PMP Certification Training - Manage Project Knowledge

PMP Certification Training - Manage Project Knowledge

Assessment

Interactive Video

Information Technology (IT), Architecture, Business

University

Hard

Created by

Wayground Content

FREE Resource

The video tutorial explains the Manage Project Knowledge process, focusing on using existing knowledge and creating new knowledge to meet project objectives and enhance organizational learning. It covers the importance of collaboration and trust, inputs like project documents and stakeholder information, tools and techniques such as expert judgment and information management, and outputs like lessons learned and process updates.

Read more

7 questions

Show all answers

1.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What are the two primary purposes of the Manage Project Knowledge process?

To hire new team members and allocate resources

To reuse existing knowledge and create new knowledge

To create a project timeline and budget

To develop a marketing strategy and sales plan

2.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Why is it important to create an environment of collaboration and trust in knowledge management?

To increase project costs

To motivate people to share knowledge

To ensure compliance with regulations

To reduce the number of team meetings

3.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

Which document provides information on effective practices in knowledge management?

Lessons learned register

Project charter

Risk management plan

Stakeholder analysis

4.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What role do expert judgments play in the Manage Project Knowledge process?

They provide specialized knowledge or training

They help in creating project timelines

They are used to allocate project resources

They are used to develop marketing strategies

5.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

How do information management tools and techniques assist in the Manage Project Knowledge process?

By creating and connecting people to information

By reducing project costs

By increasing the number of team members

By developing new marketing strategies

6.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What is the purpose of the lessons learned register in the Manage Project Knowledge process?

To develop a project timeline

To capture and update knowledge throughout the project

To document project risks

To track project expenses

7.

MULTIPLE CHOICE QUESTION

30 sec • 1 pt

What happens to the project management plan as a result of the Manage Project Knowledge process?

It remains unchanged

It is replaced with a new plan

It is discarded

It may be updated