1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the first step in developing a project schedule?

Establishing the estimated start time

Identifying the critical path of activities

Calculating the latest times for each activity

Estimating the resources required for each activity

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following is NOT a type of resource mentioned in the text?

Materials

Facilities

Time

People

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does EF stand for in project scheduling?

Effective Finish

Early Finish

Estimated Finish

End Finish

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the purpose of calculating the earliest start time (ES)?

To identify the critical path

To determine the latest time an activity can start

To calculate the total duration of the project

To find the earliest time an activity can begin

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which of the following best describes total slack?

The maximum time an activity can take

The difference between the earliest and latest finish times

The total time required to complete the project

The time an activity can be delayed without affecting the project

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the critical path in project management?

The path with the least amount of slack

The path that has the most resources allocated

The longest path through the project network

The path that includes all activities

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the significance of negative slack?

It means the project is behind schedule

It indicates that the project is ahead of schedule

It suggests that resources are over-allocated

It shows that an activity can be delayed

Access all questions and much more by creating a free account

Create resources

Host any resource

Get auto-graded reports

Google

Continue with Google

Email

Continue with Email

Classlink

Continue with Classlink

Clever

Continue with Clever

or continue with

Microsoft

Microsoft

Apple

Apple

Others

Others

Already have an account?