1.
Promptly issuing the Certificates of Payment and the Final Certificate of Completion is a responsibility of the Architect to whom?
a)
client
b)
public
c)
contractor
d)
manufacturer
2.
Which is an unethical action with respect to the Architect's responsibility to the people?
a)
Seek constructive civic service
b)
Take part in paid endorsement of building material
c)
Shares technical information
d)
Promote professional organization
3.
This shall be issued by the Owner to the Contractor following the execution of the Contract Agreement.
a)
Contract Time
b)
Notice to Proceed
c)
Contract Sum Breakdown
d)
Schedule of Completion
4.

What pre-design service involves problem seeking process which will lead to the statement and identification of both horizontal and vertical requirements?

a)

What pre-design service involves investigating, identifying and documenting the needs of the client for use in the design of the project?

b)

Space Management Studies

c)

Architectural Programming

d)

Site Selection and Analysis.

5.
Invitations issued to prospective bidders, giving information as to the nature of the proposed project, conditions for the issuance of contract documents, date of bidding, and estimated cost or information that would give the Contractor a general idea of the magnitude and extent of the project.
a)
Instruction to bidders
b)
Invitation to bid
c)
Bid bulletin
d)
Written notice
6.
Information, advice or notification pertinent to the project delivered in person or sent by registered mail to the individual. firm or corporation at the last known business address of such individual, firm or corporation.
a)
Instruction to bidders
b)
Invitation to bid
c)
Bid Bulletin
d)
Written notice
7.
A method of compensation frequently used where there is a continuing relationship on a series of projects.:
a)
Multiple of direct personnel expense
b)
Percentage of construction cost
c)
Professional fee plus expenses
d)
Lump sum or fixed fee
8.
A method of compensation that is flexible, easy to apply and is related to the size and the type of the project.
a)
Multiple of direct personnel expense
b)
Percentage of construction cost
c)
Professional fee plus expenses
d)
Lump sum or fixed fee 
9.
The multiple of personnel direct expense is applicable only to what type of work?.
a)
Research
b)
Creative work
c)
Government projects
d)
Ocular site inspection
10.
A method of selection for an Architect most often used by an individual person undertaking a relatively small project
a)
Comparative selection
b)
Design competition
c)
Bidding
d)
Direct selection
11.
Duly notarized written contract or equivalent public instrument stipulating the scope of services and guaranteeing compensation of such services?
a)
a. Sevice agreement
b)
b. General conditions
c)
c. Surety
d)
d. Project manual
12.
What part of Architect’s services is architectural programming?
a)
a. Schematic design
b)
b. Pre-design 
c)
c. Design Development
d)
d. Contract Documents
13.
What official body formulates rules and regulations relating to signing / sealing of drawings, specifications and other documents registered by the architect?
a)
a. United Architects of the Philippines
b)
b. Commission on Higher Education
c)
c. Board of Architecture
d)
d. Office of the Building Official
14.
In the Architect’s Code of Ethics, to whom does the architect have responsibility to provide for arbitration as a method for settlement of disputes?
a)
a. Contractor
b)
b. Public
c)
c. Manufacturers/dealers
d)
d. Client
15.
One of the methods of compensation for architectural service is based on technical hours and expenses & made by adding all costs of technical services (man-hours time rate). A multiplier is used to take care of overhead & profit. This method, however, is applicable only to non-creative work & aspects of pre-design services & supervision work. What is this method called?
a)
a. Per diem plus reimbursable expenses
b)
b. Per diem plus reimbursable expenses
c)
c. Mixed methods of compensation
d)
d. Multiple of direct personal expenses
16.
Under what phase of design services does the architect prepare complete construction drawings and specifications on materials/construction methods?
a)
a. Schematic Design 
b)
b. Contract documents
c)
c. Construction
d)
d. Design development
17.
Architect shall at no time act in a manner detrimental to the best interest of what? 
a)
a. Architectural Organization
b)
b. Architectural Practice
c)
c. Architectural Profession
d)
d. None of the above
18.
Architect shall refrain from taking part in paid advertisement endorsing any materials of?
a)
a. His Architectural Works
b)
b. Construction Products
c)
c. Construction or Building Equipment
d)
d. Done by his Office
19.
The Architect's _____ of purpose must be beyond reproach; he/she acts as professional adviser to his/her Client and his/her advice must be unprejudiced;
a)
a. Honesty
b)
b. Integrity
c)
c. Professional
d)
d. Main Line
20.
Under General Provisions, The Architect is engaged in a profession which carries with it grave responsibilities to whom?
a)
a. Owner / Client
b)
b. Government
c)
 c. Public
d)
d. PRC
21.
This shall be issued by the Owner to the Contractor following the execution of the Contract Agreement?
a)
a. Contract time
b)
b. Notice to proceed
c)
c. Contract Sum Breakdown
d)
d. Schedule of completion
22.
What method of compensation is most suitable for compensating the Architect's services for the pre-design phase?
a)
a. Multiple of direct personnel expense
b)
b. Lump sum or fixed fee
c)
c. Per-diem plus reimbursible expenses
d)
d. Professional fee plus expenses
23.
Which is an unethical action with respect to the Architect's responsibility to the people?.
a)
a. Seek constructive civic service
b)
b. Take part in paid endorsement of building material
c)
c. Shares technical information
d)
d. Promote professional organization
24.
What pre-design service involves investigating, identifying and documenting the needs of the client for use in the design of the project?
a)
a. Economic Feasibility Studies
b)
b. Space Management Studies
c)
c. Architectural Programming
d)
d. Site Selection and Analysis
25.
Which of the following is a responsibility of the Architect in the Construction Phase of the Regular Design Services?
a)
a. Makes periodic visits to the site
b)
b. Makes exhaustive on-site supervision
c)
c. Be held responsible for failure of contractor to carry out work
d)
d. Prepares shop drawings
26.
Promptly issuing the Certificates of Payment and the Final Certificate of Completion is a responsibility of the Architect to whom?
a)
a. client
b)
b. public
c)
c. Contractor
d)
d. Manufacturer
27.
Which is an unethical action with respect to the Architect's responsibility to his colleagues and subordinates?
a)
a. Provides free professional service for a charitable project
b)
b. Donates to obtain advantage in a religious project
c)
c. Undertakes a commission from another Architect duly notified
d)
d. Serving as professional adviser, accepts employment as Design Architect for a competition project.
28.
Which activity is included in the Contract Document Phase of the Architect's Regular Design Services?
a)
a. Prepares forms for contract documents
b)
b. Prepares forms for contract letting and bidding
c)
c. Assists the Owner in obtaining proposals from contractors
d)
d. Checks samples, schedules and shop drawings
 
