1.

The WBS can be viewed as a related list on both the Project and Project Task form.

a)

True

b)

False

2.

What applications are included when a customer purchases PPM licenses?

choose 3.

a)

Scrum Management

b)

Resource Management

c)

Application Management

d)

Test Management

e)

Project Management

3.

The Project Management application can calculate costs of affected _____ in a project.

a)

Ressources

b)

Contracts

c)

Configuration Items (CI)

d)

Delays

4.

Project card columns Status, Percent Complete, and Phase are displayed from this table:

a)

pm_toplevel_project

b)

pm_home_page_card

c)

ps_project

d)

pm_project

5.

The Project template Configuration list defines the items that are included in a template. Each item in the list is a defined parent table with the exception of what table?

a)

pm_toplevel_project

b)

pm_home_page_card

c)

pm_project

d)

pm_project_task

6.

A Program record can include the risks and issues as submitted in:

Select all that apply

a)

portfolio

b)

idea

c)

program

d)

demand

e)

project

7.

Email notifications for the Project Management application are available by default and require manual activation.

a)

true

b)

false

8.

The values for project states is stored in what table?

a)

Project State [project_state]

b)

Task [task]

c)

State [state]

d)

Planned task [planned_task]

9.

Which 'Member Preference' automatically finds the most available resource(s) from the group and allocates to a plan using the allocation action?

a)

All members

b)

Any member and specific member

c)

Any member

d)

Specific member

10.

When copying a source project to a target project, what fields are copied by default?

a)

Duration fields

b)

Short description

c)

Number

d)

State

e)

Planned dates

11.

When user's schedule changes, what action needs to be taken by system admin?

a)

Update capacity via 'Update Resource Capacity'

b)

Update Resource Plans

c)

No action needed

d)

Update resource aggregate tables manually to reflect the changed capacity

12.

A customer needs to know what activity type is associated to time entries in the project so that they can capitalize build tasks. What is the best method to do this?

a)

Enable the "Activity Type - Time Entries" property.

b)

Leverage project time categories to classify the time.

c)

Create a capital project task flag.

d)

Put all capital project tasks in one phase and report from those tasks.

13.

Which objects are cloned when activating a team space?

a)

Project Application, Demand Application, Resource Management, Program, Project Properties (configurations), Form and List Layouts, Security and Access Rules (ACLs), Tables (data), Roles

b)

Project Application, Demand Application, Project Properties (configurations), Form and List Layouts, Security and Access Rules (ACLs), Tables (data)

c)

Project Application, Demand Application, Project Properties (configurations), Security and Access Rules (ACLs), Tables (data)

d)

Project Application, Demand Application, Project Properties (configurations), Security and Access Rules (ACLs), Tables (data), Roles

14.

What needs to be configured if a customer wants to change the attributes copied when using copy partial project?

a)

com.snc.project.copy

b)

com.snc.project.copy.additional_attributes

c)

The copy project client script

d)

The copy project UI action

15.

At a minimum, what role is required to view a project status report in project workspace?

a)

it_project_manager

b)

itil

c)

it_project_user

d)

worker

16.

When a time card is approved, the actual time is stored in which tables?

a)

Resource Aggregate tables (Daily, Weekly and Monthly)

b)

Resource_Allocation_Daily table

c)

Project Time table

d)

Resource Event table

17.

The project backlog includes all stories related to a project.

a)

true

b)

false

18.

What state does a resource plan need to be in to allow a resource to be added to the assignee field when the attribute for "Derive assignee list from resource plan" is set to true?

a)

Allocated

b)

Confirmed

c)

Requested

d)

Planning

19.

How is a parent-child relationship different from a dependency relationship?

a)

A parent-child relationship, any number of tasks can be nested under a parent task with or without any dependencies.

b)

Parent-child task relationships do not have any effect on task time constraints.

c)

A parent-child task must finish before another begins.

d)

A parent-child relationship is not saved as a record in any table.

20.

Resource Manager is allowed to change allocated hours on a resource plan after the plan moves to allocated state.

a)

true

b)

false

21.

Past allocation records are deleted after a resource plan is canceled.

a)

true

b)

false

22.

Hard allocations are created when a resource plan moves to confirmed state.

a)

true

b)

false

23.

When setting-up a program, planned ROI% is calculated based on:

a)

Values in the Estimated cost field.

b)

Values in the Planned return field.

c)

Values in the Budgeted cost field.

d)

Values in the Planned cost field.

24.

Why would a program manager create a program?

a)

Manage related demands.

b)

Define ROI to the organization.

c)

Manage related projects.

d)

Manage portfolios.

e)

Define the number of sprints.

25.

Committed Utilization is calculated as _____.

a)

Confirmed Hours/Capacity

b)

Allocated Hours/Capacity

c)

Assigned Hours/Capacity

d)

(Allocated Hours + Confirmed Hours)/Capacity

26.

Is resource capacity derived from FTE or schedules?

a)

Schedules

b)

FTE

c)

Neither

d)

Both

27.

Project and _____ can be linked to either Program, a Portfolio, both, or neither.

a)

Test Cases

b)

Stories

c)

Resources

d)

Demands

28.

What provides a central location for viewing a list of associated demands, projects, planning a portfolio and tracking ist progress?

a)

Project Workbench

b)

Demand Workbench

c)

Program Workbench

d)

Portfolio Workbench

29.

When creating a project from demand, what related records are moved and copied upon Project Creation?

a)

Idea and Demand

b)

Resource Plan and Change Requests

c)

Resource Plan and Cost Plan

d)

Cost Plan, Decisions and Assessment

30.

Expenses and costs for a particular demand should be estimated before screening. When preparing the financials of a demand, what determines the present value of future cash flows?

a)

Financial Return

b)

Discount Rate %

c)

Internal Rate of Return %

d)

Net Present Value (NPV)

31.

