PMP - PROJECT INTEGRATION

Total questions: 10

Worksheet time: 10mins

Name
Class
Date
1.

Which of the following processes is included in Project Integration Management?

a)

Develop project management plan.

b)

Control scope definition.

c)

Review scope validation.

d)

Conduct procurement surveillance.

2.

All of the following are characteristics of the project charter EXCEPT:

a)

It formally authorizes the existence of a project.

b)

Projects are initiated by an entity external to the project. The project initiator or sponsor should be at the level that is appropriate to procure funding and commit resources to the project.

c)

It is used primarily to request bids for a project or a specific phase of a project.

d)

It provides the project manager with the authority to apply organizational resources to project activities.

3.

All of the following are characteristics of the Project Management Information System (PMIS) EXCEPT:

a)

Automated gathering and reporting on key performance indicators (KPls) can be part of this system.

b)

It provides access to information technology (IT) software tools, such as scheduling software tools, work authorization systems, and configuration management systems.

c)

It is used as part of the Direct and Manage Project work.

d)

It is used by the project manager and the project management team primarily to generate presentations to key stakeholders.

4.

You are managing a $10 million project. Which of the following is an acceptable cause for "re-baselining" this project?

a)

The client has approved an addition to the scope of the project with a $150,000 budget increase and a two-week extension of the scheduled completion.

b)

The contractor's company has instituted a quality assurance program in which it has pledged to spend $1 million during the next year.

c)

The productivity in the design department is lower than estimated, which has resulted in 1,000 additional hours over what was budgeted and a forecasted two-week delay of the scheduled completion.

d)

The engineering department of the performing organization has converted to a new $250,000 CAD system.

5.

A change control board (CCB) is:

a)

A formally chartered group of stakeholders responsible for ensuring that only a minimal amount of changes occurs on the project.

b)

A formal or an informal group of stakeholders that has oversight of project execution.

c)

A formally chartered group responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project, and for recording and communicating such decisions.

d)

A dashboard that provides integrated information to help control changes to cost, schedule, and specifications throughout the life of the project.

6.

Actions and activities necessary to transfer the project's products, services, or results to the next phase or to production and/or operations are addressed:

a)

As part of the Close Project or Phase process.

b)

Following the plan outlined in the Quality Management process.

c)

As requested by senior executives.

d)

As the last step in project management.

7.

Outputs of the Monitor and Control Project Work process include all of the following, EXCEPT:

a)

Change requests.

b)

Project management plan updates.

c)

Work performance reports.

d)

Final product, service, or result transition.

8.

All of the following are inputs to Manage Project Knowledge EXCEPT:

a)

Deliverables.

b)

Knowledge management.

c)

Lessons learned register.

d)

Project management plan.

9.

All of the following are Knowledge Management tools and techniques EXCEPT:

a)

Discussion forums.

b)

Storytelling.

c)

Work shadowing and reverse shadowing.

d)

Regression analysis.

10.

Lessons learned documentation generally includes all of the following EXCEPT:

a)

The causes of issues.

b)

Updates of the statement of work to reflect training and learning requirements.

c)

Reasoning behind the corrective action chosen.

d)

Other types of lessons learned about communications management.