WorksheetsReviewer kuya rr
Total questions: 100
Worksheet time: 50mins
To avoid hitting a waterfall, realignment of the route must be done. Being a new
road that will pass through loose or heterogenous strata, auger borings should be
made on the proposed alignment at an average interval of:
150 m
200 m
250 m
500 m
For any proposed bridge site, the topographic and river surveys should be extended from the centerline of the bridge at least
100 to 200 m upstream only
100 to 200 m downstream only
100 to 200 m upstream and downstream
300 m upstream and downstream
Profile along the centerline of the river channel should be extended from the centerline of the bridge by at least
100 to 200 m upstream only
100 to 200 m downstream only
100 to 200 m upstream and downstream
300 m upstream and downstream
To find the time of flow, it is required to determine the length of channel. This can
be done by transforming the drainage area into a rectangle whose two sides are in the
proportion of 1:1.5. The length of the stream is assumed one diagonal of this
rectangle plus one-half of the shorter side of the rectangle, which is the:
square root of the square of width (W) plus half of
square root of the sum of the squares of longer side (L) and W plus half of W
square root of the square of the squares of L plus half of W
3.0 W
The maximum length of ascending gradient which a loaded truck can operate without
undue reduction in speed is called:
critical length of grade for design
exceptional gradient
limiting gradient
ruling gradient
In practice, K – factor is used to convert average annual daily traffic to the 30th
highest annual hourly volume (DHV) and is defined as:
DHV/AADT
DDHV/(DxAADT)
V/PHF
L/A
A contractor encountered an equation on the plans. Quite confused, he clarified the
terms “BK” and “AH” from the Engineer. If you were the Engineer, you would say
that:
BK means new survey stationing
AH means old survey stationing corrected
BK means old survey stationing corrected;
AH, new survey stationing
Both a and b
Bearings for bridges are designed to provide free movement of girders. Which of
the following is not used to allow such movement?
expansion joints
rockers
sliding plates
rollers
For service load design of bridges, the flexural stress in the extreme fiber stress in
compression, fc (in MPa), is:
0.30 f’c
0.40 f’c
0.45 f’c
0.50 f’c
The maximum value of impact applied to the superstructure of a bridge should be:
15.24/(L+38); where L=portion of the span loaded for maximum
50/(L+125)
30%
50%
When considering wind or earthquake forces either acting alone or in combination
with vertical loads, all allowable stresses and soil-bearing value for working stress
design may be increased by:
1/4
1/3
1/2
3/4
In foundation design, the allowable load or bearing capacity is obtained by reducing the ultimate bearing capacity by a factor of safety of:
1.5
2
1 to 2
2 to 3
What do you call the vertical distance from the culvert invert at the entrance to the water surface elevation permissible in the approach channel?
freeboard
headwater depth
trailwater depth
scour depth
Culvert flow under entrance control is synonymous with flow under:
outlet control
inlet control
submerged outlet
normal depth greater than barrel height
For creeks in urban and rural areas and not subject to overbank flows, a minimum easement to be provided measured from the edge of the existing bank or the improved bank should be:
3.0 m
4.0 m
4.5 m
20.0 m
The rate of application of emulsified asphalt used as tack coat, should be within the range of:
0.2 – 0.5 lit/m²
0.2 – 0.7 lit/m²
0.15 – 0.7 lit/m²
0.15 – 0.5 lit/m²
Sub-grade soil is well compacted under the controlled condition of:
Over saturation with water
Optimum moisture content and maximum dry density
Dry soil
Cold weather
What is the accepted proportion mixture of lime to be added to the soil aggregate (dry soil), in a Lime Stabilized Road Mix Base Course (Item 203)?
2 to 10 mass percent
4 to 15 mass percent
3 to 18 mass percent
3 to 12 mass percent
What is the accepted proportion mixture of cement to be added to the soil aggregate (dry soil) in a Portland Cement Stabilized Road Mix Base Course (Item 204)?
4 to 20 mass percent
6 to 10 mass percent
5 to 12 mass percent
3 to 12 mass percent
What is the required area of the trial section needed to check the suitability of the materials and efficiency of the equipment and construction method the contractor will use?
about 500 sq.m.
about 400 sq.m.
about 100 sq.m.
about 600 sq.m.
What is the permitted variation from the design thickness of a layer of aggregate subbase course?
± 20 mm
± 10 mm
± 30 mm
± 15 mm
What is the permitted variation from the design thickness of a layer of aggregate base course?
