WorksheetsProject Management Internal II
Total questions: 10
Worksheet time: 7mins
Benefit of CPM...
A) Provides a graphical view of the Project.
B) Can't predict the time required to complete the project.
C) Easy manage a complex work.
D) Both A and C
Full form of PIs
Project Instructors
Performance Indicators
Performance Instructors
Project Indicators
Which activity aims to maximize success of the project ?
Performance monitoring
CPM
PERT
Project Audit
Find out the Odd one.
Assure Quality of products and services.
Identify the business risk
Learn
Neglect Project Performance
Project Management Information System helps to
A) To Plan
B) Monitor
C) Project Audit
D) Both A and B
WBS Stands for
Work Breakdown Structure
Work Break Structure
Work Breaking System
Work Breaking Structure
Which are Key Project Resources of project ?
Materials, Time, Budget
People, Equipment, Time, Materials
People, Time, Materials
Equipment, Time, Budget, People
Who is the inventor of Gantt Chart
Hilary Gantt
Hilon Gantt
Henry Gantt
Harry Gantt
Define Start -to - Start activity
An activity must start before the next activity can finish.
An activity must start before the next activity can start.
An activity must start after the next activity can start.
An activity must finish before the next activity can start.
Correct example for External milestones..
Audit
Teams/ Press
PIs
PMIS