREE Resource

AI

Enhance your content in a minute

Add similar questions
Adjust reading levels
Convert to real-world scenario
Translate activity
More...

16 questions

Show all answers

1.

MULTIPLE SELECT QUESTION

30 sec • 1 pt

Choose 3 management procurement systems

PM consultant

Senior project management

Management contractor

Construction management consultant

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Where does the management system sit in the divided contract approach?

Between the client and operating team

Between the developer and the client

Between the Architect and client

Between the contractor and maintenance team

3.

MULTIPLE SELECT QUESTION

30 sec • 1 pt

What are two main benefits from the divided contract approach?

Low risk for client

Overlap of maintenance and operation

Client control

Overlap of design and construction

4.

MULTIPLE SELECT QUESTION

30 sec • 1 pt

The divided contract approach is a mix between which two strategies

Design & build

Build/own/ transfer

Traditional

Cost plus

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Who could the client contract with in the divided approach?

Designer

Contractor

Subcontractors

All of the above

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Who takes most of the risk in the divided contract system

client

Consultant

Managing consultant

Subcontractors

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the primary purpose of client interaction with subcontractors

Safety concerns

Discounted prices

greater control

create good partnerships

Create a free account and access millions of resources

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?