WorksheetsWJEC Construction ROLES 4
Total questions: 21
Worksheet time: 13mins
I am the person who wants the building. who am I
The Architect
The Client
The council planning department
The Contractor
My role is to ensure that sufficient materials are calculated to complete the building project . Who am I ?
The Architect
The Site Manager
The Project manager
The Quantity Surveyor
Which trade would not be needed on the building site to progress work at the start of first fix?
Electrician
Roofers
Bricklayers
Painting and Decorating
Which of the following factors affecting building progress can be avoided with good project management?
running out of building materials
materials not arrived due to traffic problems
Weather conditions
Sub Contractors not turning up
Materials bought for the project are subject to VAT. What is this ?
Discount on bulk purchases
A penalty for late payment of goods
A Government tax
Vehicle Authorised Tax. transport costs
Most building starts by providing a stable foundation. This stage is known as....
the base
the footings
first fix
landscaping
A building has been erected. which type of dividing wall would you NOT expect inside the building ?
stud partition
concrete blockwork
brick load bearing
dry stone wall
Mini diggers, cranes and generators are often referred to as
capital
plant
statutory engineering
sub structure equipment
A young apprentice has turned up for work without these PPE. What should happen?
allow him to work on site, give him a verbal warning and tell him not to forget them next time or else!
give him a job driving a digger where risk of foot injury is minimised
Ask him to sign a disclaimer saying if he has an accident its his fault
Send him home to collect them
This vehicle is operating on site. What safety procedure's should implemented
high vis clothing to be worn by workers
a safe pedestrian route to be fenced off
a maximum speed limit implemented
safety signs posted in the area
all of the above
My role in the building industry is to investigate accidents, near misses or complaints of unsafe practice
Project Manager
Company Director
Site Manager
HSE
Groundworker
which of the following trades will commence work after the building shell and roof are completed
Plumber, Electrician, Roofer
Bricklayer, Joiner, Groundworker
Plumber, plasterer, electrician
Town planner, Architect, Quantity surveyor
What is a Gannt Chart
A list of materials needed for the building process
A calendar showing when key staff have booked holiday
a chart showing the progress of the building project
A schedule of planned operations to complete the project on time
My role is to ensure enough materials are supplied to the project in time.. Who am I ?
Architect
Quantity Surveyor
Project manager
Building Engineer
a snagging list is,,,
a list of dangerous places to work
A list of complaints by sub contractors
Things that have been completed on time
A list of things that are not to standard and need rectifying
Which of the following delays could be avoided
Weather Disruption
Logistics
Accidents
errors on the plans
which of the following would not be made out of timber
Lintel
Stud wall
Footing
Fascia board
Reorder the following ,Place the following careers with the highest salary first
Project manager
Site manager
Joiner
Security Guard
Labourer
which trade would not normally liaise/ communicate with the other three trades
Landscape Gardener
Plumber
Electrician
Joiner
Which is the odd one out here
Gas supply
water connection
wi fi instalation
Electric supply
Reorder the following in the order they would be employed on site on a house build
Security Fencing
Groundwork
Brick layer
First fix Joiner
Electrician