CHAPTER 7_PROJECT MANAGEMENT AND MANTAINANCE

Total questions: 12

Worksheet time: 6mins

Name
Class
Date
1.

Based on the table , which one is the correct way to draw pert diagram?

a)
b)
c)
2.

What is the completion time for this pert diagram ?

a)

15 weeks

b)

25 weeks

c)

15 days

d)

25 days

3.

Start the work at earliest time and finish it at earliest time too. This statement refer to:

a)

Total Float

b)

Free Float

c)

Independent Float

d)

Fee time

4.

PERT analysis is based on

a)

optimistic time

b)

pessimistic time

c)

most likely time

d)

All of above

5.

The critical path

a)

Is a path that operates from the starting node to the end node

b)

Is a mixture of all paths.

c)

Is the longest path

d)

Is the shortest path

6.

Activities A, B, and C are the immediate predecessors for Y activity. If the earliest finish times for the three activities are 12, 15, and 10, then the earliest start time for Y will be

a)

10

b)

15

c)

12

d)

2

7.

Slack time refers to

a)

an event

b)

an activity

c)

both event and activity

d)

all of above

8.

If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is

a)

(a + m + b)/6

b)

(a + 2m + b)/6

c)

(a + 4m + b)/6

d)

(a + 5m + b)/6

9.

1. Preventive maintenance is done after the tools and equipment have been damaged.

a)

True

b)

False

10.

4. Maintenance should be done only if necessary.

a)

True

b)

False

11.

5. Lubricating tools and equipment should be in accordance with the manufacturer’s specification.

a)

True

b)

False

12.

List type of maintenance work?

a)

Routine maintenance

b)

Preventive maintenance

c)

Breakdown maintenance

d)

All above