WorksheetsAs-Built - Knowledge Check
Total questions: 10
Worksheet time: 7mins
Who is responsible for recording as built data in the field?
Chorus
Field Managers
Civil workers
Technicians
Back office workers
Who is responsible for verifying and approving as built drawings?
Chorus
Field Managers
Civil workers
Technicians
Back office workers
A tie-in is...
the distance between the design and the built location
the distance between a landmark and an asset
an inn that serves Thai food
When measuring offsets what landmarks are suitable to use?
a letter box
a boundary marker
a utility pole
a parked car
an existing pit
Tie-ins should be accurate to...
within 1m
within 0.1m
within 300mm
within 1 foot
We only need to record the location, not the depth
TRUE
FALSE
What are consequences of poor as builts?
Contractors dont get paid
Assets get damaged by future works
reputational damage
Time wasted locating later
All of these
Deviations greater than 0._ m need to be recorded
(a)
As-Built measurements and tie ins should be recorded...
at time of build
at home after work
If there is not much space to add as built drawings on the lay plan you should
leave your phone no so you can explain later
use a fine pencil to draw smaller pictures
draw on a separate sheet with a reference number
draw in an open space with a line pointing to the location