1.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What does the acronym PERT stand for in project management?
Project Evaluation and Review Technique
Project Estimation and Resource Tracking
Programme Evaluation and Resource Technique
Programme Estimation and Review Tracking
2.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which project management methodology follows a linear, sequential approach where each phase must be completed before the next begins?
Kanban
Agile
Waterfall
Scrum
3.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In a Gantt Chart, what does each horizontal bar represent?
The cost of a task
The duration and schedule of a task
The number of team members assigned to a task
The priority level of a task
4.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
What is the primary purpose of a Kanban board in project management?
To calculate the critical path of a project
To estimate the total cost of a project
To visualise the flow of work and manage tasks in progress
To create a detailed timeline with dependencies
5.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In Critical Path Analysis (CPA), what is the "critical path"?
The most expensive sequence of tasks in a project
The longest sequence of dependent tasks that determines the minimum project duration
The shortest sequence of tasks that can be completed first
The sequence of tasks assigned to the most skilled team members
6.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
In a Precedence Table, what information is typically recorded for each task?
The task name, its duration, and its predecessor tasks
The task name, its cost, and the team member responsible
The task name, its priority, and its estimated completion date
The task name, its risk level, and its resource requirements
7.
MULTIPLE CHOICE QUESTION
30 sec • 1 pt
Which of the following is a key benefit of using a Gantt Chart in a digital support logistics project?
It automatically reassigns tasks when a team member is unavailable
It provides a clear visual overview of the project schedule and task dependencies
It calculates the exact cost of each task in the project
It eliminates the need for team communication during the project
Access all questions and much more by creating a free account
Create resources
Host any resource
Get auto-graded reports

Continue with Google

Continue with Email

Continue with Classlink

Continue with Clever
or continue with

Microsoft
%20(1).png)
Apple
Others
Already have an account?