1.

Understanding customers’ and potential customers’ needs through market research is one of the best ways to obtain

a)

Better profit

b)

Project visibility

c)

sustainable competitive advantage

d)

information to guide decision making

2.

Marketing without research, customer or market insight is guesswork which may give result of:

a)

Low risk

b)

Medium risk

c)

High risk

d)

Depends on the situation

3.

Niche markets within the construction industry likely do not have available secondary research, thus requiring primary research.

a)

True

b)

False

4.

There are many types of market research, often categorized as below EXCEPT:

a)

primary vs. secondary research

b)

quantitative or qualitative research

c)

syndicated research

d)

experimental research

5.

Secondary research is: information collected directly from the source, often custom to the project and typically includes surveys, interviews, and focus groups.

a)

True

b)

False

6.

Below are examples online survey for market research EXCEPT :

a)

LinkedIn Polls

b)

SurveyGizmo

c)

Flipgrid

d)

Polldaddy

7.

Businesses such as restaurants and service companies often X method to gather feedback about consumer experience

a)

Interview

b)

Questionnaire

c)

Observation

d)

Focus group

8.

X can prevent a business from making a costly mistake such as launching a new product or service that doesn't fulfill a need in the market

a)

oral market survey

b)

surveys electronically via email,

c)

social media

d)

Analysis of market survey

9.

When should you do a feasibility study?

a)

after the business case has been completed

b)

after the business case has been started

c)

after the business case is half way done

d)

none of the above

10.

Prepare a Projected Income Statement is one of the steps for feasibility study

a)

True

b)

False

11.

Best Practices for a Feasibility Study, EXCEPT

a)

involve the appropriate stakeholders to get their feedback

b)

Use market research to further data collection

c)

Do homework and ask questions to make sure data is solid

d)

Avoid using historical data

12.

Feasibility Report Template contains following EXCEPT:

a)

Technology considerations

b)

Organization structure

c)

Financial projections

d)

Procurement choice

13.

Choose the most critical factor for a feasibility study to be carried out

a)

Expanding into an unfamiliar market or territory (overseas)

b)

Embarking on a major new business investment

c)

Investing in new technology or operating approaches

d)

Opening a new facility, chain of offices or stores

14.

A proper feasibility study should be limited in scope.

a)

True

b)

False

15.

Logistics, environment, laws and regulations area examples of constraints that fall into :

a)

Internal project constraints

b)

Internal corporate constraints

c)

External constraints

d)

All of the above

16.

“Items describing the contractor’s general obligation and management arrangements. The contractor inserts lump sumps against the items such as provisions of site huts, utilities, hoardings, security and the like”

a)

Provisional sums

b)

Prime cost sums

c)

Specification

d)

Preliminaries

17.

“Clauses specifying the materials and workmanship for each trade or work-section. The quality and standards refer to the appropriate building standards and codes of practise”

a)

Provisional sums

b)

Prime cost sums

c)

Specification

d)

Preliminaries

18.

“the employer inserts the likely amounts for works that are to be carried out by NSCs or for goods to be supplied by nominated suppliers (NSCs) under the direction of the contractor. The contractor prices for the profit and attendance for such works.”

a)

Provisional sums

b)

Prime cost sums

c)

Specification

d)

Preliminaries

19.

“the employer inserts an amount to be included in the tender sum for designated work that cannot be entirely foreseen, defined or detailed at the time of tendering.”

a)

Provisional sums

b)

Prime cost sums

c)

Specification

d)

Preliminaries

20.

The statement best describe the Cost plus contract:

a)

This type of contract involves a total fixed priced for all construction-related activities

b)

usually preferred if the project scope is not clear, or has not been defined. The owner and the contractor must establish an agreed hourly or daily rate, including additional expenses that could arise in the construction process.

c)

can easily be adjusted up and/or down during scope changes, making it easier for the owner and the builder to reach into agreements during change orders

d)

This type of contract involves payment of the actual costs, purchases or other expenses generated directly from the construction activity.