What is the INTERVAL of class depth classification for the depth which exceeds 4.00m?
0.25m
1.00m
2.00m
4.00m
What is the Unit of Measurement (UoM) for basement excavation works?
M
M2
M2 stating the thickness
M3
Which clause of SMM2 described the provision of stating the "dimension on plan" of the excavation works?
Clause D.10
Clause D.12.2
Clause D.12.6
Clause D.12.8
Which of the following item is "NOT" measured as an "Extra Over"?
Excavation to receive services piping
Excavation around services piping
Breaking up concrete on surface excavation
Breaking up concrete met within excavation
What is the Unit of Measurement (UoM) an excavation works around/across the services pipe(s)?
M
M, stating as Extra Over
No
No, stating as Extra Over
The followings must be described in the description of excavation works alongside the service pipes, EXCLUDING
Starting level
Size of the service pipe(s)
Type of the service pipe(s)
Radius of the service pipe(s)
Which of the following clause stating the requirement of the "radius of excavation"?
Clause D.12.2
Clause D.12.3
Clause D.12.12
Clause D.12.13
Which of the following work require the "No" of excavation works in the description?
D.12.2
D.12.5
D.12.6
D.12.9
What is the Unit of Measurement (UoM) for breaking up brick paving jogging track?
M
M2, stating as Extra Over
M3
M3, stating as Extra Over
The followings starting levels were described in Clause D.11, EXCEPT,
Formation Level
Ground Level
Formation Level
Classification Level