29.
What percentage of the Architect's Basic Fee is for the liability of the Architect under the Civil Code?
a)
a. 5%
b)
b. 10%
c)
c. 15%
d)
d. 20%
30.
Most expensive and time-consuming method of selecting the Architect?
a)
a. Comparative selection
b)
b. Design competition
c)
c. Mixed method
d)
d. Direct selection
31.
A method of compensation that is flexible, easy to apply and is related to the size and the type of the project?
a)
a. Multiple of direct personnel expense
b)
b. Percentage of construction cost
c)
c. Professional fee plus expenses
d)
d. Lump sum or fixed fee
32.
A method of selection for an Architect most often used by an individual person undertaking a relatively small project?
a)
a. Comparative selection
b)
b. Design competition
c)
c. Bidding
d)
d. Direct selection
33.
A method of compensation frequently used where there is a continuing relationship on a series of projects?
a)
a. Multiple of direct personnel expense
b)
b. Percentage of construction cost
c)
c. professional fee plus expenses
d)
d. Lump sum or fixed fee
34.
A method of compensation that represents a risk situation to the Architect since his costs may exceed the agreed amount?
a)
a. Multiple of direct personnel expense
b)
b. Percentage of construction cost
c)
c. Professional fee plus expenses
d)
d. Lump sum or fixed fee
35.
State-owned Architecture Schools exempted from being ______by the Government Architecture Degree? 
a)
a. Technically
b)
b. Legally
c)
c. Professionally
d)
d. current
36.

