Scrum-Agile Quiz

Total questions: 49

Worksheet time: 34mins

Name
Class
Date
1.

Scrum Theory: Scrum is not a process or technique

a)

True: it is not a process, technique or method but a framework for process and technique

b)

False: it is a process and technique to use for work

2.

What is one of the three roles in Scrum?

a)

Product Owner

b)

Program Manager

c)

CSL

d)

Team Lead

3.

What is the main way in which teams work?

a)

Competition

b)

Collaboration

c)

Cooperation

d)

Coalition

4.

How should user stories be written?

a)

The system shall…

b)

Given...when…then…

c)

As a…I want…so that...

d)

If inputs…then outputs…

5.

True or False: it a good practice to have two product owners?

a)

True

b)

False

6.

What part of the capacity of the Development Team does Product Backlog refinement usually consume?

a)

Not more than 5%

b)

Not more than 10%

c)

Not more than 20%

d)

The Development team is not authorized for Product Backlog Refinement

7.

True or False: The structure of the Daily Scrum is well-defined and constant. Every team member should answer the three main questions: 1. What did I do yesterday? 2. What will I do today? 3. Is there anything blocking me from my goals for today

a)

True: there is a defined structure we must follow each time.

b)

False: there is no prescribed structure it can happen different ways as long as it focuses on progress toward the Sprint Goal. It can be questions or discussion based.

8.

How does the Scrum master serve the Development Team?

a)

Adding or removing developers from the Development Team in accordance with team velocity changes.

b)

Helping the Development Team as the team leader.

c)

Helping the Development Team to create high-value products.

d)

Coaching the Development Team in self-organization and cross-functionality.

e)

Removing impediments to the Development Team's progress.

9.

Who is responsible for the creation of the Definition of "Done"?

a)

The Product Owner

b)

The Scrum Team

c)

The Development Team

d)

The Scrum Master

10.

What should be taken into account for the Definition of "Done"? Select the two most appropriate items.

a)

Definition of "Done" of other Scrum Teams working on the same Product

b)

Conventions, standards and guidelines of the Organization

c)

Advice of the Scrum Master

d)

Experience of the Product Owner

e)

Definition of "Done" of other Scrum Teams working on other products

11.

Scrum Artifacts: What is the "increment"?

a)

All items in the Sprint Backlog that could be released regardless of whether the Product Owner decides to actually do it.

b)

All "Done" items in the Sprint Backlog

c)

The sum of all the Product Backlog items completed during the Sprint and the value of the increments of all previous Sprints

d)

The sum of all the Product Backlog items completed during the Sprint.

12.

Scrum Artifacts: What are the Product Backlog features? Select three.

a)

When the final version of a product is rolled out, its Product Backlog is dismissed.

b)

It is dynamic.

c)

It is never complete.

d)

A product backlog could be closed when it contains no items to include into the next Sprint.

e)

As long as a product exists, its product backlog also exists.

13.

Who is allowed to participate in the Daily Scrum?

a)

The Product Owner

b)

The Key Stakeholders

c)

The Scrum Maste

d)

The Development Team

14.

Scrum Events: Who has the authority to cancel the Sprint?

a)

The Product Owner and the Scrum Master

b)

The Development Team

c)

The Product Owner

d)

The Scrum Master

e)

The Key Stakeholders

15.

Scrum Events: The Daily Scrum always should take exactly 15 minutes. For example, if your team managed doing it in 5 minutes, you should spend 10 more minutes on some useful team activity like Product Backlog refinement, but not more.

a)

True- we must meet the time-box requirement

b)

False- the timebox is the maximum time but there is no minimum time. The team may get done quicker as time goes on.

16.

Scrum Artifacts: Who is responsible for coping with incomplete artifact transparency?

a)

The Product Owner

b)

The Scrum Team

c)

The Development Team

d)

The Scrum Master

17.