When working with demands, how are dates on a resource plan determined?

a)

From porfolio date

b)

Using demand created date

c)

From demand start date and due date

d)

Resource plan(s) cannot be created from demand

32.

How many relationships can exist between two tasks?

a)

1

b)

2

c)

3

d)

4

33.

Which of the following require fiscal periods to be configured?

a)

Benefit Plans

b)

Cost Plans

c)

Project Budgeting

d)

Project Plans

e)

Demand Plans

34.

Users with what role can be considered for resource planning?

a)

it_pps_user

b)

it_project_user

c)

it_user

d)

pps_resource

35.

A customer requires five (5) teamspaces to support different departments. What should you do?

a)

Use UI Policies and Business Rules to enable teamspaces.

b)

Activate via each teamspace plugin.

c)

Contact the Account Representative to activate the teamspaces.

d)

Enable the teamspace property.

36.

What rate elements contribute to building a resource plan's planned cost?

a)

Project Rate

b)

Default Rate

c)

Rate Card

d)

Group Rate

e)

Resource Rate

37.

A new assessment category has been added to support demand scoring, but the value is NOT visible in the demand once the calculation has run. What is the most likely cause?

a)

New assessment categories are not supported for demand management.

b)

The assessment result needs to be populated using the populate metric results business rule.

c)

The assessment result needs to be added by the admin.

d)

The assessment result needs to be populated using the populate metric results client script.

38.

An it_project_manager can choose from multiple rate types for their work when logging a time card.

a)

Only if the capability is enabled in the Time Sheet Policies.

b)

Only if this capability is enabled in the Project Record.

c)

Only one (1) rate type can apply.

d)

Only if the capabiliy is enabled in the Project Preferences.

39.

Which of the following are true regarding how My Project Space handles dynamic content?

a)

If the project state is Draft, actual start date and actual end date are displayed.

b)

If the project state is Pending or Open, planned start date and planned end date are displayed.

c)

If the project state is Work in Progress, actual start date and planned end date are displayed.

d)

If the project state is On Hold, actual start date and actual end date are displayed.

40.

On a project status report, what are the default status indicators?

a)

Schedule

b)

KPI's

c)

Accomplishments

d)

Cost

41.

Which field, referenced from the cost plan, determines if a cost plan is Capex or Opex?

a)

resource_type.expense_type

b)

resource_type.name

c)

resource_plan

d)

project

42.

What is the maximum number of cards that can be displayed in the project workbench?

a)

100

b)

150

c)

200

d)

300

43.

As a demand manager, you can view an artefact from a demand. What artefacts are part of a demand?

a)

Stories, Vulnerability Tasks, Enhancements

b)

Project, Defect, Requests

c)

Incidents, Problems, Change

d)

Decision, Risk, Requirements

44.

What field in the Stakeholder register determines if the user receives an assessment in Demand Management?

a)

Approver

b)

Assessment Level

c)

Level of Interest

d)

Assessment Recipient

45.

he planning console enables project managers to establish dependencies along project tasks.

a)

true

b)

false

46.

An it_project_manager can request resources by which of the following:

a)

Day

b)

Hours

c)

Month

d)

Person Days

47.

An it_project_manager can view or hide external dependencies.

a)

true

b)

false

48.

How does a it_project_manager create a Visual Task Board (VTB) for project tasks?

a)

Click the "Show VTB" related link.

b)

Hover over the project task and select "Show VTB".

c)

From the context menu, select the "VTB" view.

d)

Right-click the column header and select "Show Visual Task Board" from the menu.

49.

What types of task relationships can an it_project_manager create?

a)

Lag time

b)

Parent task

c)

Roll down

d)

All the above

50.

A fiscal calendar is required to enter a cost plan.

a)

true

b)

false

51.

For new customers who purchase Project Portfolio Suite with Financials, the com.snc.sdlc.agile.2.0 plugin is automatically activated.

a)

true

b)

false

52.

PPS activation is acomplished via the installation of plugins. Plugins are enabled in the following ways:

a)

Requested from ServiceNow

b)

Activated by an admin

c)

Activated by an it_portfolio_manager

d)

Activated by default in the base ServiceNow system

e)

Activated by an it_pps_admi

53.

What allows an it_portfolio_manager to enter CAPEX and OPEX target for each fiscal year?

a)

Portfolio Target

b)

Cost Plans

c)

Demand Workbench

d)

Portfolio Workbench

54.

The Portfolio Manager Dashboard provides portfolio level reports about:

a)

Change Requests, Enhancements

b)

Strategic Goals

c)

Risks, Issues, Activate Projects

d)

Key Milestones, Demands

55.

What is the demand workbench used for?

Select all that apply

a)

Comparing and prioritizing demands against other demands

b)

Comparing demands with portfolios

c)

Approving demands

d)

Displaying all demands to stakeholders

56.

Is the demand roadmap viewable in 2D or 3D?

a)

2D

b)

3D

c)

Both

d)

Neither

57.

To resubmit a deferred idea, the idea owner can resubmit existing idea record.

a)

true

b)

false

58.

The basics of Demand Management include:

Select all that apply

a)

Evaluate and qualify tasks

b)

Create ideas

c)

Create assessment categories

d)

Create stakeholders

59.

What are some benefits for using ServiceNow Implementation Methodology? (select all that apply)

a)

All information is stored in the customer instance providing historical record.

b)

All people working on the project are "speaking the same language."

c)

It gives control to the implementation team to do what they belive is the best thing for the customer

d)

Utilizes the platform cutting down on spreadsheets, emails or multiple applications.

e)

Allows the customer to configure the system making them independent.

60.

