1.

You were a project manager for a software development project. You decided that the agile life-cycle was the most appropriate for your project. Later, when you are in the middle of your project planning, your team member suggested that significant number of deliverable could be developed by using waterfall approach before the plans were being baselined. Later, there were some changes in management which result in a replacement of some of the previous key stakeholders with the new ones. At the regular status meeting, some new key stakeholders complained that agile life-cycle was too radically different from project management methodology which the stakeholders were familiar to, which was waterfall. Which of the following scenario is the most appropriate in the situation above?

a)

A.You should ask the team member to issue a change request to propose hybrid life-cycle to meet the expectation of stakeholders not familiar in agile. The request should be processed in Perform Integrated Change Control.

b)

B.You should provide information regarding agile project life-cycle to the complaining stakeholders.

c)

C.You should issue a change request to propose hybrid life-cycle to optimize the processes for deliverable which can be developed in waterfall approach. The request should be processed in Perform Integrated Change Control.

d)

D.You should analyse the impact if the project life-cycle is replaced to hybrid approach and provide thorough report to the Change Control Board before being processed in the Perform Integrated Change Control.

2.

You were a wedding reception project manager. The organisation you were working for provided holistic wedding services from catering to entertainment. For the next project, a customer requested a stand-up comedy show for his wedding reception. Unfortunately, you just found out that the only comedian in your organisation would not be available at the required date. You worried that you cannot fulfil your customer’s expectations because of this issue. Later, you held a meeting with your team regarding the stand-up comedy request. Fortunately, you found that one of your team members had performed as a stand-up comedian before for his previous employer. However, you thought several improvements were still required before performing in the wedding reception. What would you do next in this situation?

a)

A.Consult your Requirement Trace-ability Matrix to properly collect requirements regarding stand-up comedy request to prevent unrealistic stakeholder expectation.

b)

B.Planning to ask other project manager who have had experience in providing stand-up comedy services in wedding receptions to share his lessons learned register to leverage the knowledge and skill of your comedian candidate.

c)

C.Consult your Risk Register to properly categorise this risk and plan the response.

d)

D.Planning to invite the stand-up comedian to share his/her knowledge to your team member in interaction-rich session between mentor and mentee

3.

You have recently been assigned as a project manager to manage a project that was terminated six months ago because of funding-related issues, but which has since been re-initiated. You want to find out the exact reasons for the termination of the project. You also want to know which deliverable were produced from the terminated project. Which of the following documentation should you review to obtain this information?

a)

A.Project or Phase Closure Document

b)

B.Project Document

c)

C.Supporting document

d)

D.Final product/services

4.

Charlie Chaplin is a seasoned Project Manager at Joker Group. During the execution of the project, a number of changes were requested by the end customer. Flora managed all the change requests efficiently by formulating a Change Management Plan. The Project Management Plan was updated accordingly and a baseline version of the initial scope was created. The list of deliverable was also updated to reflect these changes. The project was successfully completed and a formal closure was executed. Which of the following activities would be included as part of closing the project?

a)

A.Review the Scope Baseline

b)

B.Create a list of the project deliverable

c)

C.Validate the project deliverable

d)

D.Create the Scope Management Plan

5.

The organisation is about to begin a series of similar projects. The projects will be managed consecutively. Each project involves developing an online cooking video focused on foods appropriate to the month in which they will be released. For example, the summer videos will include picnic food and cool treats, and the December video will feature holiday foods for new year party. The project sponsor is adamant that the management plan for each project includes emphasis on making the best possible use of the lessons learned register. He believes that other projects have not been successful because they failed to take advantage of lessons learned from previously completed projects. The lessons learned register should be updated :

a)

A.At the end of each project phase

b)

B.Weekly

c)

C.Throughout the project

d)

D.At the end of the project

6.