± 20 mm
± 15 mm
± 25 mm
± 10 mm
What should the condition of the tack coat be before the next course is applied?
wet
sticky
plastic
dry
Concrete mix not place within ______ minutes from the time ingredients were charged into the mixing drum or has developed initial set, should not be used.
90
45
30
15
What is the minimum allowable/required atmospheric temperature in the application of Item 305 bituminous material?
5⁰ C
10⁰ C
12⁰ C
15⁰ C
The inside face of a pothole, aside from squaring, must be made vertical before patching using cold or hot mix asphalt in order to:
ensure bond between the new mix and old surface
prevent pumping
minimize spalling
prevent faulting
Repainting of steel bridges is an activity under:
special maintenance
preventive maintenance
routine maintenance
periodic maintenance
What do you call the process of cutting the branches around a tree on the roadside to make them denser and grow straight?
pruning
grafting
felling
budding
The equivalent physical measurement used in the determination of the cost of maintenance of our national roads and bridges and all its facilities is known as:
lane kilometer
equivalent kilometer unit
equivalent maintenance kilometer
standard kilometer unit
The maintenance work, under vegetation control, the remaining height grasses and shrubs should be left uncut is:
50 mm
100 mm
200 mm
400 mm
Concrete class A mix used and deposited in water for footing construction shall maintain a slump between:
5 and 10 cm
10 and 20 cm
20 and 30 cm
30 and 40 cm
Concrete should be kept continuously wet by the application of water for a minimum period of how many days after it has been placed?
28
30
14
7
As practically possible, concrete mix should not be placed where this can be subject to manual dropping by not more than ____ and where no other special tools and means are used.
3.0 m
2.5 m
2.0 m
1.5 m
What is the required minimum weight of the gravity hammer used in pile driving?
2000 kg
1500 kg
1800 kg
1700 kg
What is the allowable minimum penetration of piles in firm material?
4.0 m
2.5 m
3.0 m
2.0 m
What is the maximum allowable variation at the butt end of a pile in any direction from its location shown in the approved plans?
75 mm
50 mm
25 mm
40 mm
In pile driving, when the desired penetration cannot be obtained by driving alone, other schemes are used. Which of the following is not acceptable?
Water jets
Pilot holes
Both jet and holes
Square hole
What is the technical term used in repairing the foundation of piers and abutments that have an indication of scouring and erosion?
Shotcreting
Underpinning
Riveting
Plastering
In underpinning a pier the following methods may be undertaken before the repair work starts, with exception of:
Earth-filled wood cofferdaming
Water diversion on thru dikes of rock and earth
Use of steel sheet piles
Spurdiking
Which of the following is not classified as a type of caisson foundation?
Pneumatic foundation
Box Caisson
Open Caisson
Hydraulic Caisson
What is the simplest type of superstructure of a concrete bridge with a limited span of 8 meters?
Reinforced concrete slab
Concrete plank deck
Girder and slab superstructure
Beam or plank bridge
What do you call the additional support on steel sheet piles to support embankment of the abutment of a bridge embedded in the ground designed to increase load safety factor against overturning?
Dead man
Pile
Bridge panel
Cross bracing
A project is about to be started, but the as-staked plan shows a reduction in length or shortening of the proposed structure. What should the Project Engineer do?
Issue Notice to Proceed and disregard the as-staked survey
Proceed with work, reflect the underrun in the as-built plan
Suspend work and request for review if redesign is needed
Recheck the as-staked plan
Excavation of indurated rocks can be undertaken by:
Pick and shovel
Ripper
Road grader
Bulldozer
You are assigned as a new Project Engineer on an almost completed spillway project and you found out per field survey that the spillway elevation is lower by one meter. What should you do?
Accept the project as is
Require the contractor to redo the spillway
Install corresponding ogee
Reprimand the former Project Engineer
Which of the following structures is constructed parallel to the flow of the river?
Spurdike
Revetment
Mini dam
Groin
Dams are hydraulic structures constructed to:
Increase conveyance capacity of the river
Arrest scouring on meandering river sections
Protect river banks from heavy run-off
Retard flood runoff and minimize effect of flash floods
48. Which of the following complements as a regulating flood control structure:
main canal
weir or control gate
drainage lateral
groin and spurdike
In embankment works, which of the following is undertaken first?
Clearing and grubbing
Excavation of core trench
As-stake survey works
Construction of the impervious fill
Before actual construction of a dam is started, which of the following should be secured first?