Scrum Theory: What is the essence of Scrum? Select the most appropriate option.

a)

A small team of people that is highly flexible and adaptive.

b)

The Scrum Guide

c)

The Development Team

d)

The Scrum Master and the Product Owner

18.

Scrum Artifacts: What belongs solely to the Development Team?

a)

The Sprint Backlog

b)

The Product Backlog

c)

The Definition of Done

d)

The Increment

19.

Scrum Artifacts: Who is responsible for monitoring progress toward high-level goals?

a)

The Product Owner

b)

The Scrum Master and The Development Team

c)

The Product Owner and the Development Team

d)

The Development Team

e)

The Scrum Master & Scrum Team

20.

Scrum Artifacts: What is the Sprint Backlog?

a)

The Product Backlog items selected for this Sprint plus the plan for delivering them.

b)

The Product Backlog items selected for this Sprint

c)

The Product Backlog items selected for this Sprint plus the Team Backlog items

d)

The plan for delivering Product Backlog items

21.

Scrum Theory: Where can Scrum be used? Check all that are correct

a)

Development of almost everything we use in our daily lives as individuals and societies

b)

Research and identifying of viable markets, technologies and product capabilities

c)

Development of software and hardware

d)

Development and sustaining of cloud and other operational environments

e)

Managing of the operation of an organization & Development of products and enhancements

22.

Scrum Artifacts: Who creates the increment?

a)

The Development Team and the Product Owner

b)

The Development Team

c)

The Scrum Master

d)

The Scrum Team

e)

The Product Owner

23.

Scrum Theory: It is normal to have a “hardening” Sprint to remove all technical debt and prepare the Product for upcoming release.

a)

True

b)

False

24.

Scrum Artifacts: Who is allowed to make changes in the Product Backlog? Select two options.

a)

The Key Stakeholders

b)

The Product Owner

c)

The Development Team but with permission of the Product Owner

d)

Anyone

e)

The Scrum Master

25.

Scrum Theory: Definition of “Done” is created during the first Sprint and remains unchanged until the Product release.

a)

True

b)

False

26.

Scrum Theory: What does Burn-down Chart show?

a)

The evolution of the amount of uncertainty during a project

b)

Dependencies, start times and stop times for project tasks

c)

How much work remains till the end of the Sprint

d)

Hierarchy of tasks that comprise a project

27.

Scrum Events: The purpose of the Sprint Retrospective is to (select three):

a)

Inspect how the last Sprint went with regards to people, relationships, process, and tools

b)

Identify and order the major items that went well and potential improvements

c)

Create a plan for implementing improvements to the way the Scrum Team does its work

d)

Get feedback from the Key Stakeholders invited by the Product Owner

e)

Get technical or domain advice from specialists invited by The Development Team or The Scrum Master

28.

Scrum Artifacts: Who is responsible for tracking the total work remaining in the Sprint Backlog to project the likelihood of achieving the Sprint Goal?

a)

The Scrum Team

b)

The Development Team

c)

The Scrum Master

d)

The Product Owner and the Development Team

e)

The Product Owner

29.

Scrum Theory: What are the three pillars that uphold Scrum?

a)

Agility

b)

Inspection

c)

Self-organization

d)

Adaptation

e)

Transparency

30.

Scrum Team: What are the three most applicable characteristics of the Product Owner?

a)

Lead Scrum evangelist in the Organization

b)

Product Marketplace Expert

c)

Facilitator of Scrum events

d)

Lead Facilitator of Key Stakeholder Involvement

e)

Product Value Maximizer

31.

Scrum Artifacts: The Sprint Backlog is created at the Sprint Planning. It is prohibited to add new work into the Sprint Backlog later by the Development Team.

a)

True

b)

False

32.

Scrum Theory: It is a good practice to have from time to time to have a special technical Sprint that consists only of tasks removing the technical debt without implementing any new functionality.

a)

True

b)

False

33.

Scrum Artifacts: All Development Teams working on the same Product should use the same Product Backlog.

a)

True

b)

False

34.