Your well planned project is likely to encounter a number of change requests and approved changes during its life cycle. In the change management plan, you have outlined the process that you and others will use to understand the impact of changes. Getting stakeholder acceptance of the decisions related to change on this project is critical, as a failed project could impact shareholder value and the earning projections for the organisations. Your attention is best focused on which of the following regarding changes on your project ?

a)

A.Tracking and recording changes

b)

B.Implementing changes

c)

C.Informing the sponsor changes

d)

D.Preventing unnecessary changes

7.

You have recently joined an organisation that is just beginning to follow formal project management practices. In a meeting, your manager describes your next assignment, a project to select and implement 5G roll out in Zimbabwe. When you request a signed charter authorising you to begin work, the manager suggests you “just draft something”. Which of the following is true about the development of a project charter ?

a)

A.The sponsor creates the project charter, and the project manager approves it

b)

B.The project team creates the project charter, and the PMO approves it

c)

C.The project manager creates the project charter, and the sponsor approves it

d)

D.The executive manager creates the project charter, and the functional manager approves it

8.

You are in the middle of leading a major modification project for an existing manufactured product when you learn that the resources promised at the beginning of the project are not available. According to your plans, these resources will be needed soon, and their unavailability will affect your timeline and possibly other aspects of the project. What is the best thing to do?

a)

A.Explain the impact if the promised resources are not made available

b)

B.Re-plan the project without resources

c)

C.Show how the resources were originally promised to your project

d)

D.Crash the project

9.

You have managed a federal highway construction project, which is intended to improve transportation between north and south regions of the country. In the execution phase, you received many complaints from stakeholders, including the highway transportation agency. At least half these complaints were regarding the quality of the micro texture of the road, and the non-conformance to the quality levels incorporated in the project quality management plan. So far, you have successfully fixed all the reported issues, but you are concerned by this recurrent event. What should you do to avoid future similar issues?

a)

A.Initiate a change request to update the project quality management plan

b)

B.Initiate a preventive action to reduce the probability of negative consequences associated with the poor quality of the road

c)

C.Initiate a defect repair to repair the road or completely pave a new road

d)

D.Initiate a corrective action to bring the future quality of the road in line with the project management plan

10.

Kadir are managing four phases construction project to build a new industrial park. The project size is large and involves a hundred stakeholders and 2 subcontractors. Kadir as his team member who has newbie in large projects like this one ask Kadir about project kick-off meeting when are going to be held?

a)

A.Shortly after initiation

b)

B.At the end of project planning and start of project executing

c)

C.During project initiation

d)

D.At the beginning of each phase

11.

Gombloh are a project manager for a software project. While implementation still ongoing, His customer is requiring a minor change in project scope and expects him to do this without delays and additional costs. He believes that he has adequate authorisation to make the decision by himself, but he is not quite sure. What should be the next steps?

a)

A.You can use contingency reserve to accommodate for this minor change

b)

B.Its minor change, you can approve it to increase customer satisfaction

c)

C.Handle the request according to perform integrated change control process

d)

D.Ignore the request, since the costumer has less power and authority

12.

There is a heavy demand for new houses in your city's expensive neighbourhood. STARK, a construction company, has employed you as a project manager to assess the benefit of building new energy-efficient houses in that neighbourhood, even though it takes more expensive technology to build such houses. You have started gathering data to perform a detailed payback analysis to submit a report to your management. Since the full financial impact of building energy-efficient houses is difficult to estimate, you would like to prepare a rough cost-benefit analysis and include it with the report. Which of the following describes the effort you are undertaking in this scenario?

a)

A.You are developing a cost management plan to provide as an input to the Estimate Costs process.

b)

B.You are developing a business case to provide as an input to the Develop Project Charter process.

c)

C.You are developing a risk management plan to provide as an input to the Perform Quantitative Risk Analysis process.

d)

D.You are developing a cost-benefit analysis to provide as an input to the Plan Risk Management process.

13.

