Project Management Quiz w3l2 - ITPMA2

Project Management Quiz w3l2 - ITPMA2

University

15 Qs

quiz-placeholder

Similar activities

1st Quiz

1st Quiz

University

14 Qs

Basics of Scrum

Basics of Scrum

University

12 Qs

Project Management Quiz

Project Management Quiz

University

10 Qs

Eventos Scrum - La planning

Eventos Scrum - La planning

University

11 Qs

Metodologías Ágiles

Metodologías Ágiles

12th Grade - University

10 Qs

Scrum & Kanban

Scrum & Kanban

University

15 Qs

LIBRO 1 - CAPÍTULO XIX  Gestión ágil de proyectos

LIBRO 1 - CAPÍTULO XIX Gestión ágil de proyectos

University

15 Qs

Revisão - Processos de Desenvolvimento de Software

Revisão - Processos de Desenvolvimento de Software

University

20 Qs

Project Management Quiz w3l2 - ITPMA2

Project Management Quiz w3l2 - ITPMA2

Assessment

Quiz

Information Technology (IT)

University

Easy

Created by

Stacey Byrne

Used 3+ times

FREE Resource

15 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

What is the main purpose of project planning?

To close the project

To monitor progress

To guide execution

To assign tasks

2.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Which document outlines the features and boundaries of a project?

Risk Register

Scope Statement

Team Contract

Milestone Report

3.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

What does a Gantt chart represent in project planning?

Budget allocation

Project schedule with dependencies and resources

Stakeholder engagement

Risk prioritization

4.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

What is the purpose of a Work Breakdown Structure (WBS)?

To monitor risks

To assign team roles

To break down project deliverables into manageable tasks

To document lessons learned

5.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

What is included in a Risk Register?

Team roles and responsibilities

Project timeline

List of prioritized risks

Final report

6.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

Which process group typically consumes the most resources?

Planning

Executing

Monitoring and Controlling

Closing

7.

MULTIPLE CHOICE QUESTION

45 sec • 1 pt

What is the purpose of a Milestone Report?

To track budget

To focus on completing major milestones

To assign tasks

To document stakeholder feedback

Create a free account and access millions of resources

Create resources
Host any resource
Get auto-graded reports
or continue with
Microsoft
Apple
Others
By signing up, you agree to our Terms of Service & Privacy Policy
Already have an account?