When the PPS with Financials plugin is activated, by default, which plugins are activated with it?

a)

Agile Development 1.0

b)

Agile Development 2.0

c)

Test Management 1.0

d)

Test Management 2.0

61.

Cloud Dimensions wants the project start date to remain the same despite the start date of the earliest task. Would the "rollup project start date from tasks" be set to yes or no?

a)

yes

b)

no

62.

Under which properties setting would an implementer change the average daily FTE?

a)

Project Preferences

b)

System Properties

c)

Resource Properties

d)

Resource Preferences

63.

What role would an implementer need to assign in order for groups and users to be managed through Resource Management?

a)

approval_user

b)

pps_resource

c)

timecard_user

d)

it_project_user

64.

What are the 2 base system roles provided in the DM application?

a)

it_demand_manager

b)

it_demand_owner

c)

dm_demand_manager

d)

it_demand_user

65.

T/F: The it_demand_manager role can either be assigned independently or inherited from the it_project_manager role?

a)

true

b)

false

66.

What table helps the demand manager to independently specify the level of interest, engagement, function, influence, assessment recipient and approver fields for a particular demand without having to worry about modifying the master stakeholder register record?

a)

Assessment Stakeholder [asmt_m2m_stakeholder]

b)

Stakeholder Register [dmn_stakeholder_register]

c)

Demand Stakeholder [dmn_m2m_demand_stakeholder]

d)

Project Stakeholder [pm_m2m_project_stakeholder]

67.

T/F: Only demand users can submit ideas?

a)

true

b)

false

68.

Changes made to Approver or Assessment recipient in the demand record update what table?

a)

dmn_stakeholder_register

b)

Demand Stakeholder [dmn_m2m_demand_stakeholder] table.

c)

pm_m2m_project_stakeholder

69.

T/F: Project Managers can modify the template configuration.

a)

true

b)

false

70.

T/F: Teamspace will have their own default template configuration items.

a)

true

b)

false

71.

Can you delete the default project template configuration items?

a)

Yes, but doing so affects the ability to create project templates.

b)

No, you can't delete the default template configuration items.

72.

T/F Any user with the resource_user role can create a resource plan.

a)

true

b)

false

73.

Can you delete the default project template configuration items?

a)

true

b)

false

74.

T/F Any user with the resource_user role can create a resource plan.

a)

true

b)

false

75.

T/F: The pps_resource role allows users or groups to become a user of resource planning.

a)

true

b)

false

76.

T/F: Can a PPS implementer create users or groups with the pps_resource role?

a)

true

b)

false

77.

T/F: Any type of task can have a resource plan (i.e. demand, incident, problem) attached to it.

a)

true

b)

false

78.

T/F: Resource Management can only be used with Project.

a)

true

b)

false

79.

T/F: The aggregate record does not contain capacity.

a)

true

b)

false

80.

When a user submits a time card and it is approved, the system generates an expense line?

a)

true

b)

false

81.

When the expense line state is set to processed and updated, the cost will be accounted in the _________________ which in turn will rollup the actuals to the project.

a)

Cost plan breakdown

b)

Expense line

c)

Resource plan

82.

"Planned capital" cost of the Project is the sum of "Cost of functional currency" of all cost plans who expense type is ________________.

a)

Capex

b)

Opex

83.

'Planned operating’ cost of the Project is sum of ‘Cost in functional currency’ of all cost plans whose expense type is _______

a)

Capex

b)

Opex

84.

Every resource plan creates a cost plan.

a)

true

b)

false

85.

Which role has the ability to access the Time Card application and submit a time card for a project, project task, or another type of task.

a)

timecard_admin

b)

timecard_user

c)

time_card_admin

86.

If a group will be responsible for approving time sheets or submitting time cards on behalf of team members, they should be given what role?

a)

timecard_admin

b)

timecard_user

c)

timecard_approver

87.

The Project Portfolio Suite adds which of the following plugins?

a)

Demand Management, Agile Development, Test Management, Resource Management

b)

Ideation, Agile Development, Test Management, Resource Management, Project Management

c)

Demand Management, Agile Development, Test Management, ResourceManagement, Project Management

d)

Portfolio Management, Agile Development, Test Management, Resource Management

88.

A customer has a requirement to create a task expense line for the top task when creating a task expense line. Which approach is recommended to satisfy this requirement?

a)

Edit the code in the Expense Line Related List and validate that the Related List is

b)

Validate that the ‘glide.cost_mgmt.process_task_top_task” property is set to true

c)

Edit the ‘com.snc.project.rollup.cost’ property to add the creation of a task expense line to the top task

d)

Override the Dictionary attributes for the Expense field

89.

Bottom-up tasking involves creating several sets of small tasks and estimating task items such as effort, cost, and duration. The emphasis is on _________.

a)

Creating estimates for high-level items such as phases and parent tasks

b)

How the project relates to similar projects or initiatives

c)

Creating dependencies between tasks

d)

Estimating smaller chunks of work

90.

Can a resource requester request a change for a plan that was already submitted for review?

a)

No, the plan was already submitted for review

b)

Yes, if the plan is in an Allocated state

c)

Yes, if the plan is in a Requested or Confirmed state

d)

No, only a resource manager can change a plan

91.

A ________ field combines information from two fields in a table to form a single field.

a)

Stage

b)

Assessable

c)

Combination

d)

Composite

92.

The Program Manager dashboard displays reports only for the programs managed by a program manager.

a)

true

b)

false

93.

A checklist item record provides only a name and a _________.

a)

Status

b)

Short Description

c)

Complete field

d)

Percent complete field

94.

A demand manager can delete a demand only when the demand is in which state?

a)

Qualified

b)

Submitted

c)

Draft

d)

Approved

95.

A Program is a container for the following except for:

a)

Program Tasks

b)

Issues

c)

Cost Plans

d)

Programs

96.

