WorksheetsProject Scheduling
Total questions: 15
Worksheet time: 8mins
This set of data is correct:
ES = 10, EF =9, t=1
True
False
In Critical Path Method, the project completion period is the EF of last activities.
True
False
Changing the duration of a critical activity will not affect the overall completion time.
True
False
The starting activities that have no predecessor cannot be carried out in parallel.
True
False
Changing the duration of a non-critical activity will not affect the overall completion time, provided the revised float is positive.
True
False
The backward pass calculation cannot proceed if the forward pass had not completed.
True
False
The critical path activities can be identified only after all the floats were determined.
True
False
To start the backward pass computation, the LF is equal to EF for the last activity.
True
False
Organizing a trip to Paris for the upcoming school holiday is a project
True
False
Organizing a tour of multiple cities for Christmas holiday is an operation.
True
False
In Critical Path Method, the project completion period is the sum of all of all activities duration.
True
False
Develop an App for smartphone by hired programmer is a project
True
False
The LS and LF is the result of forward pass calculation.
True
False
LS = LF - t
True
False
Activities on critical path will have positive float.
True
False