wayground logo

Free Printable Worksheets

NEW

Font size

S
M
L
XL
Worksheets

QUIZ 3 : TOPIC 10 [Standard Costing & Variance Analysis]

Total questions: 20

Worksheet time: 31mins

Name
Class
Date
1.

Given that:

Variable Overhead Expenditure Variance = 960F

Variable Overhead Efficiency Variance = 600F

Fixed Overhead Budget Variance = 2,100F

Fixed Overhead Volume Variance = 2,600UF,

What would be the amount of variable overhead variance and fixed overhead variance?

a)

Variable overhead variance 1,560F; Fixed overhead variance 500UF

b)

Variable overhead variance 1,560F; Fixed overhead variance 4,700UF

c)

Variable overhead variance 600F; Fixed overhead variance 2,100F

d)

Variable overhead variance 1,650F; Fixed overhead variance 5000UF

2.

Given that:

Variable Overhead Expenditure Variance = 960F

Variable Overhead Efficiency Variance = 600F

Fixed Overhead Budget Variance = 2,100F

Fixed Overhead Volume Variance = 2,600UF,

How much manufacturing overhead is under/over-applied?

a)

RM1,060 Under-applied

b)

RM1,060 Over-applied

c)

RM360 Under-applied

d)

RM360 Over-applied

3.

Determine the material price variance?

a)

RM2,425 Favorable

b)

RM2,425 Unfavorable

c)

RM196,425 Favorable

d)

RM195,425 Unfavorable

4.

Determine the material usage variance?

a)

RM46,075 Favorable

b)

RM46,075 Unfavorable

c)

RM11,500 Favorable

d)

RM11,500 Unfavorable

5.

How much is the actual hours worked?

a)

4,200

b)

4,800

c)

3,600

6.

How much is the actual price?

a)

RM2

b)

RM6

c)

RM2.10

7.

How much is the standard price?

a)

RM2

b)

RM6

c)

RM2.10

8.

Determine the material price variance.

a)

RM2,500 Favorable

b)

RM2,500 Unfavorable

c)

RM2,400 Favorable

d)

RM2,400 Unfavorable

9.

Determine the material usage variance.

a)

RM2,000 Favorable

b)

RM2,000 Unfavorable

c)

RM2,400 Favorable

d)

RM2,400 Unfavorable

10.

Determine the labour rate variance.

a)

RM8,500 Favorable

b)

RM8,500 Unfavorable

c)

RM68,000 Favorable

d)

RM68,000 Unfavorable

11.

Determine the labour efficiency variance.

a)

RM3,000 Favorable

b)

RM3,000 Unfavorable

c)

RM6,000 Favorable

d)

RM6,000 Unfavorable

12.

An unfavorable labour efficiency variance indicates that

a)

the actual labour rate was higher than the standard labour rate per direct labour hours

b)

overtime labour was utilised during this period

c)

the actual direct labour hours exceeded standard direct labour hours for the production

d)

the total labour variable must be unfavourable

13.

The materials price variance may be computed by

a)

(Actual price - Standard price) X Actual quantity

b)

(Actual price - Standard price) X Standard quantity

c)

(Actual quantity - Standard quantity) X Actual price

d)

(Actual quantity - Standard quantity) X Standard price

14.

The labour rate variance may be computed by

a)

(Actual rate - Standard hours) X Actual hours

b)

(Actual hours - Standard hours) X Standard price

c)

(Actual hours - Standard rate) X Actual hours

d)

(Actual rate - Standard rate) x Acutal hours worked hours

15.

An unfavorable materials quantity variance may be the result of

a)

a greater than anticipated waste in the manufacturing process

b)

an increase in the cost per unit of raw materials

c)

a decrease in the cost per unit of raw materials

d)

a lower than anticipated waste in the manufacturing process

16.

The following information relates to product A:


Quantity / Unit Price Cost Per Unit

Material (3kg @ RM23) RM69

Labour (2 hours@RM20) RM40


Budgeted production is 1,000 units.

Actual production is 900 units.

Actual inputs were as follows:


Material 2,650 kg @ RM66,250

Labour 1840 hours @ RM34,960


The material price variance is:

a)

RM5,300 F

b)

RM4,150 F

c)

RM5,300 UF

d)

RM4,150 UF

17.

Quantity / Unit Price Cost Per Unit

Material (3kg @RM23) RM69

Labour (2 hours@RM20) RM40


Budgeted production is 1,000 units.

Actual production is 900 units.


Actual inputs were as follows:


Material 2,650 kg @ RM66,250

Labour 1840 hours @ RM34,960


Compute Material Usage Variance

a)

RM1,250 F

b)

RM1,150 F

c)

RM1,250 UF

d)

RM1,150 UF

18.

Quantity / Unit Price Cost Per Unit

Material (3kg @ RM23) RM69

Labour (2 hours @ RM20) RM40


Budgeted production is 1,000 units.

Actual production is 900 units.


Actual inputs were as follows:


Material 2,650 kg @ RM66,250

Labour 1840 hours @ RM34,960


Compute the labour rate variance is:

a)

RM1,040 UF

b)

RM1,840 F

c)

RM1,040 F

d)

RM1,840 UF

19.

Quantity / Unit Price Cost Per Unit

Material (3kg @ RM23) RM69

Labour (2 hours @ RM20) RM40


Budgeted production is 1,000 units.

Actual production is 900 units.


Actual inputs were as follows:


Material 2,650 kg @ RM66,250

Labour 1840 hours @ RM34,960


Compute the labour usage variance is:

a)

RM800 F

b)

RM800 UF

c)

RM760 UF

d)

RM760 F

20.

During July actual labour costs amounted to RM19,800, the standard rate was RM4.50 per hour and the labour rate variance amounted to RM225 unfavorable. The actual hours worked were:

a)

4,000

b)

4,350

c)

4,400

d)

4,450