wayground logo

Free Printable Worksheets

Font size

S
M
L
XL
Worksheets

ACC 311 - Long-term Construction Contracts

Total questions: 14

Worksheet time: 25mins

Name
Class
Date
1.

In computing the percentage of completion ratio, under the cost-to-cost method, actual costs incurred should exclude:

a)

costs of materials used in construction

b)

costs of hiring equipment

c)

costs of design and technical assistance

d)

costs of materials purchased in advance

2.

The excess of the Construction in Progress account over the Contract Billings is treated as:

a)

current asset

b)

current liability

c)

other asset

d)

noncurrent liability

3.

Before the year of completion, under the percentage of completion method, the year-end balance of the Construction in Progress account equal to:

a)

cost incurred to date

b)

cost incurred this year

c)

cost incurred to date plus gross profit to date

d)

gross profit earned to date

4.

Under the zero-profit method, (a)   should not be recognized until the final year or year of completion.

5.

Which of the following does not belong to the group?

a)

insurance

b)

expected warranty cause

c)

claims from third parties

d)

construction overheads

6.

Revenue is recognized each year in both methods (Percentage of Completion and Zero-profit Method).

a)

True

b)

False

c)

It depends

d)

hala di ko sure

7.

Before the year of completion, under the zero-profit method, the year-end balance of the Construction in Progress account is equal to:

a)

cost incurred to date

b)

cost incurred this year

c)

cost incurred to date plus gross profit earned to date

d)

gross profit earned to date

8.

Because of some specifications posed by the customer that a contractor cannot perform, the process of (a)   is usually being entered into.

9.

Whether Percentage of Completion or Zero-profit Method is used, it will ALWAYS result to the same total gross profit.

a)

True

b)

False

c)

It depends

d)

ano nga ba?

10.

This is the accounting framework/standard that deals with the long-term construction contracts.

(a)  

11.

BebeTime Construction has consistently used the percentage-of-completion method of recognizing income. In 2021, BebeTime started work on a P3,000,000 fixed-price construction contract. The accounting records disclosed the following data for the year ended December 2021:

Costs incurred 930,000

Estimated cost to complete 2,170,000

Progress billings 1,100,000

Collections 700,000

How much loss should BebeTime have recognized in 2021?

a)

230,000

b)

100,000

c)

30,000

d)

0

12.

LoveKo Incorporated has consistently used the percentage-of-completion method of accounting for their contracts. In 2020, LoveKo started work on a 9,000,000 fixed-price construction contract that was completed in 2021. The company's accounting records disclosed the following:

cumulative contract costs incurred (2020) 3,900,000

cumulative contract costs incurred (2021) 6,300,000

estimated total costs at completion (2020) 7,800,000

estimated total costs at completion (2021) 8,100,000

How much gross profit would LoveKo have recognized on this contract for the year 2021?

a)

700,000

b)

600,000

c)

300,000

d)

100,000

13.

LoveKaBa Company began a construction project on a building for 3,000,000. The project was completed during 2021. The accounting records disclosed the following:

Progress billings during the year (2020) 1,100,000

Progress billings during the year (2021) 1,900,000

Cost incurred during the year (2020) 900,000

Cost incurred during the year (2021) 1,800,000

Estimated cost to complete (2020) 1,800,000

What is the balance of construction in progress account at the end of 2020 under the percentage of completion method?

(a)  

14.

BabyLove Company has consistently used the POC method. On January 12, 2020, BabyLove began work on a 6,000,000-construction contract. At the beginning of the contract, the estimated cost of construction was 4,500,000.

The following data relate to the progress of the contract:

Income recognized at December 31, 2020 600,000

Cost incurred from Jan. 12, 2020 thru Dec. 31, 2021 3,600,000

Estimated cost to complete at Dec. 31, 2021 1,200,000

How much gross profit should BabyLove recognize for the year ended December 31, 2021?

(a)