A project can be directly part of a portfolio and not part of a program

a)

True

b)

False

97.

A project expense line is a cost associated with a specific source. Examples of specific sources could include:


Choose 3 answers.

a)

Fixed Asset

b)

Project

c)

User

d)

Demand

e)

Configuration item (CI)

98.

A project expense line is cost associated with a specific source, except for:

a)

Software

b)

Resource

c)

Fixed Assets

d)

Program

99.

A project manager can create subcategories to define specific activities in the project.

a)

True

b)

False

100.

A project uses the default schedule, which specifies that work hours are Monday to Friday from 08:00 to 17:00 with an hour break from noon to 13:00. A change request with a 13-hour duration starts at midnight. When will the project task link start and end?

a)

he project task link starts at midnight and continues through the start of the schedule at 08:00. It stops at noon for one hour, and continues until 14:00.

b)

The project task links starts at midnight and continues through the start of the schedule at 08:00. It stops for one hour, and continues until noon.

c)

The project task link starts at 08:00 and continues through until noon. It stops at 13:00 for one hour, and continues at 14:00

d)

The project task link starts at 01:00 and continues through the start of the schedule at 08:00. It stops at noon for one hour, and continues until 17:00.

101.

A user that is typically under the default time sheet policy can select additional rate types when logging time if the following steps are completed:

a)

Create new rate type, associate rate type to user, enable multiple rate types from project preferences

b)

Create new rate type, create multiple labor rate cards that apply to the user, enable multiple rate types from project preferences.

c)

Create new rate type, associate rate type to user, enable multiple rate types from the default time sheet policy

d)

Create new rate type, create 2 or more labor rate cards that apply to the user, enable multiple rate types from the default time sheet policy

102.

Actuals on a resource plan are updated by what activity?

a)

Resource plan is approved

b)

User submits time card

c)

Project manager enters actuals

d)

Time card is approved

103.

After creating the portfolio forecast plan, the investment committee review the plan. You decide to modify the forecast plan for the project to implement the changes suggested by the investment committee. What action would you take to reflect the changes in the forecast plan?

a)

Select repromoted Forecast Plan

b)

Select open/close Forecast Periods

c)

Select update Forecast Plan

d)

Select Forecast Plan Change

104.

An Agile phase can be created for a project from the project workbench if the com.snc.sdlc.agile.2.0 plugin is activated.

a)

True

b)

False

105.

An it_portfolio_manager can add stakeholders to a portfolio where they are listed as the portfolio owner.

a)

True

b)

False

106.

An it_pps_admin user is able to update: Choose 2 answers.

a)

Budget Periods

b)

Portfolio Targets

c)

Client Scripts

d)

Business Rules

107.

An it_project_manager can choose from multiple rate types for their work when logging a time card.

a)

Only if the capability is enabled in the Time Sheet Policies

b)

Only if the capability is enabled in the project Record

c)

Only one (1) rate type can apply

d)

Only if the capability is enabled in the project preferences

108.

As an admin, what can you use to customize the PPM Mobile Application?

a)

ATF Suites

b)

Self-Service

c)

Service Catalog

d)

Mobile Studio

109.

As an it_pps_admin, what can you use to detect corrupt data in a project, such as tasks with invalid parents or cyclic relations in a project?

a)

Edge Encryption Diagnostics

b)

System Diagnostics

c)

Analytics Diagnostics

d)

Project Diagnostics

110.

At a minimum, what role is required to view the summary of a project in the summary tab of project workspace?

a)

It_project_user

b)

Worker

c)

Itil

d)

It_project_manager

111.

Base system portfolio manager dashboards provide portfolio level reports about: Choose 2

a)

Key Milestones, Demands

b)

Strategic goals

c)

Change Request. Enhancements

d)

Risks, Issues, Active Projects

112.

Budget plans created for a fiscal year can be promoted only if the budget period is ____

a)

Open

b)

Closed

c)

Deffered

d)

Skipped

113.

By default, assessments are due _____ after being sent to as assessment recipient.

a)

Two weeks

b)

Three weeks

c)

One week

d)

Four weeks

114.

By default, these features are not included in a teamspace application; however can be added in teamspace settings.


Choose 2 answers

a)

Project

b)

Workbench configuration

c)

Idea

d)

Demand Assessments

115.

Can a PPS admin edit properties in System Property [sys_properties] table?

a)

No, only a system administrator can edit properties in this table.

b)

Yes, a PPS admin can edit some properties in this table

c)

No, system properties can not be edited

d)

Yes, a PPS admin can edit all properties in this table

116.

Can an it_project_manager convert a task to a milestone?

a)

Yes, from the planning console right-click a task and select convert to milestone.

b)

Yes, it must be manually done from the project record.

c)

No, the task must be deleted and re-created.

d)

No, this can only be done by an admin.

117.

Can an PPS admin edit properties in System Properties [sys_properties] table?

a)

No, only a system administrator can edit these properties

b)

Yes, all the properties can be edited

c)

Yes but only properties specific to projects

d)

No, a PPS admin cannot edit any properties in any ServiceNow table

118.

Cloud Dimensions wants the project start date to remain the same despite the start date of the earliest task. Would the "rollup project start date from tasks" be set to yes or no?

a)

Yes

b)

No

119.

Demand assessments are triggered as soon as the demand enters what state?

a)

Submitted

b)

Approved

c)

Qualified

d)

Screening

120.

Depending on the execution type selected for a particular project, one of these dashboards will also be available:

a)

Project Summary – Waterfall Dashboard

b)

PMO Dashboard

c)

User Manager Dashboard

d)

Timecard Dashboard

121.

Domain separation in the PPM application is supported at the data level only

a)

true

b)

false

122.

