O&M PROFESSIONAL MINDSET

Total questions: 5

Worksheet time: 3mins

Name
Class
Date
1.

Preventive maintenance tasks should be grouped by?

a)

Parts required, task interval and lockout -tag out requirement

b)

Skill required, parts required and equipment availability

c)

Skill required, task and interval

d)

Skill required, task interval and lockout-tag out requirement

2.

The historical evolution of maintenance methods from earliest to latest has been

a)

Reliability centered, predictive, preventive, breakdown (reactive

b)

Preventive, reliability centered, predictive, breakdown (reactive)

c)

Breakdown (reactive), predictive, preventive, reliability centered

d)

breakdown (reactive), preventive, predictive, and reliability centered

3.

Which of the following is a directly controllable leading performance indicator?

a)

Monthly production levels

b)

Schedule compliance

c)

Unplanned downtime

d)

Plant (facility) profitability

4.

What are the three elements that form the fire triangle?

a)

Fuel, oxygen and ignition source

b)

Gasoline, air and heat

c)

Fuel, air and spark

d)

Diesel, air and heat

5.

If a machine is running for 1000 hours and five failures are observed during this period, what is theMean Time Between Failure?

a)

0,005 hours

b)

5000 hours

c)

200 hours

d)

2500 hours