Total questions: 6
Worksheet time: 3mins
An agile project with a single sponsor is now being replaced by a project management committee.The committee will be have 8 members.
Change your communication to account for the new sponsor/stakeholder structure.
Stick to the original project since it was made to include everyone.
Plan a meeting with a new committee and the team,but continue to follow the original project plan.
Be sure that the committee members receive all reports
While working on a large national project,few members are worried about sign-off. How should the project manager obtain appropriate sign-off on the acceptance of project deliveries.
Ask the project sponsor to sign-off.
Ask the team lead for a sign-off
Ask the senior management for a sign-off.
No sign-off is needed.
A project has the following features in planning:
-The scope of the project has been decomposed.
-All the activities has been decomposed.
What should the project manager do next ?
Create the project charter
Conduct a feasibility study
Create a project budget
Acquire project team
An organization is hoping that a new waste disposal project will allow them to get more government funding to finish the project.Unfortunately,after the project start,you realize that may not be qualifying project.
How should the project manager handle the situation?
Assess how this may impact the cost reductions to the project.
Be sure the issue log is updated.
Utilize the contingency reserve
Send a change request
An organization has recently moved to agile project management and the team is not following most of the agile meeting.They claim the daily scrum is not worth it.
What should the project manager do to help the team?
Conduct the meeting yourself.
Train the team on the benefits of the meetings.
Ask the sponsor to conduct team training.
Hire a new team that knows agile methods.
A very large international project is nearing completion and close-out documents are being prepared.What should the project manager do to gain acceptance of the project deliveries?
Get the steering committee to sign-off.
Get the director of the project manager’s business to sign-off.
Get the project sponsor to sign-off.
Get the various international managers to sign-off.