Wayground logo

Free Printable Worksheets

Font size

S
M
L
XL
Worksheets

Meeting Minutes Quiz

Total questions: 25

Worksheet time: 16mins

Name
Class
Date
1.

Which of the following people were NOT part of the meeting?

a)

Lloyd Christmas

b)

Chris Foley

c)

Brennan Huff

d)

Dominic Toretto

2.

What date was WCB on site for review?

a)

November 12

b)

November 13

c)

November 14

d)

WCB was not on site

3.

Miranda will return the paint submittals by December 2nd

a)

True

b)

False

4.

What date will the sprinkler fitters start on site?

a)

November 19th

b)

November 23rd

c)

November 28th

d)

December 7th

5.

Which of the following attendees works for the General Contractor?

a)

Miranda Priestly

b)

Dale Doback

c)

Lloyd Christmas

d)

Brennan Huff

e)

Dominic Toretto

6.

Which entrance had a damaged door frame?

a)

North

b)

South

c)

East

d)

West

7.

What day will EPCOR connect the site power?

a)

November 13th

b)

November 19th

c)

December 10th

d)

No date given

8.

The electrical transformer was scheduled to be delivered November 25th.

a)

True

b)

False

9.

Dale is waiting for Change Order #4 approval.

a)

True

b)

False

10.

When will the AHU be delivered?

a)

November 19th

b)

November 29th

c)

December 13th

d)

December 15th

e)

Did not say

11.

What is the RFI that the Architect is currently reviewing?

a)

RFI#30

b)

RFI#31

c)

RFI#32

d)

RFI#33

12.

Miranda confirmed that the repaired entrance door will meet the required fire rating.

a)

True

b)

False

13.

What date is the Structural Engineer inspecting the rebar?

a)

November 1st

b)

November 2nd

c)

November 3rd

d)

This was not discussed

14.

Who is managing the painting of the panel boards?

a)

Brennan

b)

Dominic

c)

Dale

d)

This was not discussed

15.

Which meeting members performed a site walk-through?

a)

Dale & Miranda

b)

Lloyd & Miranda

c)

Lloyd & Dale

d)

Brennan & Dale

e)

None of these members

16.

The sprinkler fitters will need their own a site office.

a)

True

b)

False

17.

Dale will follow up with the Owners on Change Order #6

a)

True

b)

False

18.

What date was the site review performed?

a)

November 17th

b)

November 16th

c)

November 15th

d)

Date of the review was not given

19.

Approval of Progress Bill #4 is expected by November 19th.

a)

True

b)

False

20.

When will the next Progress Meeting be held?

a)

November 29th

b)

December 5th

c)

December 7th

d)

No date was set

21.

The damaged entrance noted by Miranda will be repaired by November 30th.

a)

True

b)

False

22.

Lighting shop drawings will be resubmitted by what date?

a)

November 19th

b)

November 25th

c)

November 29th

d)

December 1st

23.

Dale Doback is waiting on RFI#32 from which party?

a)

Architect

b)

Mechanical Sub

c)

Electrical Sub

d)

RFI#32 is complete

24.

Heating and hoarding for the concrete will start on:

a)

November 19th

b)

November 23rd

c)

November 26th

d)

This was not discussed

25.

Is the project ahead, on, or behind schedule?

a)

Ahead

b)

On Schedule

c)

Behind