DMAIC DMADV

Total questions: 13

Worksheet time: 6mins

Name
Class
Date
1.

DMADV stands for

a)

design measure analyse define validate

b)

define measure analyse design verify

c)

define measure analyse design validate

d)

design measure analyse define verify

2.

we use DMADV if ...

a)

it can't be analyse in DMAIC

b)

the cpk value below 1.33

c)

any special cause

d)

the process doesn't exist

3.

we have to maintain MSA value >90% in .... stage

a)

control

b)

measure

c)

validate

d)

analyse

4.

DMADV is a .... approach/method

a)

reengineering

b)

continous improvement

5.

which of the following tools are not used in DMAIC ?

a)

pFMEA

b)

MSA

c)

Control Charts

d)

dFMEA

6.

which of the following tools used for DMADV and DMAIC

a)

MSA, Control Chart, Preliminary Control Plan

b)

Pokayoke, pFMEA, MSA plan, prototype control plan

c)

QFD, dFMEA, MSA

d)

MSA, Control Chart, pFMEA, Pokayoke

7.

Verify cause & effect relationship and to determine the root cause(s) of the defect is the definition of ... stage

a)

analyse

b)

verify

c)

control

d)

design

8.

The following tools can be used in define stage, except

a)

Pareto Chart

b)

SPC

c)

Bar Graph

d)

QFD

9.

These tools can be used in analyse (DMADV) stage ...

a)

Pokayoke, MSA, Control Charts

b)

Predictive Models, Simulation Prototype, Pilot Runs

c)

Regression, Correlation, Hypothesis Testing

d)

Analytical Hierarchy, QFD

10.

MSA Tools can be used in .... stages

a)

Control, Measure, Design

b)

Control, Measure, Verify

c)

Measure, Analyse, Control

d)

Measure, Analyse, Verify

11.

the process is capable if

a)

gage rnr below 10 or cpk value is 1.33 and MSA above 90%

b)

gage rnr is 10 or cpk value is 1.33

c)

cpk value is 1.33 or MSA above 90%

d)

gage rnr below 10 and cpk value is 1.33

12.

To ensure that any deviations from target are corrected before producing defect is definition of

a)

verify stage

b)

control stage

c)

improve stage

d)

design stage

13.

The design, set up pilot runs, implement the production process and hand it over to the process owners is the definition of ....

a)

Analyse Stage

b)

Design Stage

c)

Verify Stage

d)

Improve stage