1.

What organization manages project management standards and certifications?

a)

AIGA (American Institute of Graphic Arts)

b)

The Project Management Association of America

c)

The Project Management Institute

d)

The American Association of Project Management

2.

What are the typical phases in a project management life cycle?

a)

Planning; Design; Execution; Testing; Closure

b)

Discovery; Design phase; Developemnt and Testing

c)

Initiation; Planning; Execution; Monitoring & Control; Closure

d)

Planning and analysis phase; Design phase; Implementation; Testing and Integration; Maintenance

3.

How can you tell if a project is veering off course?

a)

Use your intuition.

b)

Schedule peer and client reviews.

c)

Ask the team leaders how their work is going.

d)

During the development and testing phase, monitor closely the project scope, schedule, and costs.

4.

What are three methods for good client and peer communication?

a)

Ask clarifying questions, paraphrase, and use design jargon.

b)

Explain your position, ask clarifying questions, and use design jargon.

c)

Listen, ask clarifying questions, and paraphrase.

d)

Listen, explain your position, and ask clarifying questions.

5.

Project Management Triangle consist of

a)

Time, money, scoop

b)

Quality, Cost, Delivery

c)

Scope, Time, Quality

d)

Cost, Scope, Time

6.

What is the purpose of identifying milestones?

a)

To keep track of your finances

b)

To help you keep track of each key stage of the project

c)

To speed up your work process

d)

To delegate all your tasks to others

7.

What is meant by contingency?

a)

An identified verifiable stage of the project that you can tick off once it's done

b)

The term given to describe the different stages a project goes through

c)

The allocated amount of time/money identified as a buffer for minimising risks

d)

The tasks that may or may not be included in the project

8.
Peter Parker was the real name for which super hero?
a)
Superman
b)
Spiderman
c)
The Hulk
d)
Ironman
9.

Kanban board focuses on

a)

Flow

b)

People

c)

Revenue

d)

All of the above

10.

How does Kanban prevent work over capacity?

a)

By using Work In Progress (WIP) Limit

b)

By setting a robust Kanban workflow

c)

By having daily meetings about work in progress

d)

By defining explicit policies

11.
On what principle does Kanban works on?
a)
It helps to visualize the task you working on and the items in context of each other
b)
It helps to balance the workflow for teams.
c)
On completion of any work, it pulls out the most prioritized work from the backlog
d)
All of the above
12.

Management reserves are used to handle which type of risk?

a)

A. Unknown unknowns

b)

B. Known unknowns

c)

C. business risks

d)

D. pure risks

13.

Which of the following are examples of indirect costs?

a)

A. Salaries of corporate executives

b)

B. Salaries of full-time project staff

c)

C. Overhead costs

d)

D. A and C

14.

An organization has recently moved to agile project management and the team is not following most of the agile meeting.They claim the daily scrum is not worth it.


What should the project manager do to help the team?

a)

Conduct the meeting yourself

b)

Train the team on the benefits of the meetings

c)

Ask the sponsor to conduct team training

d)

Hire a new team that knows agile methods

15.
An experienced agile practitioner was explaining the benefits of empowered, self-organizing, and self-directing teams. Some agile team members then complained that their manager is not very agile as demonstrated by their very directive style of communication. How would the agile practitioner most likely respond to this comment?
a)

The team is still in the storming stage, which requires a lot of direction

b)
The team is already in the norming stage, which requires a lot of direction
c)

The project has a very tight schedule and must be managed by directives

d)

Theory is one thing, and real life is a totally different story

16.
The product owner for an agile project has another project at the same time. As a result, the product owner spends very little time with the development team and the product is suffering. What should an agile practitioner on this team do first?
a)
Coach the product owner on the importance of participating in the team events
b)
Escalate the issue to the project sponsor
c)
Request a new product owner be assigned to the project
d)
Have the scrum master fill a dual role as Agile encourages generalizing specialists
17.