The Architect is selected for the project by _____ method?

a)

a. Direct

b)

b. Comparative

c)

c. Architectural Design Competition

d)

d. All listed

37.
The ____regulates the practice of the Profession of Architecture in the Philippines?
a)
a. RA 8266
b)
b. RA 8256
c)
c. RA 9246
d)
d. RA 9266
38.
The client can select an architect for a project through ____?
a)
a. Bidding
b)
b. Advertisement
c)
c. Referral by an Architect
d)
d. Proposal
39.
The Architect is selected for a project by _____ method?
a)
a. Bidding
b)
b. advertisement
c)
c. Design Competition
d)
d. Proposal
40.
Architects are people who are registered and _____ qualified to practice architecture?
a)
a. Technically
b)
b. Legally
c)
c. Professionally
d)
d.Current
41.
Architect may acquire a project through _____.
a)
a. an invitation
b)
b. a newspaper advertisement
c)
c. Bidding
d)
d. Facebook
42.
Architect's license may be suspended due to?
a)
a. No projects done
b)
b. Non-payment of cues
c)
c. Non-renewal
d)
d. Fraudulent acts
43.
Participants in an architectural design competition should be?
a)
a. artists
b)
b. Civil engineer
c)
c. students
d)
d. Registered Architects
44.
The____ will incorporate a space program in offering a design solution?
a)
a. Feasilbility Studies
b)
b. Space Programming
c)
d. Architectural Research
d)
d. Architectural Programming
45.
The ____ entails the conduct of primary and secondary search for facts as basis for future conclusion to be use in decision making in the Architectural Project?
a)
a. Architectural Studies
b)
b. Architectural data collection
c)
c.Technical Research
d)
d. Architectural Research
46.
The detailed analysis that will determine the viability of a proposed development?
a)
a. Feasibility studies
b)
b. Design Analysis
c)
c. Project Viability Studies
d)
d. Viability Analysis
47.

The ____ is the formulation of site criteria to determine the most appropriate for a proposed project?

a)

a. Site Planning

b)

b. Site Selection and analysis

c)

c. Site Comparison

d)

d. Site utilization and land use

48.
The ____ are studies involving the studies of secondary information as in-puts in Architectural Design?
a)
a. Programming
b)
b. Matrix Analysis
c)
c. Architectural Research
d)
d. Pre-Feasibility Studies
49.
SPP Documents replaced the ____?
a)
a. 1975 UAP Documents
b)
b. 1979 PIA Documents
c)
c. 1979 UAP Documents
d)
d. IAPOA Documents
50.
SPP Document no. 205 is?
a)
a. Pre-Design Services
b)
b. Regular Design Services
c)
c. Construction Services
d)
d. Post-Construction Services
51.

It involves studies for the appropriate utilization of land?

a)

a. Site Studies

b)

b. Site Planning

c)

c. Site Utilization and land-use

d)

d. Non-listed

52.
SPP Document no. 204 is?
a)
a. Pre-Design Services
b)
b. Regular Design Services
c)
c. Post-Construction Services
d)
d. Full time construction supervision
53.
Government Agency which regulates the practice of Architecture?
a)
a. UAP
b)
b. CHED
c)
c. PRC
d)
d. SEC
54.
Architect should register with the____in order to qualify to practice Architecture?
a)
a. PRC
b)
b. IAPOA
c)
c. LGU
d)
d. all listed
55.
For Non creative projects, the architect is compensated on the basis of?
a)
a. % of Construction Cost
b)
b. Multiple of Direct Personnel Expenses
c)
c. Salary
d)
d. Fixed Fee
56.
The ____can order changes in the construction based on technicalities only?
a)
a. Owner
b)
b. Architect
c)
c. Consultant
d)
d. Contractor
57.
The Architect has a duty to Himself, Country & ____? 
a)
a. UAP
b)
b. IAPOA
c)
c. GOD
d)
d. Non-listed
58.
In a typical owner-general contractor agreement, who is responsible for the payment of insurance for personal injury and to property?
a)
a. Architect
b)
b. Owner
c)
c. Project Manager
d)
d. Contractor
59.