During allocation process, when named resources are allocated to a plan, where is resource cost derived from?

a)

Cost specified on user record

b)

Labor rate card for the user

c)

From resource management property

d)

Cost specified on group record

123.

Each teamspace has its own: Choose 2 answers.

a)

Resource table

b)

Project table

c)

Problem table

d)

Demand table

124.

Email notifications for the Project Management application are available by default and require manual activation

a)

true

b)

false

125.

Every resource plan creates a cost plan.

a)

true

b)

false

126.

For new customer who purchase Project Portfolio Suite with Financials, the com.snc.sdlc.agile.2.0 plugin is automatically activated.

a)

true

b)

false

127.

How are actual costs created for cost plans?

a)

Every night a scheduled job runs to process estimated expenses for all projects

b)

When a timecard is created

c)

Estimated cost is manually entered in the cost plan

d)

When a timecard is approved

128.

How can the planned start date on a WIP/Closed task be changed?

a)

By setting the property - 'Enable altering of planned date(s) for task in WIP/Closed'

b)

By setting the property - 'Enable firing of Business Rules on save from Planning Console'

c)

By setting the property- 'Enable alter of planned date with Actual for Manuel Project'

d)

By setting the property - 'Enable project cost rollup'

129.

How does a project manager request a change to a resource plan in the requested state?

a)

Email resource user

b)

Use notes on resource plan

c)

Email resource manager

d)

Request change on resource plan

130.

How many resource groups can a resource be associated to?

a)

Only 10

b)

Any number

c)

Only 5

d)

Only 1

131.

How many WBS levels can be shown on the planning console?

a)

One

b)

Two

c)

Three

d)

No Limit

132.

If a "Business Unit" for a demand is selected in the "Details" tab, then the choice list will display the business strategies for that Business Unit, as well as other enterprise strategies.

a)

true

b)

false

133.

If a project manager is responsible for approving time sheets or submitting time cards on behalf of team members (what role must he be granted?)

a)

approval_admin

b)

form_admin

c)

activity_admin

d)

timecard_admin

134.

If a resource plan is not associated manually to a timecard, then a resource plan is auto-associated. The auto-association is done based on the selected _____ in the time card.

a)

Task

b)

Hard allocation

c)

Soft allocation

d)

Resource type

135.

If a user works 8 hours a day, and 2 person days are requested for 5 days, how many hours are being requested?

a)

10

b)

40

c)

80

d)

16

136.

If an it_project_manager does not want to equally distribute hours across the resource plan time frame, (allocation spread)

a)

Front Load

b)

Any

c)

Even

d)

Back Load

137.

If the estimated cost and planned benefit values roll up from the cost and benefit plans, what determines the currency in which the roll-up happens?

a)

Glide.syste.locale property

b)

Glide.cost_mgmt.calc_actual_cost

c)

Glide.workflow.log

d)

Com.snc.sdlc.scrum.pp.burndown.idea.linear

138.

If you create a new demand from the demand workbench, it is created in a _______ state and appears on the bubble chart

a)

Approved

b)

Submitted

c)

Draft

d)

Qualified

139.

In order for a business unit to have its own Idea Portal, what must be configured first?

a)

A Business Unit cannot have its own Idea Portal

b)

Idea categories

c)

Idea module

d)

Idea Portal URL

140.

In the base system, the default sprint length used if the length cannot be calculated from the sprint is ___ days.

a)

12

b)

14

c)

16

d)

18

141.

In the base system, when working with demands, what two assessment metrics are supported when taking an assessment survey?


Choose 2 answers

a)

Risk

b)

Strategic Alignment

c)

Cost

d)

Size

142.

In what way would you restrict the assigned to field on a project task to only allow users with resource allocations to be assigned?

a)

Create a reference qualifier on the ‘assigned to’ field

b)

Create an Access Control List (ACL) rule

c)

On the project record under the preferences tab select the ‘Derive assignee list from resource plan” preference

d)

The system automatically does this and can lonely be disabled by an admin

143.

Nested or sub-projects cannot have:

a)

baselines

b)

project schedules

c)

stories

d)

reports

144.

On a day-to-day basis, what table stores the events that are created through a resource plan and also stores user created calendar events?

a)

Resource Allocation Daily [resource_allocation_daily]

b)

Resource Aggregate Daily [resource_aggregate_daily]

c)

Resource Allocation [resource_allocation]

d)

Resource Report [resource_report]

145.

On a resource plan, when the attribute for "Derive assignee list from resource plan" is set to true, in what state must the plan be to allow a resource to be added to the assignee field?

a)

Allocated

b)

Requested

c)

Confirmed

d)

Planning

146.

On the demand form, what does the Discount Rate impact?

a)

ROI

b)

Internal Rate of Return %

c)

Net Present Value (NPV)

d)

Financial Benefit

147.

Only one time sheet policy can be set as a default policy

a)

true

b)

false

148.

Plugins may be added to the base platform in one of the following ways: Choose 3 answers.

a)

Activated by an it_pps_admin

b)

Requested from ServiceNow

c)

Activated by an admin (not by default)

d)

Activated by default in the base ServiceNow system

e)

Activated by an it_portfolio_manager

149.

Project card columns in Project Workspace are displayed from this table:

a)

Pm_project

b)

Pm_home_page_card

c)

Ps_project

d)

pm_toplevel_project

150.

Project card columns Status, Percent Complete, and Phase are displayed from this table:

a)

pm_toplevel_project

b)

pm_home_page_card

c)

ps_project

d)

pm_project

151.

Project templates can be shared across teamspaces

a)

true

b)

false

152.

Projects and ______ can be linked to either a Program, a Portfolio, both, or neither.

a)

Resources

b)

Stories

c)

Test Cases

d)

Demands

153.

