wayground logo

Free Printable Worksheets

Font size

S
M
L
XL
Worksheets

Project Scheduling

Total questions: 15

Worksheet time: 8mins

Name
Class
Date
1.

This set of data is correct:

ES = 10, EF =9, t=1

a)

True

b)

False

2.

In Critical Path Method, the project completion period is the EF of last activities.

a)

True

b)

False

3.

Changing the duration of a critical activity will not affect the overall completion time.

a)

True

b)

False

4.

The starting activities that have no predecessor cannot be carried out in parallel.

a)

True

b)

False

5.

Changing the duration of a non-critical activity will not affect the overall completion time, provided the revised float is positive.

a)

True

b)

False

6.

The backward pass calculation cannot proceed if the forward pass had not completed.

a)

True

b)

False

7.

The critical path activities can be identified only after all the floats were determined.

a)

True

b)

False

8.

To start the backward pass computation, the LF is equal to EF for the last activity.

a)

True

b)

False

9.

Organizing a trip to Paris for the upcoming school holiday is a project

a)

True

b)

False

10.

Organizing a tour of multiple cities for Christmas holiday is an operation.

a)

True

b)

False

11.

In Critical Path Method, the project completion period is the sum of all of all activities duration.

a)

True

b)

False

12.

Develop an App for smartphone by hired programmer is a project

a)

True

b)

False

13.

The LS and LF is the result of forward pass calculation.

a)

True

b)

False

14.

LS = LF - t

a)

True

b)

False

15.

Activities on critical path will have positive float.

a)

True

b)

False