SPP doc 206?

a)

a. Complete Services

b)

b. Full Architectural Services

c)

c. Comprehensive Architectural Services

d)

Non-listed

60.
Construction Management Services
a)
a. SPP 204a
b)
b. SPP 204b
c)
c. SPP 205
d)
d. Non-listed
61.

Specialized Architectural Services

a)

a. SPP Doc. 203

b)

b. SPP Doc. 205

c)

c. SPP Doc. 206

d)

d. SPP Doc. 207

62.
Comprehensive Architectural Services
a)
a. SPP Doc 204
b)
b. SPP Doc 205
c)
c. SPP Doc 206
d)
d. SPP Doc 207
63.

Under which phase of Regular design services the Architect prepares an initial statement of probable construction cost.

a)

Project Definition Phase

b)

Contract Document Phase

c)

Bidding or Negotiation Phase

d)

Construction Phase

64.
Most expensive and time-consuming method of selecting the Architect.
a)
Comparative selection
b)
Design competition
c)
Mixed method
d)
Direct selection
65.
A method of compensation that represents a risk situation to the Architect since his costs may exceed the agreed amount.
a)
Multiple of direct personnel expense
b)
Percentage of construction cost
c)
 Professional fee plus expenses
d)
Lump sum or fixed fee
66.
Which component is not considered in the formulation of the Master Development Plan under the Comprehensive Planning Services?
a)
Site Development
b)
Legal and Administrative
c)
 Economic
d)
Transport
67.
Under what phase of design services does the architect prepare complete construction drawings and specifications on materials/construction methods?
a)
Schematic design
b)
Contract documents
c)
Construction
d)
Design development
68.
One of the methods of compensation for architectural service is based on technical hours and expenses & made by adding all costs of technical services (man-hours time rate). A multiplier is used to take care of overhead & profit. This method, however, is applicable only to non-creative work & aspects of pre-design services & supervision work. What is this method called?
a)
Per diem plus reimbursable expenses
b)
Professional fee plus expenses
c)
Mixed methods of compensation
d)
Multiple of direct personal expenses
69.
What official body formulates rules and regulations relating to signing / sealing of drawings, specifications and other documents registered by the architect?
a)
United Architects of the Philippines
b)
Commission on Higher Education
c)
Board of Architecture
d)
Office of the Building Official
70.
When were the 3 architectural organizations integrated into one association of architects called UAP?
a)
1972
b)
1975
c)
1976
d)
1978
71.
What is the general basis of the Architect’s minimum basic fee?
a)
Architect’s professional standing in the community
b)
Owner’s offer
c)
 Type of structure
d)
Project construction cost
72.
What part of the Architect services is space/management studies?
a)
Contract documents
b)
Pre-design
c)
Design development
d)
 Schematic design
73.

Methods of selecting and Architect

a)

ADI

b)

Component Selection

c)

Direct Selection Competition

d)

Recomendation

74.

This type of selection is used when undertaking a relatively small project. The Client selects his Architect on the basis of recommendation of another Architect.

a)

Comparative Selection

b)

Invitation

c)

Direct Selection

d)

Architectural Design Competition

75.

This type of selection may be conducted by committees representing institutions, corporations or public agencies.

a)

Direct Selection

b)

Comparative Selection

c)

Architectural Design Competition

d)

Invitation

76.

This type of selection is used for civic or monumental projects.

a)

Invitation

b)

Comparative Selection

c)

Direct Selection

d)

Architectural Design Competition

77.