Rate types have start and end validity dates

a)

true

b)

false

154.

Requesting a resource plan by Person Day and FTEs results into same hours.

a)

true

b)

false

155.

Resource requesters can view resource allocations and can modify them at any time.

a)

true

b)

false

156.

Submitters or collaborators can edit their ideas as long as the idea is in the submitted state

a)

true

b)

false

157.

Submitters or collaborators can edit their ideas except when the idea is in which state?

a)

Submitted

b)

In backlog

c)

Planned

d)

Duplicate

158.

The ______ table stores events through a resource plan, including calendar events and actual hours.

a)

Resource Aggregate Daily [resource_aggregate_daily]

b)

Resource Allocation Daily [resource_allocation_daily]

c)

Resource Plan [resource_plan]

d)

Resource Allocation [resource_allocation]

159.

The Business Unit field on a Project or Demand form displays values from a specific table. What (type of field is this??)

a)

Journal

b)

Reference

c)

List

d)

Conditions

160.

The color band at the top of the project card in Project Workspace displays what project attribute?

a)

Status

b)

Risk

c)

Issues

d)

State

161.

The colors and quadrant labels are configurable in this central location for viewing and assessing business demands.

a)

Demand Workbench

b)

Investment Portal

c)

Investment Funding

d)

Idea Portal

162.

The colors and quadrant labels are non-configurable on the demand workbench.

a)

true

b)

false

163.

The Defect and Enhancement demand choices are available only when agile is installed

a)

true

b)

false

164.

The planning console enables project managers to establish dependencies along project tasks.

a)

true

b)

false

165.

The Portfolio workbench is based on _____ which means that a user can configure, customize, and extend the workbench per requirements and organizational workflow.

a)

Core config

b)

Dashboard Configuration

c)

Service Portal

d)

Portfolio Planning

166.

The project console pulls data from the project [pm_project] table and the project task [pm_project_task] table. The list of tables is maintained in the __________.

a)

Planning console Configuration

b)

Project status portal configuration

c)

None of these

d)

Project configuration

167.

The Project Management application enables users to create parent-child relationships between tasks and dependencies, such as finish-to-start and finish-to-finish, between tasks. How many relationships can exist between two tasks?

a)

One

b)

Two

c)

Three

d)

Four

168.

The Project management application supports two types of external dependencies. What are they?

Choose 2 answers.

a)

Milestone Dependency

b)

Change Dependency

c)

Task Dependency

d)

Hard Dependency

e)

Soft Dependency

169.

The Project Portfolio suite with financials enables an it_project_manager to perform the following activities:


Choose 3 answers

a)

Establish resource requirements and track costs.

b)

Configure cost type definitions

c)

Define target for the portfolio

d)

Determine overall project cost requirements

e)

Track actual amount spent compared to an approved budget

170.

The project property to update actual effort from time card is controlled at what level?

a)

Program Level

b)

Project Level

c)

Portfolio Level

d)

Application Level (Global)

171.

The resource workbench does not support mobile devices

a)

true

b)

false

172.

The resources in "Assigned to" column can be constrained to be derived only from the allocated resource plans associated with the project or any of its task. What controls this behaviour on the project form?

a)

The "Watchlist" field

b)

The "Impacted Business Units" field

c)

The "Enablers" field

d)

The "Derive assignee list from resource plan" field

173.

The selections from the Category and Type fields determine the artifact that can be created from a demand (…)

Choose 3 answers.

a)

change

b)

resource

c)

task

d)

enhancement

e)

defect

174.

To integrate Investment Funding with PPM, what plugin must be activated?

a)

Investment Funding for PPM [com.snc.investment_planning_pmo]

b)

Investment Funding [com.snc.investment_planning]

c)

Financial planning [com.snc.financial_planning]

d)

Rate Model [com.snc.rate_model]

175.

To resubmit a deferred idea, the idea owner can resubmit existing idea records.

a)

true

b)

false

176.

Users with the ___________ role can use the workflow designer to set up a workflow that sends an email notification when the state of a project task becomes Work in Progress


Chose 2 answers

a)

Admin

b)

It_project_manager

c)

It_pps_admin

d)

It_project_user

177.

What allows a project manager to see the difference in the financials of a project from when it initiated?

a)

Financial baseline

b)

Task baseline

c)

CI baseline

d)

Baseline CMDB

178.

What applications are shared across teamspaces?

choose 3

a)

Resource, Project Financials, Agile

b)

Agile, Test only

c)

Project Financials, Agile, Test

d)

Resource, Agile, Test

179.

What are the allocation types available on a resource plan? Choose 3 answers.

a)

Monthly

b)

Weekly

c)

Plan Duration

d)

Daily

e)

Yearly

180.

What are the offset types in Benefit Plans?

a)

Start Date and End Date

b)

Rate Card

c)

Cost

d)

Risk

181.

What are the three trend types that can be used for allocation reporting?

a)

Committed utilization

b)

Capacity

c)

Confirmed allocation

d)

Forecasted utilization

e)

Demand allocation

182.

What can help validate the continued functionality of PPM applications after a configuration change such as a upgrade or after developing an application?

a)

Stories

b)

Test board

c)

Test Assignments

d)

Quick start tests

183.

What capability in ServiceNow allows you to compare the cost vs. price of a resource?

a)

Rate types

b)

None

c)

Planned cost vs. actual cost reports

d)

Labor rate cards

184.

What captures a snapshot of cost plan, benefit plan, and financial metrics of both a demand and project?

a)

Financial baseline

b)

Task baseline

c)

Tracking tab in project workspace

d)

Analytics tab in project workspace

185.

What demand type would a demand manager select if the demand manager needs to create an enhancement?

a)

Operational

b)

Strategic

c)

Enhancement

d)

Defect

186.