Maintenance of access road
Delivery of construction materials
Stripping of ground surface
Installation of safety requirements
If the void ratio (e) of a soil is 1, the porosity (n) is equal to:
50 %
30 %
20 %
10 %
What is the apparatus used in determining the consistency of a liquid asphalt?
penetrometer
Viscometer
Thermometer
viscometric meter
Which of the following is not a quality test for cement?
Compressive strength
Loss of ignition
Soundness
California Bearing Ratio
What Kind of joint is required to be constructed when there is an interruption of more than 30 minutes in the concreting operations of a road pavement?
longitudinal
transverse expansion
transverse contraction
transverse construction
Which of the following project documents attests that the materials incorporated into the project works corresponds to the quantity accomplished and conform with specifications?
Certificate of Quality Control Assurance
Quality Control Program
Notice to Proceed
Statement of Work Accomplished
Concrete in the area represented by the cores will be considered adequate if their average strength is equal to:
at least 85% of and no single core is less than 85% of f’c
at least 75% of and no single core is less than 75% of f’c
at least 85% of and no single core is less than 75% of f’c
at least 75% of and no single core is less than 85% of f’c
To attain a uniform consistency of concrete during the pouring operation of a concrete pavement, the slump should not be more than:
40 mm (1½ inches)
50 mm (2 inches)
62 mm (2½ inches)
75 mm (3 inches)
The flexural strength of concrete is considered satisfactory when the average strength of all sets of 3 consecutive strength test results equal or exceed the specified strength and when no individual strength test result is deficient by more than:
10 % of 550 psi
15 % of 550 psi
20 % of 550 psi
25 % of 550 psi
For a compacted pavement, what does the stability value in the Marshall test measure?
cohesion resistance
resistance to displacement
diametric distortion
skid resistance
If the required thickness of Item 200 is 300 mm, the material may be spread and compacted in layer (s).
One
Two
Three
Uniform
If the type of soil in Item 200 material is non-plastic, what Atterberg limit test can be performed.
Plastic limit
Liquid limit
Shrinkage limit
Both liquid limit and plastic limit
The plasticity Index (PI) required for Item 201, Aggregate Base Course materials, should not be greater than:
8 %
12 %
6 %
9 %
When the grading test results of the three (3) stockpiles are not in accordance with Item 201 requirements, which of the following is economical to recommend?
Replace the three (3) stockpiles with quality Item 201 materials
Blend the three (3) stockpiles to produce a correct proportion that will meet the specified grading
Allow the use of the materials provided corresponding deduction in payment will be affected
Increase the thickness of Item 201
In identifying project location intended for asphalt pavement, which of the following criteria is not appropriate to recommend?
Drainage facilities is well - maintained
Location is not in a typhoon belt area
Existing base course is stable
Flood-prone road section
After three weeks of completion, the asphalt overlay exhibited reflection cracking. What will you recommend to correct the said defect?
apply seal coat
apply additional bituminous mix
redo the construction of the asphalt overlay
apply cover aggregates
Soil classification is determined by:
Atterberg limits tests
Sieve analysis test
Hydrometer test
Atterberg limits tests and Sieve analysis test
The Item No. for Portland Cement Concrete Pavement in the DPWH Standard Specification is:
200
201
310
311
The minimum flexural strength requirement of concrete for Item 311 (Portland Cement Concrete Pavement) is:
500 psi
550 psi
3,000 psi
3,500 psi
To protect portland cement concrete pavement against rain before it has sufficiently hardened, the contractor should be required to have at all times any of the following materials with the exception of:
metal form or wood planks
burlaps or cotton mats
plastic sheeting material
plastic water stops
The minimum testing requirement of concrete for Item 405 is the compressive strength test on concrete cylinder samples consisting of a set of 3 concrete cylinder samples to represent not more than:
50 m³ of concrete
75 m³ of concrete
100 m³ of concrete
125 m³ of concrete
What is the minimum cement content (40 kg/bag) per cubic meter of class B concrete?
8 bags
9 bags
9.5 bags
11 bags
In laying stone components of Item 505 (Riprap and Grouted Riprap) each stone should be:
Laid with its longest axis perpendicular to the slope
Pitched to line along the beds and joints
Laid with its face parallel to the faces of the walls
Reasonably uniform with no projections more than 150 mm
What is Item 506 in the DPWH Standard Specification?
