1.

The following are the Knowledge Areas in Project Management, EXCEPT:

a)

Project Integration Management

b)

Project Scope Management

c)

Project Time Management

d)

Project Cost Management

2.

How many Knowledge Areas in Project Management?

a)

10

b)

9

c)

8

3.

Project Management Body of Knowledge (PMBOK) is:

a)

The association that represents the Project Managers

b)

The book that presents guidelines for project management

c)

The person who acts as a project manager

4.

Which of the following is TRUE about PMBOK?

a)

Has 49 processes, 5 process groups and 10 knowledge areas

b)

Has 49 process groups, 5 processes and 10 knowledge areas

c)

Has 47 process groups, 5 phases and 9 knowledge areas

5.

Project management is the application of the following, EXCEPT:

a)

Knowledge

b)

Skill

c)

Tool

d)

Information

e)

Techniques

6.

Project management aims to meet or exceed ________ needs and expectation:

a)

Client

b)

Customer

c)

Stakeholder

d)

Employer

7.

Effective is about:

a)

Doing the right things

b)

Doing things right

c)

Doing things right effectively

8.

Characteristics of a project are as follows EXCEPT:

a)

Has specific objectives

b)

Has temporary undertakings

c)

Produce many outcomes

d)

Subject to a lot of changes

9.

Characteristics of an operation are as follows EXCEPT:

a)

Use the existing system

b)

Involve repetitive work

c)

Produce unique product

d)

Focus on “maintaining”

10.

The following are the process groups in Project Management EXCEPT:

a)

Initiating

b)

Planning

c)

Executing

d)

Maintaining