Scrum Artifacts: Imagine the following situation. At the Sprint Retrospective meeting the Scrum Team identified some improvements that can be done. What should the Scrum Team do? Select the best option.

a)

Make sure the Sprint Backlog for the next Sprint includes all the improvements.

b)

Make sure the Sprint Backlog for the next Sprint includes at least one high priority process improvement.

c)

Assign responsible team members for every improvement. Check the progress at the next Retrospective.

d)

Assign a responsible team member for at least one improvement. Check the progress at the next Retrospective.

35.

Scrum Artifacts: What could be a source of requirements for any changes to be made to the product?

a)

The Key Stakeholders

b)

The Product Backlog

c)

The CEO of the Organization

36.

Scrum Theory: What does Cone of Uncertainty show?

a)

How much work remains till the end of the Sprint

b)

Dependencies, start times and stop times for project tasks

c)

Hierarchy of tasks that comprise a project

d)

How much is known about the Product over time

37.

Scrum Artifacts: What is the order of the items in the Product Backlog?

a)

The less clear items at the top

b)

Alphabetical

c)

Less valuable and most unclear items at the bottom

d)

The recently added items at the top

38.

Scrum Artifacts: What are the Scrum Artifacts? Select all applicable items

a)

The list of removed impediments

b)

The Sprint Goal

c)

Product Backlog

d)

Sprint Backlog

e)

Increment

39.

Scrum Theory: All the Scrum Teams working on the same product should have the same Sprint length.

a)

True

b)

False

40.

Scrum Theory: Select the five Scrum Values.

a)

Commitment & Courage

b)

Agility

c)

Effectiveness & Self Organization

d)

Focus & Respect

e)

Openness

41.

Scrum Team: Who is responsible for promoting and supporting Scrum? Select the best choice.

a)

The Scrum Team

b)

The Development Team

c)

The Scrum Master and Product Owner

d)

The Product Owner

e)

The Scrum Master

42.

Scrum Events: What are the time-boxes for the Sprint Review and the Sprint Retrospective?

a)

3 hour time-box for each

b)

3 and 4 hours respectively

c)

4 and 3 hours respectively

d)

4 hour time-box for each

43.

Scrum Artifacts: Who is responsible for all estimates in the Product Backlog?

a)

The Product Owner

b)

The Scrum Team

c)

The Product Owner and the Development Team

d)

The Development Team

e)

The Scrum Master

44.

Scrum Artifacts: How does Definition of “Done” help the Scrum Team? Select three most applicable items.

a)

DoD helps in inspection and adaptation

b)

DoD guides the Development Team in knowing how many Product Backlog items it can select during a Sprint Planning

c)

DoD helps to calculate velocity of the Scrum Team

d)

DoD is used to assess when work is complete on the product Increment

e)

DoD ensures artifact transparency

45.

Scrum Artifacts: Who is responsible for the Product Backlog?

a)

The Product Owner and The Scrum Master

b)

The Product Owner and The Development Team

c)

The Scrum Master and The Development Team

d)

The Development Team

e)

The Product Owner

46.

Scrum Team: What are the three main qualities the team model in Scrum is designed to optimize?

a)

Creativity

b)

Competence

c)

Productivity

d)

Responsibility

e)

Flexibility

47.

Scrum Theory: What does the word “development” mean in the context of Scrum? Select the best option.

a)

Complex work that can include all the suggested options and even more

b)

Product development, its releasing and sustaining

c)

Development of an operational environment for the Product

d)

Research and identifying of viable markets, technologies, and Product capabilities

e)

Software and hardware development

48.

Scrum Theory: Scrum recommends using only those Scrum components and rules which suit most for a particular project.

a)

True

b)

False

49.

Scrum Events: Who participates in the Sprint Planning? Select three.

a)

The Team Manage

b)

The Development Team

c)

The Scrum Master

d)

The Product Owner

e)

The Key Stakeholders