Font size
WorksheetsAC Mock Exam
Total questions: 100
Worksheet time: 54mins
Which of the following documents is used for correspondence between the architect or owner and the contractor?
job diary
memorandum
construction report
formal business letter
Which of the following documents is used for correspondence between the home office and the job site?
job diary
memorandum
construction report
formal business letter
What is the best time to distribute the working agenda to the participants of a meeting?
as a follow-up to the meeting
at the beginning of the meeting
about one day after the meeting
about one day prior to the meeting
Which document describes the suggested agenda for the preconstruction meeting?
general conditions
general requirements
technical specifications
supplementary conditions
What is the best time to distribute the meeting minutes to the participants?
at the beginning of the meeting
about one day after the meeting
about one hour prior to the meeting
about one day prior to the meeting
Which of the following descriptions are the primary content items for the meeting minutes?
to, from, project, date, time, place, subject, and schedule
purpose, specific objectives, time frame, topical headings in paragraph, role of each attendee
clear and measurable objectives, attendance, role of each attendee and their expertise
attendance, topical headings, brief notes on what was discussed in paragraph form, who is assigned to action items, completion status
Which of the following statements is true about the use of texting as a means of communicating in the construction industry?
a means of easily and effectively documenting communication
appropriate for clarifying but not for formal direction
should be completely avoided in construction
acceptable for communication if specifically allowed in the contract
What is the best way for a contractor to get formal clarification on an apparent discrepancy found on the plans?
change order proposal
RFI
addressed in a meeting agenda
any communication as long as each party completely understands the message and direction
What are the leadership skills needed to conduct a productive meeting?
planning, probing questions, responding critically, and decision making
planning, timing, coordinating, probing, responding critically, and following up
listening attentively, responding constructively, soliciting all ideas, and matching decision making to the situation
coordinating, listening selectively, responding critically, soliciting supportive ideas, and adjusting decision making to the situation
Which of the following is not commonly discussed at monthly owner/architect/contractor progress meetings?
outstanding RFIs
quality control
project schedule
pending subcontractor change orders
What is a listener’s retention percentage of an oral conversation?
10%
50%
60%
90%
Which of the following communication methods is the most effective in knowing that the communication has been understood?
The sender should ask closed-ended questions and tell the receiver twice.
The sender should ask open-ended questions and make them speak.
The sender should ask how they feel and their attitude toward the activity.
The sender should tell them what to do and get them back to work quickly.
Which of the following is the best example of an open-ended question?
Do you understand what work is supposed to be completed?
Do you know which shovel to get me from the tool shed?
What steps are you going to take to complete the activity?
How do you feel about completing the activities assigned?
Which source or organization promotes a uniform organizational system for categorizing construction materials, specifications, and documentation into divisions and sections for projects?
International Building Code
Underwriters Laboratories
Construction Specifications Institute
American Society for Testing Materials
Assume you have a simple beam 16 ft long supported on each end by R1 and R2. There is a concentrated load of 900 lb that is 4 ft from R2. Reaction R1 is pinned 12 ft from the load. Reaction R1 is 225 lb and R2 is 675 lb. What is the maximum bending moment in pounds per foot?
900
1,800
2,700
3,600
Assume that you are pouring a wall that is 151 ft 4 in. long, 14 ft high and, 1 ft 4 in. thick. The crew’s daily placement rate is 375 cy per 8-hr day. How many hours will it take to complete the wall?
0.3
2.2
27.0
58.8
Using the average soil weights from the table in Figure 1, what is the swell percentage of a loam soil?
8.3%
23.8%
31.9%
81.0%
Using the psychrometric chart provided in Figure 2, what is the enthalpy of 1 lb of air given a dry bulb temperature of 75º F and a relative humidity of 50%?
14 BTUs
28 BTUs
54 BTUs
64 BTUs
The owner wants to fast-track a construction project. Which project delivery system best supports this process?
partnering
design-bid-build
CM agency
design-build
A contract is entered into in which the design and scope are undefined and the owner agrees to pay for all direct labor, materials, and equipment, plus an agreed upon fee to the contractor for their services. What is this type of contract called?
cost plus
turnkey
unit price
lump sum
A contract is entered into in which the owner holds a contract with the architect and each trade contractor. In addition, the owner holds a contract with a management service company to perform the trade coordination, cost control, and scheduling services. What is this project delivery method called?
partnering
joint venture
design-build
construction management
. Which legal entity is considered perpetual?
partnership
corporation
joint venture
sole proprietorship
Under which municipal law are corporations formed?
city
state
federal
municipal
. Which law establishes basic rules governing the sale of goods used to establish a purchase order?
