Project Manager Skills - Midterm - Project Management Techniques

Total questions: 22

Worksheet time: 22mins

Name
Class
Date
1.

What is NOT true about the project manager?

a)

Must have a clear understanding of how the project fits into the organization

b)

Technical knowledge is more valuable than broad knowledge

c)

He should produce as much of the project plan as possible

d)

He should come in early into the project

2.

Which of the following describes a functional manager (as opposed to a project manager)?

a)

Manager is a generalist

b)

Manager has very high technical skills

c)

Manager rarely decides who performs each task

d)

Manager must be skilled at synthesis

3.

Which of the following describes a project manager (as opposed to a functional manager)?

a)

Manager needs some technical skills

b)

Manager is responsible for the big picture

c)

Manager must be skilled at analysis rather synthesis

d)

Manager must use the analytical rather than the systems approach

4.

Which of the following is NOT a criterion for selecting a project manager?

a)

Technical credibility

b)

Political sensitivity

c)

Strong sense of ethics

d)

Technical expertise

5.

Which is NOT a quality of effective management?

a)

Innovate and maintain stability

b)

Be hands on/hands off

c)

Exercise high control over every aspect of the work that gets performed

d)

Optimism

6.

Towards whom does the project manager NOT have a responsibility?

a)

The general organization

b)

All project stakeholders

c)

The project client

d)

The project staff

7.

What is NOT required when selecting a project manager?

a)

Administrative credibility

b)

Financial skills

c)

Stress handling skills

d)

Interpersonal sensitivity

8.

What is NOT a required quality of an effective manager?

a)

Innovate and maintain stability

b)

Encourage teams but stress the individual

c)

Be flexible but firm

d)

Be hands off/hands on

9.

What is NOT a required quality of an effective manager?

a)

High intellectual coefficient (IQ)

b)

Personal integrity

c)

Being proactive

d)

Being optimistic

10.

The PM has responsibilities towards different parties. What is a responsibility that he has towards the project staff?

a)

He must use resources with care

b)

He must produce reports regularly depicting accurately the project

c)

He must think beyond the project completion

d)

He must preserve the scope of the project

11.

What is NOT a special demand on the project manager?

a)

Dealing with obstacles

b)

Acquiring adequate resources

c)

Technical training of personnel

d)

Negotiation

12.

What is NOT a responsibility of the project manager?

a)

Ensure that the customer is satisfied

b)

Coordinates the activities of team members

c)

Continues with original plan if progress or costs change

d)

Monitor actual vs. planned progress

13.

Which of the following statements is FALSE?

a)

The PM must be a generalist

b)

The PM is responsible for planning and implementation

c)

The PM can integrate a project at any time during the life of a project

d)

The PM must care for all communications in and around the project

14.

Let’s say a project manager realizes that one of the employees given to him for the project does not have the technical skills to even begin the work demanded. How should he approach this?

a)

He has authority over him so he pushes him harder

b)

He has only partial authority so he asks the functional manager of the employee to step in

c)

He does not have authority over him but he threatens him with harsh consequences

d)

He looks on his own for appropriate training for the employee

15.

The CEO of a company is looking for a good project manager. Human resources have interviewed four candidates and are reporting the skills of each. Which one would you prefer?

a)

Technical skills, negotiation skills, analytical skills, management skills

b)

Synthesis skills, analytical skills, management skills, facilitating skills

c)

Technical skills, Negotiation skills, synthesis skills, management skills

d)

Negotiation skills, synthesis skills, management skills, facilitating skills

16.

Towards whom does the project manager NOT have a responsibility?

a)

The general organization

b)

All of the project stakeholders (internal and external)

c)

The project client

d)

The project staff

17.

What is NOT required when selecting a project manager?

a)

Administrative credibility

b)

Stress handling

c)

Interpersonal sensitivity

d)

High level of authority over employees

18.

What is NOT a required quality of an effective manager?

a)

Innovate and maintain stability

b)

Encourage mostly individuals

c)

Be flexible but firm

d)

High level of focus on every small detail of a project

19.

What is NOT a required quality of an effective manager?

a)

Ability to micro-manage all tasks

b)

Personal integrity

c)

Proactive

d)

Optimist

20.

What is not a type of currencies in leadership?

a)

Task-related

b)

Position-related

c)

Operational-related

d)

Relationship-related

21.

What is NOT a factor in leadership?

a)

Keep all decisions for himself because PM is only capable person

b)

Understands what motivates team members and creates a supportive environment

c)

Does not create situations that cause individuals to become discouraged

d)

Fosters motivation through recognition

22.

What is NOT a factor in leadership?

a)

Encourages the same positive attitude

b)

Being highly motivated and setting a positive example

c)

Pushes others to obey commands no matter what

d)

Leads by making things happen