You are in the final phase of a low-cost car manufacturing project. This project has successfully delivered a low-cost car that runs on batteries. However, to close this project and avoid auditing from government authorities, it must demonstrably comply with many administrative standards. Since your organisation possesses experts who know closing procedures and standards, you want to use them to close this project. This effort is an instance of :

a)

A.Using organisational process assets in closing the project

b)

B.Using enterprise environmental factors in closing the project

c)

C.Using expert judgement in closing the project

d)

D.Poor project management practice

14.

Munaroh has recently been assigned as the project manager for a new shopping mall construction project. Since the project will span well over five years, Munaroh is a bit hesitant to use the current market rates for estimating construction materials cost. The prices have been steadily increasing and the current market rates might not remain valid in the future. Which of the following techniques can Munaroh apply to determine her project budget?

a)

A.Determine the cost of the project using current market rates and increase the total budget by some factor.

b)

B.Compute the Net Present Value of the cost of materials and use that to determine the project budget.

c)

C.Use Rolling Wave Planning to determine the budget as the project progresses.

d)

D.Conduct a trend analysis on the cost of materials and use that to extrapolate the cost of materials in the future.

15.

The project is nearing its end. The executives are anxious to assign the project manager to other projects. However, before moving on, the project manager has to deliver the final product to the customer. What should the project manager do first?

a)

A.Reassign resources to other projects

b)

B.Obtain stakeholder approval

c)

C.Present a list of quality concerns to the customer

d)

D.Close the project

16.

You are in the closing phase of your project and one of your colleagues has practised the executions of many projects including their closure. This colleague advised you to review the business case. Why did he give this advice?

a)

A.To determine if the expected outcomes from the economic feasibility study used to justify the project occurred

b)

B.To ensure that it is feasible to have this project

c)

C.No need to review the business case at this stage as it was created very early before the project started

d)

D.None of the above

17.

Sule has been managing a project for Kokoronotomo Oil Corp. This project involves redesigning filling stations across the state. The redesign involves new gas pumps, security cameras, convenience stores, and use of environmentally friendly materials in the construction. While the redesigning work proceeds, Sule design engineer suggests a secondary alarm system for gas pumps to alert the attendant in case of a spill. Although this suggestion is not in the project requirements, Sule is impressed with the engineer’s recommendation. What should be the next step for Sule with regard to the engineer’s suggestion?

a)

A.Approve his recommendation and allocate resources and funds

b)

B.Initiate the formal change control process to find the impact of his recommendation

c)

C.Create an issue log to document the engineer‘s suggestion for future use

d)

D.Reject his recommendation as it requires additional funding

18.

You are a consulting project manager and an investment bank has a contract with you to run a large information technology project that is expected to last 15 months. During the Direct and Manage Project Work process, you discover that several regulatory requirements were addressed in the project management plan but missed from the scope statement. Failure to meet these requirements could result in legal action against the company. However, implementing the technology to comply with these regulations could exceed the budget and scope of the project and result in the cancellation of the project. What should you do?

a)

A.Do not do anything as these requirements are not a part of the scope baseline

b)

B.Request additional funds to implement these requirements

c)

C.This is a classic example of scope creep and such requirements must be ignored

d)

D.Submit a change request to incorporate the missed requirements in the project's scope

19.

You are working on an information technology project as a project manager to develop a shopping website for your customers. Some key stakeholders in the project suggested scope changes to improve the website’s look and feel. Your team has analysed the impact of these changes and presented the analysis to the Change Control Board (CCB) for approval. What should be your next step if the CCB accepts all proposed changes?

a)

A.Implement the change request and update stakeholders

b)

B.Review change control board decisions and inform stakeholders for their input

c)

C.Revise cost estimates, schedule dates, resource requirements, and planning documents

d)

D.Conduct a team status meeting to update the progress on change requests

20.

You have just returned from the weekly change control board meeting where you presented the requested changes to the employee move project. Five changes were approved, but one was denied. You are now updating the project management plan to incorporate the changes. In which project management process would this be done?

a)

A.Planning

b)

B.Direct and Manage Project Work

c)

C.Monitor and Control Project Work

d)

D.Executing