Davis Bacon Act
Uniform Commercial Code
National Labor Relations Act
Uniform Transportation Code
Which graphical measurement tool is a bar chart that displays a frequency distribution?
histogram
Pareto chart
pie chart
fishbone chart
Which of the following principles of law states that if the prime contractor reasonably relies on the promise or price of the subcontractor to its detriment, then the subcontractor must be held to its promise to avoid harm to the prime contractor even though a signed contract between the contractor and subcontractor does not exist at the bidding phase of a project?
consideration
legal purpose
promissory estoppel
equitable adjustment
At which point in time must the ownercontractor agreement be provided to each prospective subcontractor bidder?
at the bid opening
during the bidding phase of the project
at the signing of the owner-contractor agreement
before the signing of the owner-contractor agreement
Using the financial statements provided in Figures 3a and 3b, what is the working capital for this company at the end of the year?
$176,177
$733,154
$1,463,403
$1,633,389
Using the financial statements provided in Figures 3a and 3b, what is the current ratio?
0.47
1.00
2.07
4.36
Using the financial statements provided in Figures 3a and 3b, what is the quick ratio (acid test)?
0.23
0.48
1.00
2.07
Which CSI division contains technical information on structural steel?
01
03
05
15 and 23
Which CSI division is considered the technical specifications?
00
01
01–49
02–49
Which CSI division contains the bidding requirements for a project?
00
01
01–49
02–49
Which part in the CSI technical specifications provides the contractor information about how the work is to be executed, including approved installation procedures?
Part 1
Part 2
Part 3
Part 4
The technical specifications reference ASHRAE as a publisher of numerous technical standards. What does the acronym ASHRAE stand for?
American Steel Housing Rating Association of Engineers
Associated Structural Hoists Rating Association of Engineers
American Society for Heating, Refrigerating and Air Conditioning Engineers
Associated Society for Home Rating Air Equipment
Which party is normally responsible for designing the temporary structures?
owner
engineer of record
contractor/vendor
architect
Which of the following systems is designed to carry the total vertical load of a structure?
piling
cofferdam
timber shoring
cribbing and tiebacks
Which piece of equipment is most efficient for compacting granular soils, such as sand, gravel, and crushed stone?
backhoe
sheepsfoot
smooth wheel roller
wheel tractor scraper
Using the information provided in Figure 4, how many layers or mats of reinforcement are required for concrete beam 1B1?
1
2
12
24
Using the information provided in Figure 5, where is AHU-1 located?
Lower Level
Prayer Room 205
Sanctuary Room 202
Mechanical Room 107
Which document notifies the contractor of the forms, content, and procedures for submitting the bid proposal?
general conditions
general requirements
instructions to bidders
supplementary conditions
Which party has the design liability for a prescriptive specification?
owner
contractor
architect/engineer
code official
A specification reads as follows: “Furnish, install, operate, and maintain all necessary pumping equipment for dewatering the various parts of the work and for maintaining free of water the foundations and trenches as required for construction operations.” Which type of specification is this?
proprietary specification
performance specification
combination specification
descriptive or design specification
The contractor submits a bid for $1,303,071 with the appropriate forms. They receive a notice of award letter indicating that their bid has been selected. The contractor decides not to accept the contract. Which of the following statements is a likely outcome?
They will lose the amount of their bond premium.
They will lose the amount of their bid bond face value.
As long as the letter or contract has not been signed they can withdraw without ramifications.
They will lose the amount of their performance bond face value.
Using the bond premium schedule below, what is the bond premium for a $2,755,000 project?
First $5,000 = $12.00/$1,000
Next $2M = $6,000 + $7.25/$1,000
Next $2.5M= $20,500 + $5.75/$1,000
A. $19,974
$45,373
$55,974
$66,341
What does the R.S. Mean’s unit of measure abbreviation MBF stand for?
100 board feet
1,000 board feet
1 million feet
1 million board feet
The plans call for the contractor to drive, pull, and salvage steel sheet piling 15 ft deep. The estimated quantity is 12,000 sq ft of contact area (SFCA). Given the crew makeup as shown in Figure 6, an 8-hr workday, and a crew daily output of 545 SFCA, how many total work hours are expended per day?
28
32
60
100
The plans call for the contractor to drive, pull, and salvage steel sheet piling 15 ft deep. The estimated quantity is 12,000 sq ft of contact area (SFCA). Given the crew makeup as shown in Figure 6, an 8-hr workday, and a crew daily output of 545 SFCA, what is the productivity rate expressed in work hours per unit (Whr/Unit)?
