Certificate of Completion & Compliance by PSP

Total questions: 12

Worksheet time: 5mins

Name
Class
Date
1.

At the end of today's lesson, you should be able to achieve the following learning outcomes: (you may choose more than one options)

a)

Understand the necessity for a Building Plan Approval and its general requirements and process

b)

understand the Code of Conduct for Professional Engineer

c)

understand who is the Principal Submitting Person

d)

understand what constitute of Certificate of Completion and Compliance (CCC)

2.

Previously, before April 2007, Certificate of Fitness for Occupation (CFO) was issued by local authorities before being replaced by Certificate of Completion and Compliance (CCC)

a)

True

b)

False

3.

The CCC has to be issued by the Principal Submitting Person (PSP)

a)

False

b)

True

4.

The following person (s) can be the PSP depending on the type of projects agreed between Board of Architects Malaysia and Board of Engineers Malaysia (you may choose more than one option)

a)

Professional Architect (Ar.)

b)

Professional Civil Engineer (Ir.)

c)

Professional Surveyor (Sr)

d)

Professional Technologist (Ts)

5.

The followings are the duties of PSP. (You may choose more than one option).

a)

To prepare & present planning and building plans to PBT for approval & Inform PBT of the commencement of construction works on site.

b)

Issue CFO upon satisfactory completion of the works and after all conditions have been complied with, confirming the building is safe and fit for occupation.

c)

Supervise construction works at site and ensure that laws and technical conditions of the PBT are followed.

d)

Report building breaches, explain reasons of breach and ensure breach is rectified during construction.

e)

Ensure Form Gs are duly certified by bona fide Professionals practising through ACPs/ECPs registered with BAM/BEM, at various stages of the works and when all the essential services have been provided.

6.

Select the common offences by PSP that warrant a penalty under Section 70(27) of Street, Drainage and Building Act with a fine not exceeding RM 250K or to imprisonment not exceeding 10 years or to both.

a)

Issues a CCC without all the relevant forms

b)

Not a PSP but issues a CCC

c)

Issues CCC in contravention of a direction by PBT

d)

Make any false or fraudulent declarations or uses any forged, altered or counterfeit declaration, certificate

e)

Allowed the building to be occupied with CCC

7.

Form F1 (Partial Completion) can be issued only when phased completion of an integrated development has been submitted for approval by PBT at Building Plan approval stage.

a)

True

b)

False

8.

The following works are correct for form G EXCEPT

a)

Form G1 - Earthworks

b)

FORM G 2 - Setting Out

c)

Form G3 - Structural

d)

FORM G12 - Building

e)

Form G11 - Lift/Escalator Installation

9.

Select the correct BEM circular that allows PEPC endorsement of CCC

a)
b)
10.

Select the correct discipline of signing SP in Form G (you may choose more than one option)

a)

G4: Structure - Civil Engineer

b)

G12: Building - Architect or Civil Engineer

c)

G9: Active Fire: Architect or Civil Engineer

d)

G10: Mechanical Ventilation: Mechanical Engineer

e)

G20: Telecommunication: Electrical Engineer

11.

Under the Uniform Building By-Laws (Amendment 2007), the Principal Submitting Person (PSP) who is also defined as the Qualified Person may submit Building Plan to the local authority and thereafter issue the Certificate of Completion and Compliance (CCC) upon its completion together with all 21 Form Gs (G1-G21) fully certified by the respective Submitting Persons (SP) or PSP

a)

False

b)

True

12.

The following PSP who have committed offences can be deregistered as professionals:

I) Ir. Ahmad a PEPC failed to deposit copies of CCC to PBT and BEM.

II) Ar. Allen, a Prof. Architect allowed the building to be occupied without CCC.

III) Ir. Siti, a PEPC (civil) signed Form G1

IV) Ir. Elle, a PEPC (civil) falsified the receipt date stamp of PBT OSC for Form G13 to G21 in order to mislead the developer.

V) Ir. Peter, a PEPC (mechanical) use of forged PE stamp to sign Form G10.

a)

I & III

b)

All of the above

c)

I, II, IV & V

d)

I, II & III