Electrical Fault Finding A

Total questions: 20

Worksheet time: 10mins

Name
Class
Date
1.

An approved voltage indicator should be used to

a)

Measure R1+R2

b)

Prove a circuit is dead before work begins

c)

Measure appropriate voltage

d)

Prove a circuit is live before work begins

2.

The definition of isolation is

a)

Functional switching for normal operation

b)

Single pole devices connected in the phase conductor

c)

Removing from every source of electrical energy

d)

Isolating equipment from general mass of earth

3.

The item shown in the photo should be used in what process?

a)

Voltage measurement

b)

Socket polarity

c)

Calibration checks

d)

Safe isolation

4.

Which of the following is the most likely of implications caused from an exposed terminal?

a)

Electric shock to a person or livestock

b)

MCB operate

c)

RCD Operates

d)

Main Cut off fuse operates

5.

When working on a circuit supplied by a fuse, which of the following methods is the LEAST acceptable method of ensuring accidental re-energisation?

a)

The gap should be covered by bright insulation tape

b)

A lockable fuse insert is put in its place

c)

The lid of the consumer unit is locked

d)

A dummy fuse carrier should be placed in place

6.

The safest method of ensuring that a system is safe to work on is?

a)

Follow the safe isolation procedure

b)

Isolate the installation at the main cut-out

c)

Use a fluke volt stick before you begin

d)

Place barriers at the distribution boards

7.

What is the benefit of using multi-hasp type padlock when isolating and locking off a circuit for maintenance?

a)

More than one circuit can be isolated at any one time

b)

Any single operative can make the circuit live once they have completed their task

c)

A circuit can only be made dead if all the operatives use locks

d)

More than one person can work on the circuit safely

8.

Which of the following is the most likely of implications caused from fault diagnostics

a)

Arcing

b)

Open circuit

c)

Loss of power

d)

Short circuit

9.

Which of the following would be most important to be discussed with the client prior to any fault diagnostics being carried out.

a)

Cost of the work

b)

Isolation timing

c)

The Earthing system

d)

The breaking capacity of the main protective device

10.

Which of the following could cause an SPD to operate

a)

Short circuit

b)

Lightning stikes in the area

c)

Overload in the circuit

d)

A damaged light switch

11.

Which of the following could cause an SPD to operate

a)

Short circuit

b)

Overload in the circuit

c)

Switching of large induction motors

d)

A damaged lamp

12.

Which of the following would be the most likely cause of the final light in a lighting circuit not working when the other lights do

a)

Short Circuit at the origin

b)

Open Circuit at the origin

c)

Open circuit in the last leg of the cable

d)

Short Circuit in the last leg of the cable

13.

If equipment plugged into a socket outlet is not working which of the following is the likely cause

a)

Loose Earth cable

b)

Faulty Switch

c)

Earth leakage

d)

One of the Line conductors has become loose

14.

Which of the following is likely to cause a transient voltage spike

a)

Switching surge from large induction motors

b)

High resistance joint

c)

Short Circuit

d)

Earth fault

15.

Which of the following would most likely cause a motor to not work if the circuit is healthy

a)

High resistance joint in the isolator

b)

Equipment malfunction

c)

Too many capacitors causing a leading effect

d)

Lightning strike

16.

Which logical stage should be carried first before carrying out fault diagnosis

a)

Gather information on Symptoms

b)

Rectify the work

c)

Safe isolation

d)

Functional testing

17.

To maintain accurate readings, an instrument should

a)

Have its batteries replaced frequently

b)

Be checked annually against national standards

c)

Be checked against similar instruments

d)

Be checked daily for any wear or tear

18.

Which of the following tests is performed if a broken cable is suspected?

a)

Prospective Fault Current

b)

Insulation Resistance

c)

Continuity of Ring Final Conductors

d)

Earth Fault Loop Impedance

19.

Several test instruments are used on an installation, which of the following would be most likely to give a reading of 2.5kA?

a)

Low resistance ohmmeter

b)

Prospective fault current

c)

Insulation resistance tester

d)

RCD tester

20.

The main reason for the cross connecting the conductors during the ring final circuit test and not just relying on end to end reading is?

a)

To record the values in the R1+R2 box at the same time

b)

A more accurate R2 reading can be obtained

c)

To ensure that the circuit is clear of short circuits or earth faults

d)

To detect any interconnections in the circuit