0.059
0.110
9.083
17.031
Given a rectangular cofferdam that is 60 ft wide × 100 ft long and 10 ft deep and enclosed with a 3-ft toe, how many total SFCA are required for the sheet piling?
3,200
4,160
6,000
60,000
Given the information provided in Figure 7 for a rectangular cofferdam that is 60 ft wide × 100 ft long and 10 ft deep and enclosed with a 3-ft toe, approximately how many total board feet (BF) are needed for all of the cofferdam components, including waste?
16,164
22,826
25,565
27,229
Using the information provided in Figures 8a and 8b, how many cubic yards of concrete are needed for the walls (excluding foundation and slab)?
101
120
135
155
Using the information provided in Figures 8a and 8b, how many bank cubic yards of soil must be excavated and removed? Assume the existing grade is 204 ft and that excavated soil is being used for backfilling.
40
350
1,070
9,633,601
Using Figure 9a what is the budgeted unit work hours in work hours per unit for the column forms?
0.045
0.171
0.241
5.838
Using Figure 9a what is the weekly unit work hours in work hours per unit for the column forms?
0.007
0.195
4.919
5.118
Using the information provided in Figure 9a what is the to date unit work hours in work hours per unit for the column forms?
0.011
0.241
3.821
4.148
Using the information provided in Figure 9a what are the total earned work hours for the column forms?
19
27
465
2,387
Using the information provided in Figure 9a what is the total projected work hours at completion for the column forms?
27
104
602
2,472
Using the information provided in Figure 9a what is the projected gain/loss in work hours for the column forms?
(174)
325
1,897
2,396
Using the information provided in Figure 9b what is the budgeted unit cost in dollars per unit for the concrete footings?
0.047
21.45
137.25
256.00
Using the information provided in Figure 9b what is the week labor unit cost in dollars per unit for the concrete footings?
0.70
1.43
3.14
14.60
Using the information provided in Figure 9b what is the to date unit cost in dollars per unit for the concrete footings?
0.32
3.14
20.13
5,125.00
Using the information provided in Figure 9b what is the total projected cost at completion for the concrete footings?
81.41
803.84
5,150.72
10,615.00
. Using the information provided in Figure 9b what is the projected gain/loss in dollars for the concrete footings?
(110)
(4,685)
339
5,452
Using the information provided in Figure 9c what is the current projection for the quantities of piles in vertical linear feet (VLF)?
680
5,300
5,980
6,700
Which statement is true about the critical path?
is the shortest string of activities through the schedule
is the longest string of activities through the schedule
has zero total float but possibly some free float in the activities
includes all activities that are impossible to compress their duration any further
. How is free float defined?
the amount of slack in a node
the amount of slack between activities
the amount of slack within a series of activities
the amount of slack accumulated throughout the logic network
Which types of activities are considered first when compressing the length of a project?
zero float and least cost to compress
zero float and highest cost to compress
highest floats and least cost to compress
highest floats and highest cost to compress
How is the term fast tracking defined in construction?
planning and scheduling the design
overlapping execution of the construction activities
finalizing the design and procurement before construction begins
overlapping execution of the design, procurement, and construction
What is the name of the term for shifting the activities within their available free floats to produce a uniform workforce and reduce the maximum resource usage requirements?
crashing
crew utilization
resource leveling
time-scaled networking
What is the best source for developing the list of activities for the logic network and schedule?
general requirements
technical specifications
financial reports and balance sheets
estimate and earned work hour report
How is total float defined?
the amount of slack in a node
the amount of slack within an activity
how much a series of activities can be delayed without delaying a project
the amount of slack accumulated throughout the logic network
What is the primary reason the courts disfavor bar chart schedules?
They do not display the activities’ time scale.
They do not show the activity descriptions.
They do not show the interrelationship of activities or the float within activities.
They are too complicated for most members outside the project team to understand.
Using the information provided in Figure 10, what is the total number of days to complete this sequence of activities?
13
14
18
31
. Using the information provided in Figure 10, what are the critical activities for this logic network?
B, G
A, C, F
A, D, E, G
A, C, F, G
Using the information provided in Figure 10, what is the total float for activity B?
0
1
2
8
Using the information provided in Figure 10, what is the free float between activities B and G?
0
2
4
6
The Safety Standards utilize the abbreviation 29 CFR Part 1926. What does the acronym CFR stand for?
Code of Federal Register
Code of Federal Regulations
Construction Federal Register
Construction Federal Regulations
Which part of the OSHA Standards is designated for record keeping?
