PMI-RMP Certification Training - Early, Iterative, and Emergent Identification

PMI-RMP Certification Training - Early, Iterative, and Emergent Identification

Assessment

Interactive Video

Information Technology (IT), Architecture, Business

University

Hard

Created by

Quizizz Content

FREE Resource

The video emphasizes the importance of early, iterative, and emergent risk identification in project management. Early identification helps manage uncertainty and allows for cost-effective risk responses. Iterative identification ensures risks are continuously assessed throughout the project lifecycle, while emergent identification allows for the recognition of new risks as they arise, ensuring they are managed promptly.

Read more

7 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Why is it crucial to identify risks early in a project?

Because it reduces the overall project cost.

Because uncertainty is highest at the beginning of a project.

Because it ensures the project is completed on time.

Because it eliminates all risks from the project.

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is a key benefit of iterative risk identification?

It allows for risk identification only at the start of the project.

It ensures that all risks are identified at the end of the project.

It helps in identifying risks that may arise later in the project.

It focuses only on financial risks.

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What can happen if risks are not identified iteratively?

All risks will be identified at the project's conclusion.

Risks that were not initially present may become issues.

The project will not require any changes.

The project will automatically succeed.

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

In the given example, what new risk emerged due to project delays?

Lack of resources.

Communication breakdown.

Increased project costs.

Ground freeze risk.

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Why is emergent risk identification important?

It allows risks to be identified only during formal reviews.

It limits risk identification to specific project phases.

It ensures risks are identified at any time during the project.

It focuses on identifying risks only at the project's start.

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How can emergent risk identification be integrated into project management?

By incorporating risk discussions into regular status meetings.

By discussing risks only during the project's final review.

By identifying risks only when a problem arises.

By limiting risk discussions to project managers only.

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is a potential consequence of not identifying a risk that emerges during a project?

The risk may become an issue if not identified.

The project timeline will not be affected.

The project will automatically adjust to the risk.

The risk will be eliminated without any action.