Structural concrete
Prestressed concrete
Stone masonry
Riprap and grouted riprap
In the DPWH Standard Specifications, what is the Item no. of Embankment?
100
102
104
106
What is the required minimum field density for embankment materials?
85%
90%
95%
100%
Who supervises the work and tests employed in project implementation?
Project Inspector
Contractor’s Engineer
Materials Engineer
Project Engineer
Who recommends actions to resolve problems during field implementation of a project?
Project Engineer
Materials Engineer
Project Inspector
Resident Engineer
Who gives orders to equipment operators, labor foremen and supply controllers in the work operations at the project site?
Project Inspector
Resident Engineer
Project Engineer
Contractor’s Engineer
In PERT/CPM networking, the process of compressing the duration of a project is called:
Time optimization
Crashing
Contract time adjustment
Reduction
Which of the following need not be resorted to when compressing the duration of a project?
Use of two-shift work force
Use of advanced construction technology
Use of additional equipment
Use of additional materials
In the calculation of total project duration in an infrastructure project (equipment oriented), which of the following is the most important consideration?
Right-of-Way acquisition
Local manpower capability
Climatic condition in the area
Availability of funds
In a PERT/CPM network, this is the sequence of activities in the project that comprises the longest time duration from start to finish:
Early Finish
Late Finish
Critical Path
Zero Slack
In project monitoring of a river channel, which of the following is the origin station (Sta. 0+000) of a river?
at the river bank
at the uppermost station
at the confluence station
at the mouth of the river
If a contractor continues to disregard agreed project plans and specifications, what recommendation should you prepare?
Contract suspension
Termination of contract
Rescission of contract
Blacklisting of contractor
The catch-up schedule reflects:
Financial expenditures
Accomplishment-duration relationship
The advance accomplishment
Preliminary engineering activities
For reference in the preparation of catch-up plans the following are the prevailing weather conditions in the Philippines with the exception of:
Two pronounced seasons, dry from November to April, wet during the rest of the year
No dry season, with a very pronounced maximum rainfall from November to January
Dry and rainy season is equally distributed throughout the year
Rainfall more or less distributed throughout the year
If a project is started more than 8 months after the bidding, the contractor is entitled to claim for:
Bonus
Additional advance payment
Price adjustment
Extra work order
After the final inspection of a reported 100% accomplished project, before a certificate of final inspection is issued, which of the following should be conducted in the field:
Emergency Conference
Exit Conference
Pre-construction Conference
Turn-over Ceremony
In an inspection report, aside from the findings, which is the most important item to be included?
duration of inspection
members of the inspectorate team
copy of the memorandum to inspectorate team
recommendation of possible actions to be undertaken
A logbook contains the following data with the exception of:
activities done during the day
materials delivered and used for the day
the day’s weather condition
survey data
What formula is used in computing price escalation?
No loss – no gain formula
Economic Formula
Parametric Formula
Parabolic Formula
Where do we base and reckon the computation of contract price escalation of a project that is awarded thru public bidding?
Notice to proceed
Effectivity of the contract
Date of approval of the contract
Date of bidding
Where do we base and reckon the computation of the contract price escalation of a project that is awarded thru simplified bidding?
Notice to proceed
Date of bidding
Approval of the contract
None of the choices
What is the allowable variance from the original unit price, so that a contract will be entitled to contract price escalation?
Less than 2 %
Less than 5 %
More than 5 %
Less than 3 %
The government may rescind the contract work if there is:
Existing right-of-way problem
Delay in the payment of contractor’s claim for billing
Undue delay attributable solely to the contractor
Adverse peace and order conditions
From the time of project was bid to the issuance of notice to proceed, how many calendar days is required for a project to be entitled to contract priced adjustment?
60
90
120
150
Under which of the following conditions must a change order not be issued?
Where there is a decrease in work due to deletion of work items
Where there is reclassification of item of works
Where the aggregate cost has increased and is limited to 25 % of the original cost
Where there is increase in cost in construction materials
Which of the following is not considered a Variation Order?
Change Order
Extra Work Order
Resume Order
Supplemental Agreement
A project with delays due to reasons beyond the control of the contractor may be granted a time extension if the affected works, as shown in the PERT/CPM diagram, are:
dummy activities
critical activities
non-critical activities
hammock activities
If after fifty (50%) completion, the work is satisfactorily undertaken and on schedule no additional retention should be made otherwise the progress payment should be imposed a retention rate of:
5%
10%
15%
20%