Who sings the song "Malchik brodyaga"?

a)

Olha Poliakova

b)

DZIDZIO

c)

Nirvana

d)

Andrey Gubin

18.
A developer joins a new agile team after working with a different team for 3 years. The developer's former manager keeps asking her for help resolving defects from their previous project. As a result, the developer multitasks and cannot fully dedicate herself to either project, negatively impacting the throughput of both and making both teams frustrated. What is the best course of action for the project manager who leads the current project?
a)
Allow the developer to support both projects
b)
Recommend the termination of both projects
c)
Escalate the issue to the project sponsor
d)
Remove a few items from the product backlog
19.
At the beginning of your project, you were authorized to offer incentives to the designers to work in your company's office building for the duration of the project. You secured a temporary workspace to accommodate the entire project design team in a common area. This strategy allows them to work in proximity to one another to enhance their ability to preforms a unified design team. What tool or technique did you use in this scenario?
a)
Virtual teams
b)
Collocation
c)
Forming
d)
Strategic placement
20.
While working on the screen layout of a mobile application, a developer on an agile team came up with a screen improvement idea that will enhance the application's usability, and ultimately increase customer satisfaction. Implementing this idea represents a new requirement. The developer's first thought is to implement this improvement to impress their client. What should the developer do next?
a)
Implement the improvement and demonstrate the new screen layout to the product owner
b)
Do nothing since this requirement is out of scope and it should not be added to the product.
c)
Suggest the improvement to the product owner for possible inclusion in the upcoming iterations
d)
Reach out to the customer and obtain their approval to implement the suggested improvement
21.
During a sprint planning meeting, the scrum team is arguing over 115 story points' worth of user stories that the product owner is pushing to be completed in the upcoming sprint. However, the development team’s average velocity is only 100 story points. Who makes the final decision on how many story points will be targeted for completion during a sprint?
a)
The project manager
b)
The development team
c)
The scrum master
d)
The product owner
22.
After a few successful iterations, agile team members hold a planning meeting for their next sprint. Which of the following would be a result of this meeting?
a)
A working product increment
b)
An activity list and a project schedule network diagram
c)
A prioritized list of product backlog items
d)
A list of work items to be completed in the next sprint
23.
You are about to attend a bi-weekly status meeting with you program manager when she calls and asks you to be certain to include earn value analysis in this and future meetings. why is earned value analysis important to communication process?
a)
It communicates how the project is doing against the plan
b)
It communicates the project's long term success
c)
It communicates the date the project deviated from the plan
d)
It communicates the value-to-cost ratio
24.

Jack is the project manager of a project that is halfway through its execution. He is currently looking at the work schedule. He adjusts a few of the schedule milestones and imposes date constraints for some of the work packages. This relates to which of the following processes?

a)

Develop Schedule

b)

Control Scope

c)

Control Schedule

d)

Control Quality

25.

Your boss is giving you a rough outline of the scope, constraints, and risks involved in a prospective client's project. The project is highly similar to another project you are currently closing. The sponsor wants to know how long this project would take your team to complete. You think your team may need two months, but what should your answer be?

a)

"Let me run some numbers in a simulation, and get back to you tomorrow."

b)

"Considering the uncertainty in scope, I estimate three months."

c)

"Give us two months. We will knock it out just like the project that we are closing now."

d)

"If it truly resembles this project we are closing, it could be six to ten weeks."

26.

A project was estimated to cost $100,000 with a timeline of five months. Due to some unusual causes, the schedule was delayed. At the end of the third month, the project manager reviews the project and finds that the project is 40 percent complete and Actual Costs are $60,000. Assuming that the cost variations observed to date would not continue going forward, the Estimate to Complete (ETC) for the project are:

a)

90,000

b)

40,000

c)

120,000

d)

60,000

27.
a)

Ha-ha

b)

I did not get it

28.

Which of the following is NOT a characteristic of a leader who serves?

a)
Listening
b)
Happiness
c)
Foresight
d)
Stewardship
29.

Kate and Anatoly are unable to come to a conclusion for projects. Anatoly tend to keep quiet and stop contributing, keeping disagreements to himself. He will also try to leave meting as soon as possible when there is a conflict. Which conflict management style is this?

a)

Collaborating

b)

Silent departure

c)

Avoiding

d)

Accommodating

30.