5(a)(1)
1904
1910
1926
According to OSHA, which document must the supervisor complete immediately after an accident by describing the accident in detail?
insurance forms
OSHA’s Summary of Work-Related Injuries and Illnesses (Form 300A)
OSHA’s Log of Work-Related Injuries and Illnesses (Form 300)
OSHA’s Injury and Illness Incident Report (Form 301)
When and where must a project’s OSHA Summary of Work-Related Injuries and Illnesses (Form 300A) be posted?
all year long and easily accessible to all employees at the job site
all year long and in the project manager’s office at the home office
February 11–April 30 and accessible to all employees at the job site
for three months and in the employees’ break room at the home office
According to OSHA, what is the name of the violation where the firm or designated person is aware that a hazardous condition exists, knows that the condition violates a standard, and makes no effort to eliminate the safety hazard?
willful violation
serious violation
de minimis violation
other-than-serious violation
The pipefitting subcontractor is required to lay pipe in a trench that is 10 ft deep and 3 ft wide with vertical walls and no sloping or other protection. The trench was dug by the excavator. The general contractor supervised the work but had no employees in the trench. The concrete subcontractor told the general contractor and excavator that the trench needed to be sloped or shored before their employees could work in the trench. During the OSHA inspection, OSHA observed the general contractor at the trench supervising the pipefitter in the trench. Which contractor(s) would receive a citation for an unsafe trench?
pipefitting only
pipefitting and excavator
pipefitting, excavator, and general contractor
pipefitting, excavator, general contractor, and concrete subcontractor
What is the maximum horizontal travel distance to retrieve a fire extinguisher for a project under construction?
10 ft
25 ft
75 ft
100 ft
4. The job site has a primary vertical control point with a reference benchmark of 100 ft. An instrument is set up with an HI of 5.42 ft above the BM. A grade stake is set at an elevation of 96 ft. What is the height reading on the rod at the grade stake?
1.42 ft
4.00 ft
5.42 ft
9.42 ft
Using the information provided in Figure 11, what is the benchmark elevation at IP #4?
864.62
889.90
896.27
902.64
Which of the following items are never included with a purchase order?
labor
material
tax
rental equipment
The terms on a purchase order indicate FOB Factory. At which point does the responsibility for the goods change?
passes at the invoice date
passes at the payment due date
passes at time of pickup by the carrier
passes at time of receipt at the job site
Which of the following descriptions defines the term 2/10 Net 30?
If paid within 10 days of the arrival of goods, a 2% discount can be deducted; full payment is due in 30 days.
If paid within 10 days of the invoice date, a 2% discount can be deducted; full payment is due in 30 days.
A 2% discount is available for 30 days.
A 2% discount is available through the 10th of the month following the receipt of goods; full payment is due in 30 days.
Which position typically writes the subcontract agreements?
superintendent
project engineer
project manager
planning engineer
Which of the following activities does a millwright perform?
cuts and installs trim and cabinets
assembles and aligns rotating equipment
fits and aligns high-pressure process piping
fabricates and assembles sheet metal for ductwork
Which party typically obtains the general building permit?
owner
subcontractor
contractor
architect/engineer
Which form is filled out by the employees to inform the employer how much money is to be withheld from their paychecks for taxes?
I-9
W-2
W-4
1099
Which of the following posters describes the regulations for wage payment and hours of work for all industries and must be posted at the job site?
Fair Labor Standards
Prevailing Wage Rates
Material Safety Data Sheet
Safety and Health Protection
What is the name of the act that requires the contractor to pay prevailing wage rates on all federally funded projects?
Wagner Act
Taft-Hartley Act
Davis-Bacon Act
Norris-LaGuardia Act
Which document is signed in agreement by the owner, architect, and contractor and modifies the contract’s terms and conditions?
addenda
change directive
contract change order
contract change order proposal
Which document establishes the actual start date from which the beginning of the project is calculated?
notice of award
notice to proceed
contractor’s proposal
supplementary conditions
. Which of the following parties issues the certificate of occupancy?
contractor, architect, and owner
banker, surety, and title company
contractor, mechanical subcontractors, and electrical subcontractor
fire marshal, mechanical inspector, electrical inspector, and building inspector
Which of the following descriptions provides the best example of how to report progress on the job site?
Poured concrete for the columns.
Installed rebar and poured concrete.
Poured 75 cy concrete, placed rebar, and stripped forms for columns D1–D4.
Poured 75 cy concrete, placed rebar, and stripped forms for the building.
Which party is typically the developer of the shop drawings?
owner
architect
construction manager
subcontractors and vendors
Which document explicitly tells the reader the specific shop drawings, product data, and reference standards required on a project?
in part 1 of each section of the general requirements
in part 1 of each section of a technical specification division
in part 2 of each section of a technical specification division
at the beginning of the first section of each technical specification division
