What is Float? And, What is Slack? in Project Management

What is Float? And, What is Slack? in Project Management

Assessment

Interactive Video

Business

12th Grade - University

Hard

Created by

Quizizz Content

FREE Resource

The video tutorial explains the concept of float and slack in project management, highlighting their importance in scheduling flexibility. It covers different types of float, including free float, total float, and project float, and their calculations. The critical path method is discussed, emphasizing that activities on this path have zero float. The tutorial concludes by explaining why float is crucial for risk management, prioritization, monitoring, and team morale.

Read more

7 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the primary purpose of float in project management?

To eliminate project risks

To increase project costs

To allow flexibility in scheduling

To reduce project scope

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How is free float calculated?

Latest start minus earliest start

Earliest start of successor minus earliest finish of prime

Total project time minus task time

Latest finish minus earliest finish

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What does negative float indicate in a project?

The project is ahead of schedule

The project has excess resources

The project is on schedule

The project will be delayed

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the critical path in project management?

The path with the least risk

The shortest path through a project network

The longest path through a project network

The path with the most resources

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Why is float important for team morale?

It ensures constant work without breaks

It increases the number of deadlines

It reduces pressure and allows for creative thinking

It eliminates the need for teamwork

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which activities should be prioritized in a project?

Activities with the highest cost

Activities with the least resources

Activities with zero float

Activities with the most float

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How can float help in risk management?

By allowing schedule flexibility to mitigate delays

By increasing project costs

By reducing the number of tasks

By eliminating all risks