1.

What is the purpose of programming

(can select more than one answer)

a)

To allow Dates and durations allocated to tasks

b)

to show a critical path and "Float" items

c)

to be a tool to help plan activities, monitor progress and identify where additional resources may be required.

d)

to be apart of the construction contract documents

2.

What is a critical path?

(a)  

3.

What is a Predecessor Task?

(a)  

4.

What is a Successor Task?

(a)  

5.

What is a Float item?

a)

sequence of critical tasks

b)

is the task whose start or end date is controlled by another

c)

an event or activity can be delayed without delaying the overall completion of the works

d)

the actual cost of the construction

6.

What is a Gantt chart?

(a)  

7.

How would you make a number of selected tasks in sequence to each other ?

a)

A

b)

B

c)

C

d)

D

e)

E

8.

where would you find an option to extend working days/hours or add in non working days

a)

A

b)

B

c)

C

d)

D

e)

E

9.

after listing/adding your recourses how would you add them to tasks?

a)

A

b)

B

c)

C

d)

D

e)

E

10.

Which document below provides information to apply a stress test?

a)

RICS Practice Standards

b)

Applying the work breakdown structure

c)

A quick guide to network analysis

d)

CIOB-Planning-Protocol-2021

11.

Quick note: Methods of acceleration

a)

1.Working overtime.

2.Adding new shifts.

3.Providing additional labour.

4.Additional supervision.

b)

5.Providing additional resources,

6.Early procurement of key items

7. Re-sequencing work activities

8. Adopting alternative construction methods.

c)

9. Changing the design or specification.

10. Reducing the scope of the work.

11. Overlapping activities (fast tracking)

12. Reduction in scope of work