Quality Control Measures in Asphalt Pavement Construction

Total questions: 10

Worksheet time: 3mins

Name
Class
Date
1.

Constant checking of bituminous mixture as it leaves the pugmill/central mixing plant for compliance with the job-mix formula is important. Hence, the tolerance temperature of asphalt mix is:

a)

165 degree Celsius

b)

110 degree Celsius

c)

130 degree Celsius

d)

120 degree Celsius

2.

It is an assembly of mechanical and electronic equipment where aggregates, recycled materials, or other additives are blended, heated, dried, and mixed with a binder to produce an asphalt mixture meeting specified requirements.

a)

Asphalt Batch-Type Mixing Plant

b)

Asphalt Mixture Plant

c)

Asphalt Drum-Type Mixing Plant

d)

Portland Cement Concrete Mixture Plant

3.

Quality asphalt pavement has:

a)

Good design

b)

Good quality of materials

c)

Good construction control or workmanship

d)

Good foundation

e)

Good drainage

4.

What is the required stability (index retain strength) of the asphalt mix when tested by AASHTO T165?

a)

greater than or equal to 70

b)

less than or equal to 70

c)

greater than 70

d)

less than 70

5.

What are the basis of acceptance and final payment on the completed asphalt pavement?

a)

thickness and strength determination

b)

thickness and density determination

c)

thickness determination only

d)

density determination only

6.

The variation of the surface from the testing edge (3-m straight edge) between contact with the surface shall ________.

a)

exceed 6 millimeters

b)

not exceed 6 millimeters

c)

not exceed 8 millimeters

d)

exceed 8 millimeters

7.

The mixture shall be placed at a temperature ____________ as measured in the truck prior to dumping into the spreader.

a)

not less than 107 degree Celsius

b)

less than 107 degree Celsius

c)

not less than 105 degree Celsius

d)

less than 105 degree Celsius

8.

If no core was taken at the end of each day’s operation and the project has already been completed, a core shall be taken for __________ of the completed pavement.

a)

every 50 linear meters per lane

b)

every 100 linear meters per lane

c)

every 150 linear meters per lane

d)

every 200 linear meters per lane

9.

Test to determine the asphalt content in bituminous paving mixture:

a)

Laboratory Density Test

b)

Immersion-Compression Test

c)

Grading Test

d)

Extraction Test

10.

Also known as as thermal cracking, occur roughly perpendicular to the centerline of the pavement or laydown direction.

a)

Transverse Cracking

b)

Linear Cracking

c)

Fatigue Cracking

d)

Slippage Cracking