Your company just won a major new project. It will begin in three months and is valued at 2m USD. You are the project manager for an existing project. What is the FIRST thing you should do once you hear of the new project?

a)

Ask management how the new project will affect your project

b)

Ask management how the new project will use resources

c)

Resource level your project

d)

Crash your project

31.

During project executing, a team member comes to the project manager because he is not sure of what work he needs to accomplish on the project. Which of the following documents contain detailed descriptions of work packages?

a)

Project scope statement

b)

Scope management plan

c)

Activity List

d)

WBS Dictionary

32.

Your project management plan results in a project schedule that is too long If the project network diagram cannot change but you have extra personnel resources, what is the BEST thing to do?

a)

Level the resources

b)

Fast track the project

c)

Crash the project

d)

Monte Carlo analysis

33.

An activity has an early start (ES) of day 3, a late start (LS) of day 13, an early finish (EF) of day 9, and a late finish (LF) of day 19. The activity:

a)

Has a lag

b)

Is progressing well

c)

Is on the critical path

d)

Is not on the critical path

34.

Early in the life of your project, you are having a discussion with the sponsor about what estimating techniques should be used. You want a form of expert judgment, but the sponsor argues for analogous estimating. It would be BEST to:

a)

Determine why the sponsor wants such an accurate estimate

b)

Try to convince the sponsor to allow expert judgment because it is typically more accurate

c)

Agree to analogous estimating, as it is a form of expert judgment

d)

Suggest life cycle costing

35.

During risk management activities, 236 risks have been identified which are caused by 13 root causes. You could eliminate the 234 risks by your risk management activities. For the remaining 2 risks, you, together with your team, could not find a way to mitigate or insure the risks. Also, these 2 risks cannot be outsourced or removed from the project scope. What is the best solution?

a)

Accept the risk

b)

Mitigate the risk

c)

Avoid the risk

d)

Transfer the risk

36.

Amy, your friend, works as a software developer at an E-commerce company. When you are chatting with Amy about her project, she told that their project management approach relies on three practices. 1- Visualize what you do today, 2- Limit the amount of work in progress, 3- Enhance flow. Which of the following approach is used in Amy’s project?

a)

Scrum

b)

Kanban

c)

Extreme Programming

d)

Lean

37.

Sue is working as a Scrum Master in a Scrum Team. There are five developers in the team. Rick is one of the developers in the team and Sue noticed that Rick is applying a different approach to complete Sprint tasks faster. Which one is the best course of action to do for Sue?

a)

During the retrospective, ask Rick to share his approach with the team and ask the team if it is applicable for every developer

b)

Ask Rick in the next daily standup meeting why he did not share this approach with the team

c)

Ask Rick to stop his task, and prepare a detailed guide regarding how to apply this approach. Then, distribute to the team

d)

Ask Rick not to use approach as it's not part of the Company OPA and EEF

38.

If you need to review some of PM Yalantis's processes, where should you refer to first?

a)

Confluence

b)

Your Mentor

c)

Head of PMO

d)

Tetya Lena

39.

Who should approve Yalantis team members' education according to the new process?

a)

Delivery Manager

b)

Project Manager first, than Delivery Manager

c)

SDO member

d)

Serhiy Herasimov

40.

Which language is used for formal communication in Yalantis?

a)

English

b)

English, Russian, Ukrainian

c)

Java

d)

Depends on stakeholders' language

41.

Which tool in Yalatis Project Plan shows the project progress regarding the project budget?

a)

Budget & Milestone list

b)

Project Charter

c)

Project Performance Chart

d)

None of the above

42.

Who is Alex Kholodov?

a)

COO

b)

CEO

c)

CFO

d)

Doesn't work in Yalantis

43.

What wouldn't be a good approach to facilitating stakeholder meetings on an agile project?

a)

Establish your authority as the facilitator early in the meeting to keep everyone focused on the task at hand.

b)

Establish basic ground rules, and then enforce them.

c)

Establish a clear goal for the meeting, and keep the discussion focused on it.

d)

Establish the duration of the meeting ahead of time, and assign someone to be the timekeeper.