What does the project status report allow project managers to do?

Choose 2 answers:

a)

Publish the status report to various stakeholders as PDF attachment

b)

Show historical trend of project KPIs

c)

View the WBS

d)

View the project Gantt Chart

187.

What features are not included in a teamspace application but can be added in teamspace settings?

Choose 2 answers.

a)

Project

b)

Workbench configuration

c)

Demand Assessments

d)

Idea

188.

What field in the Stakeholder register determines if the user receives an assessment in Demant Management?

a)

Approver

b)

Assessment Level

c)

Level of Interest

d)

Assessment Recipient

189.

What happens to resource allocations with actual hours after a resource plan is cancelled?

a)

A resource plan with actual hours cannot be cancelled

b)

They remain active until the project is closed

c)

They are deleted

d)

They are automatically moved to the next resource plan in the project

190.

What is a program?

a)

A group of related projects and program activities

b)

A group of related projects

c)

A group of related projects, ideas, demands, and task activities

d)

A group of related projetcs, demands, and program activities

191.

What is a resource event?

a)

An external event

b)

An event scheduled by a project manager

c)

A block of time that a resource spends on a task

d)

A non-schedule activity impacting capacity

192.

What is the default schedule for a project?

a)

9-hour workday (8-12 and 1-5)

b)

8-hour workday (9-12 and 1-5)

c)

8-hour workday (8-12 and 1-4)

d)

8-hour workday (8-12 and 1-5)

193.

What is the purpose of the demand state business rule?

a)

Limits creation of a project record

b)

Limits user access to a demand record

c)

Allows demand manger to add stakeholders

d)

Provides workflow for demand process

194.

What is the result of an expense line after it’s processed?

a)

The actual cost is recorded at the portfolio level

b)

Noting significant results

c)

The actual amount incurred becomes part of the cost plan

d)

The cost plan closes

195.

The planning console enables project managers to establish dependencies along project tasks

a)

true

b)

false

196.

The Portfolio workbench is based on _____ which means that a user can configure, customize, and extend the workbench per requirements and organizational workflow.

a)

Core config

b)

Dashboard Configuration

c)

Service Portal

d)

Portfolio Planning

197.

The project console pulls data from the project [pm_project] table and the project task [pm_project_task] table. The list of tables is maintained in the __________.

a)

Planning console Configuration

b)

Project status portal configuration

c)

None of these

d)

Project configuration

198.

The Project Management application enables users to create parent-child relationships between tasks and dependencies, such as finish-to-start and finish-to-finish, between tasks. How many relationships can exist between two tasks?

a)

One

b)

Two

c)

Three

d)

Four

199.

The Project management application supports two types of external dependencies. What are they?

Choose 2 answers.

a)

Milestone Dependency

b)

Change Dependency

c)

Task Dependency

d)

Hard Dependency

e)

Soft Dependency

200.

The Project Portfolio Suite adds which of the following plugins?

a)

Demand Management, Agile Development, Test Management, Resource Management

b)

Ideation, Agile Development, Test Management, Resource Management, Project Management

c)

Demand Management, Agile Development, Test Management, Resource Management, Project Management

d)

Portfolio Management, Agile Development, Test Management, Resource

201.

The Project Portfolio suite with financials enables an it_project_manager to perform the following activities:


Choose 3 answers

a)

Establish resource requirements and track costs.

b)

Configure cost type definitions

c)

Define target for the portfolio

d)

Determine overall project cost requirements

e)

Track actual amount spent compared to an approved budget

202.

The project property to update actual effort from time card is controlled at what level?

a)

Program Level

b)

Project Level

c)

Portfolio Level

d)

Application Level (Global)

203.

Users with the ___________ role can use the workflow designer to set up a workflow that sends an email notification when the state of a project task becomes Work in Progress


Chose 2 answers

a)

Admin

b)

It_project_manager

c)

It_pps_admin

d)

It_project_user

204.

What minimum role is required to assign a time sheet policy to a user?

a)

It is not possible to assign a time sheet policy to a user

b)

It_project_manager

c)

It_project_user

d)

Timecard_admin

205.

What property when set to true will move all entries like Cost Plan, Resource Plan and Benefit Plans relative to the project start date?

a)

com.snc.project.portfolio_workbench.confirm_to_create_project

b)

com.snc.project.date_change_cascade

c)

com.snc.project.rollup.cost

d)

com.snc.project.copy.additional_Attributes

206.

What provides a central location for viewing a list of associated demands, projects, planning a portfolio and tracking its progress?

a)

Project Workbench

b)

Demand Workbench

c)

Program Workbench

d)

Portfolio Workbench

207.

What rate elements contribute to building a resource plan’s planned cost?


Choose 3 answers

a)

Resource Rate

b)

Project rate

c)

Default rate

d)

Rate card

e)

Group rate

208.

What role can configure an idea module, map idea categories to the idea module, and add navigation for the Idea Portal?

a)

Idea admin [idea_admin]

b)

Idea manager [idea_manager]

c)

Demand manager [it_demand_manager]

d)

Project manager [it_project_manager]

209.

What role can set the Portfolio Planning field to Simple or Advanced for a portfolio?

Choose 2 answers.

a)

Resource_manager

b)

Category_manager

c)

It_portfolio manager

d)

It_pps_admin

210.

What role can view a project status report in the project workspace?

a)

It_project_manager

b)

Worker

c)

It_project_user

d)

Itil

211.

What role is required to view the summary of a project in project workspace?

a)

It_project_user

b)

It_project_workspace_user

c)

It_project

d)

It_project_manager

212.

What table displays project card columns in the Project Workspace?

a)

Dmn_demand

b)

Pm_toplevel_project

c)

Pm_project

d)

Pm_home_page_card

213.

