Project Management Chapter 3

Total questions: 15

Worksheet time: 6mins

Name
Class
Date
1.

TRUE statements regarding project scope

a)

Establishing project priorities

b)

Creating the Work Breakdown Structure (WBS)

c)

Integrating the WBS with the organization

d)

Coding the WBS for the information system

2.

The elements of project scope checklist

a)

Project objective

b)

Budget

c)

Milestone

d)

Technical Requirements

3.

Elaboration of "deliverables" in project scope chekclist?

a)

Overall objective to meet your customer’s needs

b)

The expected outputs over the life of the project

c)

The boundary of the project by stating what is not included

d)

Completion of the scope checklist

4.

Major segments of work, rough-cut estimates of time, cost, and resources for the project representing

a)

Deliverables

b)

Technical requirements

c)

Limit and exclusion

d)

Milestones

5.

"The understanding and agreement of expectations" refering to

a)

Customer review

b)

Project objective

c)

Milestones

d)

Limit and exclusions

6.

The primary jobs of a project manager is to manage the trade-offs among

a)

Task

b)

Time

c)

Cost

d)

Performance

7.

The performance should be ...., time should be ...., and cost should be .....

a)

enhanced, accepted, constrained

b)

accepted, enhanced, constrained

c)

constrained, enhanced, accepted

d)

constrained, accepted, enhanced

8.

Definition of Work Breakdown Structure (WBS)

a)

A map of the project and an outline of the project with different levels of detail

b)

A product or service will have technical requirements to ensure proper performance

c)

Answers the questions of what, when, and how much

d)

The completion of the scope checklist ends with a review with your customer; internal or external

9.

WBS helps to:

a)

Assure project managers that all products and work elements are identified

b)

Integrate the project with the current organisation

c)

Establish a basis for control

d)

Taking advantage of opportunities to either reduce costs or shorten the schedule

10.

The following statements define WBS:

a)

Provides management with information appropriate to each level

b)

Defines all the elements of the project in a hierarchical framework and establishes their relationships to the project end items

c)

Provides the opportunity to “‘roll up" (sum) the budget and actual costs of the smaller work packages into larger work elements

d)

Serves as a framework for tracking cost and work performance

e)

Can also be used to define communication channels and assist in understanding and coordinating many parts of the project

11.

WBS Coding for "Planning"

a)

1.1

b)

1.1.1

c)

1.2

d)

1.3.4

12.

WBS Coding for "Project Report"

a)

1.5

b)

1.5.1

c)

1.5.2

d)

5.0

13.

WBS Coding for "Assess feasibility"

a)

1.1

b)

1.1.2

c)

1.0

d)

1.1.4

14.

Process name of WBS Code "1.4"

a)

Initiation

b)

Execution

c)

Control

d)

Closure

15.

Process name of WBS Code "1.2.3"

a)

Risk analysis

b)

Set budget

c)

Performance tracking

d)

Documentation