Which aspect of Agile projects allow for the ability to adjust to ever-changing conditions?
Agile is incremental
Agile is iterative
Agile is adaptive
Agile is predictive
When using Agile project management, which of the following elements is used to help the team share responsibility for the backlog and burndown chart, and also helps them to hold each other accountable for their daily obligations?
Iterative Team Meetings
Sprints
Daily Scrum Meetings
Scrum Retrospectives
What are user stories used for in the Agile method?
To provide constant stakeholder feedback for shaping the product to meet the customer's needs
To complete one of the product's requirements in a usable form
To add detail and functionality to a product at the end of a sprint
To use historical data to provide a linear development plan structured around a desired result
Which of the following are common traits of the Agile method of project management? Choose two.
Iterative
Predictive
Scrums
Waterfall
Which of the following is commonly used to track sprint progress in Agile?
User Stories
Iterative Cycles
Feedback Loops
Burndown Charts
Based on the information in this chart, is the team meeting their sprint committments?
Yes
No
Which of the following make up the "Triple Constraint?" Choose three.
Scope
Time
Budget
Quality
During which phase are project constraints first developed?
Initiating
Executing
Planning
Monitoring and Controlling
Who is responsible for approving changes to any project constraints?
Project Manager
Project Management Office
Project Sponsor
Change Management Office
Kelly is a project manager for a construction company. The project is already underway when Kelly learns that the cost of drywall are higher than anticipated, impacting the budget of her project. Which of the following strategies could Kelly use to deal with this change to her constraints? Choose the two best options.
Meet with the stakeholders to change the overall scope of the project
Obtain additional funds to cover the increased cost
Decrease cost in other areas
Stop the project
What element of a project must meet specific, measurable benchmarks or key performance indicators (KPIs) to be accepted?
Requirements
Deliverables
Constraints
Issues
When completing a WBS, what is the smallest unit of work?
Main Phases
Project Deliverables
Work Packages
Mini Components
WBS focuses on developing a list of tasks to help produce ________? Choose the best answer.
Resources
Deliverables
Solutions
Programs
Which of the following is best described as, "points in time that are reached as a project progresses?"
Work Packages
Deliverables
Milestones
Check-ins
Christopher is the Project Manager for his company. He has an item on the task list that is unable to start because of a predecessor task. What kind of relationship exists between these two tasks?
Left-to-Right
Up-to-Down
Dependency
Critical Path
Which of the following is the Critical Path?
A-D-E-G
B-D-E-G
A-C-F-G
C-F-G
Calculate the length of the Critical Path
8 Days
9 Days
10 Days
14 Days
A Project Manager would like to ensure that there is a mechanism built into project schedules to ensure that all required approvals are obtained. What does this Project Manager need to add?
Benchmarks
Scope Limits
Float and Slack Boudaries
Governance Gates
Juan would like to emphasize areas of agreement while dealing with a conflict between two team members. What technique should he employ?
Smoothing
Forcing
Compromising
Confronting
Anthony works in a Projectized company. There are often times between projects where some members of his team are idle. What is Anthony's team experiencing?
Scope Creep
Benched Resources
Resource Overallocation
In-house Personnel
What stage of the Tuckman ladder involves the team starting to work together, adjust work to support the team, and trust one another?
Storming
Norming
Performing
Adjourning
Ivanna is working on a critical project and she needs to ensure her team is only focused on this project. What kind of resource does Ivanna need?
Dedicated Resource
Shared Resource
Allocated Resource
Overallocated Resource
You are the project manager for an iOS app development project. As part of the project, you'll need to ensure that you have five (5) SQL developers available; however, you've discovered that only three (3) are available to start with the other two (2) being available a week later. Which of the following constraints will need to be adjusted as a result of this issue?
scope
time
cost
quality
Which process will create the initial list of risks on the Risk Register?
Risk Planning
Risk Identification
Risk Review
Risk Response
Paul's project is facing the risk that's impact has been estimated to cost $10,000 per day. The probability is that it could happen two (2) times a year, making a single incident valued at $5,000. What kind of risk analysis was completed for this risk?
Qualitative
Quantitative
Sandra has identified a risk and placed it on her risk register. After discussions, the stakeholders have decided to do nothing about the risk. What strategy is being used?
Mitigation
Transferrance
Acceptance
Avoidance