Management Procurement and Divided Contract Systems Worksheet

Management Procurement and Divided Contract Systems Worksheet

University

16 Qs

quiz-placeholder

Similar activities

Pipes and Fittings, Plumbing Fixtures

Pipes and Fittings, Plumbing Fixtures

University

13 Qs

Week 3 quiz OUA SP2 CC&P

Week 3 quiz OUA SP2 CC&P

University

17 Qs

Governing Law Quiz

Governing Law Quiz

University

14 Qs

Week 4 Project life cycle IMC

Week 4 Project life cycle IMC

University

16 Qs

SHU Seminar Quiz 11.11.2024

SHU Seminar Quiz 11.11.2024

University

14 Qs

Chapter 7 contracts

Chapter 7 contracts

University

17 Qs

Week 1 IMC

Week 1 IMC

University

16 Qs

Understanding the RIBA Design Stages

Understanding the RIBA Design Stages

University

20 Qs

Management Procurement and Divided Contract Systems Worksheet

Management Procurement and Divided Contract Systems Worksheet

Assessment

Quiz

Construction

University

Hard

Created by

RYAN SUN

Used 1+ times

FREE Resource

16 questions

Show all answers

1.

MULTIPLE SELECT QUESTION

30 sec • 1 pt

Choose 3 management procurement systems

PM consultant

Senior project management

Management contractor

Construction management consultant

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Where does the management system sit in the divided contract approach?

Between the client and operating team

Between the developer and the client

Between the Architect and client

Between the contractor and maintenance team

3.

MULTIPLE SELECT QUESTION

30 sec • 1 pt

What are two main benefits from the divided contract approach?

Low risk for client

Overlap of maintenance and operation

Client control

Overlap of design and construction

4.

MULTIPLE SELECT QUESTION

30 sec • 1 pt

The divided contract approach is a mix between which two strategies

Design & build

Build/own/ transfer

Traditional

Cost plus

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Who could the client contract with in the divided approach?

Designer

Contractor

Subcontractors

All of the above

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Who takes most of the risk in the divided contract system

client

Consultant

Managing consultant

Subcontractors

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the primary purpose of client interaction with subcontractors

Safety concerns

Discounted prices

greater control

create good partnerships

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?