What types of task relationships can an it_project _manager create?

a)

Lag time

b)

Parent task

c)

Roll down

d)

All the above

214.

When a time card is approved, the actual time is stored in which two tables? Choose 2 answers.

a)

Resource Aggregate tables (Daily, Weekly and Monthly)

b)

Resource_Allocation_Daily table

c)

Resource Event table

d)

Project Time table

215.

When Agile Development 2.0 and Test Management 2.0 plugins are activated with PPM with Financials plugin, the project manager can create and edit which of the following phase types depending on execution type? Choose 2 answers.

a)

Test

b)

VTB

c)

Agile

d)

List

216.

When creating a program, which of the following cannot be part of multiple programs?

Choose 2 answers.

a)

Demand

b)

Portfolio

c)

Tasks

d)

Project

217.

When setting up a program, a project or demand cannot be included in multiple programs.

a)

true

b)

false

218.

When setting up a program, planned ROI% is calculated based on:

Choose 2 answers.

a)

Values in the NPV field.

b)

Values in the Planned cost field.

c)

Values in the Planned return field.

d)

Values in the Budgeted cost field.

219.

When working with demands at what state can a user create a project record?

Choose 2:

a)

During Screening

b)

After Completed

c)

After Approved

d)

Before Work in Progress

220.

When working with demands, what role is required for a stakeholder to take an assessment?

a)

It_demand_user

b)

It_assessment_manager

c)

Demand_user

d)

Assessment_user

221.

Where is planned cost calculated from when requesting resources from a group and when resource role is specified?

a)

Hourly rate of the specified role

b)

Task rate cards

c)

CI rate cards

d)

Distribution cost

222.

Where is the normalization process used?

a)

Cost Plan updates

b)

Risk records

c)

Assessment scoring

d)

Demand Approval

223.

Which "Member Preference" automatically finds the most available resource(s) from the group and allocates to a plan using the allocation action?

a)

Any member

b)

All members

c)

Specific member

d)

Any member and specific member

224.

Which dashboards provide burndown chart progress of a release or sprint from start to finish compared with the actual daily progress?

a)

PMO Dashboard

b)

Timecard Dashboard

c)

Project Summary – Waterfall Dashboard

d)

Agile Development Dashboard

225.

Which field, referenced from the cost plan, determines if a cost plan is capex or opex?

a)

Resource_type.expense_type

b)

Resource_type.name

c)

Resource_plan

d)

Project

226.

Which of the following are true regarding how the My Project Space handles dynamic content? Choose 2 answers.

a)

If the project state is Draft, actual start date and actual end date are displayed.

b)

If the project state is Pending or Open, planned start date and planned end date are displayed

c)

If the project state is On Hold, actual start date and actual end date are displayed

d)

If the project state is Work in Progress, actual start date and planned end date are displayed

227.

Which of the following defines a parent-child relationship?


Choose 2 answers

a)

Parent-child task relationships do not have any effect on task time constraints.

b)

A parent-child relationship is not saved as a record in any table

c)

In a parent-child relationship, any number of tasks can be nested under a parent task with or without any dependencies

d)

A parent-child task must finish before another begins

228.

Which of the following elements can be included when creating the planned cost in a resource plan? Choose 3 answers.

a)

Demand rate

b)

Group rate

c)

Default rate

d)

Rate card

e)

Project rate

229.

Which of the following require fiscal periods to be configured? Choose 3 answers.

a)

Project Budgeting

b)

Benefit Plans

c)

Risks

d)

Requirements

e)

Cost Plans

230.

Which of the following roles can access the project administration application?

a)

it_project_user

b)

it_pps_admin

c)

timecard_admin

d)

it_project_manager

231.

Which propertie restricts the maximum number of days for which a resource plan can be created?

a)

com.snc.project.rollup_project_start_date

b)

com.snc.project.allow_start_on_relations

c)

com.snc.resource_manager

d)

com.snc.resource_management.plan.max_duration

232.

Which role allows you to allocate a resource?

a)

Business_stakeholder

b)

Resource_manager

c)

It_project_user

d)

Resource_user

233.

Which role has the ability to access the Time Card application and submit a time card for a project, project task, or another type of task.

a)

timecard_admin

b)

timecard_user

c)

time_card_admin

234.

Which roles can modify agile properties?


Choose 2 answers

a)

Product_owner

b)

It_pps_admin

c)

Admin

d)

Scrum_master

235.

Which roles have access to change the level of time reporting for a project? Choose 2 answers.

a)

it_project_user

b)

it_pps_admin

c)

it_timecard_user

d)

it_project_manager

236.

Which statements below define the Project Workbench?

a)

Displays demands screened by stakeholders or qualified individuals

b)

A central location for creating and managing projects

c)

Displays projects as cards based on filter criteria

d)

Allows for a hybrid approach to project management

237.

Which table stores daily capacity of a user?

a)

User Profile

b)

Resource_Allocation_Daily

c)

Resource_Aggregate_Daily

d)

Resource_Event

238.

Who can submit ideas?

a)

Any it user

b)

Any user

c)

Any demand user

d)

Any ITIL user

239.

Why is it recommended to keep the value of the property ‘com.snc.project.task.max_task_duration’ to 2600 or under?

a)

Because projects longer than 2600 days will no longer load.

b)

To avoid application memory issues.

c)

Best practice states projects should be no longer than 5 years.

d)

The system is unable to handle more than 2600 tasks.

240.

Why would a program manager create a program?


Select all that apply

a)

Manage related demands

b)

Define ROI to the organization

c)

Manage related projects

d)

Manage portfolios

e)

Define the number of sprints

241.

You can forecast future costs of projects based on: Choose 2 answers.

a)

Actual cost incurred

b)

Changes in project such as project requirements.

c)

Incident cost

d)

Paired instances