Microsoft Project 2021 From Beginners to Advanced - Practical Sharing and Consolidation - Part 2

Microsoft Project 2021 From Beginners to Advanced - Practical Sharing and Consolidation - Part 2

Assessment

Interactive Video

Information Technology (IT), Architecture

University

Hard

Created by

Quizizz Content

FREE Resource

This video tutorial covers the practical aspects of managing a resource pool in project management. It explains how to work with a resource pool in both read-only and read-write modes, allowing for updates and modifications. The tutorial also discusses creating a master project for consolidated reporting and the process of unlinking resources from a shared pool. Additionally, it provides guidance on managing sub-projects and converting them into regular tasks, emphasizing the importance of maintaining correct dependencies.

Read more

7 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the primary purpose of a resource pool in project management?

To consolidate financial reports

To track project deadlines

To manage resource information across multiple projects

To store project files

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

When opening a resource pool in read-only mode, what can you do?

Delete resources

Make changes to resource pay rates

Run reports and view resource properties

Update assignments

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What happens when you open a resource pool in read-write mode?

You can change resource information like pay rates

Others can update the resource pool simultaneously

The resource pool becomes inaccessible to others

You can make changes to assignments

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the benefit of creating a master project file?

It enables running reports on all projects together

It allows for permanent consolidation of all projects

It simplifies project deadlines

It restricts user access to individual projects

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How can you stop a project from sharing resources with a resource pool?

Select 'Use own Resources' in the share resources option

Change the project deadline

Delete the resource pool

Close the project file

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is a key consideration when converting a sub-project to regular tasks?

It can be easily reversed

It automatically updates all related projects

It requires no changes to dependencies

It is not reversible

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Why is it recommended to take a backup before converting a sub-project to regular tasks?

To update the resource pool

To ensure data is not lost

To allow easy reversal of the conversion

To share the project with others