Multiple of Direct Personnel Expenses:

Reimbursable expenses such as transportation, housing and living allowance of Consultant, transportation, per diem, housing and living allowance of local consultants and technical staff if assigned to places over________.

a)

50km

b)

150km

c)

100km

d)

200km

78.

METHOD OF COMPENSATION:

The SPP provides for more than one method of compensation on a project. Each project should be examined to determine the most appropriate and equitable method of compensation.

a)

Mixed Methods of Compensation

b)

Multiple of Direct Personnel Expenses

c)

Professional Fee Plus Expenses

d)

Method of Compensation

79.

METHOD OF COMPENSATION:

This method of compensation is frequently used where there is continuing relationship involving a series of projects.

a)

Mixed Methods of Compensation

b)

Lump Sum or Fixed Fee

c)

Professional Fee Plus Expenses

d)

Multiple of Direct Personnel Expenses

80.

The Architect can render services in any of the following ways:

a)

Individual Architect / Architect’s Own Staff / By Association, Consultation or Networking

b)

Independent Architect / Architect’s Own Staff / By Association, Consultation or Networking

c)

Individual Architect / Owner's Own Staff / By Association, Consultation or Networking

d)

Individual Architect / Architect’s Own Staff / By Association, Company or Networking

81.

MANNER OF PROVIDING SERVICES:

After the initial meeting / conversation / correspondence with the Client, the Architect must submit his proposal for pre-design services, stating the following: Manner of Payment, Scope of Work, Other Conditions of Services and ___________.

a)

Contractor's responsibilities

b)

Owner’s Responsibilities

c)

Feasibility studies

d)

Architect's responsibilities

82.

Under Pre-design services, the Architect states the project terms of reference (ToR) including the concept, objectives and other necessary requirements to bid out architectural services (whether public or private).

a)

Space Management Studies

b)

Design Brief Preparation

c)

Space Planning

d)

Site Utilization and Land-Use Studies

83.

Republic Act No. 9266 was published on?

a)

March 17, 2004

b)

March 14, 2004

c)

April 17, 2004

d)

April 14, 2004

84.

RA 9266:

ARTICLE I - General Provision

"Section 1"

a)

Short Title

b)

Statement of Policy

c)

Definition of Terms

d)

Creation and Composition of the Professional Regulatory Board

85.

RA 9266:

ARTICLE I - General Provision

"Section 2"

a)

Short Title

b)

Statement of Policy

c)

Definition of Terms

d)

Creation and Composition of the Professional Regulatory Board

86.

RA 9266:

ARTICLE I - General Provision

"Section 3"

a)

Short Title

b)

Statement of Policy

c)

Definition of Terms

d)

Creation and Composition of the Professional Regulatory Board

87.

RA 9266:

ARTICLE IV - PRACTICE OF ARCHITECTURE

"Section 38"

a)

Limitation to the Registration of a Firm, Company, Partnership, Corporation or Association

b)

Coverage of Temporary/Special Permits

c)

Liability Insurance of a Person or Entity Allowed to Practice under a Temporary/Special Permit

d)

Collection of Professional Fees

88.

RA 9266:

ARTICLE V - Final Provisions

"Section 41"

a)

Integration of the Architecture Profession

b)

Implementing Rules and Regulations

c)

Appropriations

d)

Act Not Affecting Other Professionals

89.

RA 9266:

ARTICLE V - Final Provisions

"Section 44

a)

Enforcement of the Act

b)

Separability Clause.

c)

Repealing Clause

d)

Effectivity

90.

The Architect in this area of practice undertakes a scientific study on the built environment’s well being, which allows the Architect to focus on the ways in which the building/structure can best maintain itself and prolong its life in a cost-efficient manner, and finally provide recommendations to the Owner/ Client.

a)

Architectural Research Methods

b)

Historic and Cultural Heritage Conservation and Planning

c)

Forensic Architecture

d)

Special Building/ Facility Planning and Design