What presidential decree enabled the creation and development of what is known today as the National Building Code of the Philippines?
1069
1609
1096
1906
What republic act substantiate the implementation of the National Building Code of the Philippines?
RA 6641
RA 6541
RA 6451
RA 6154
A framework of minimum standards and requirements to regulate and control the buildings' / structures' location, site, design, quality of materials, construction, use, occupancy, and maintenance?
National Structural Code of the Philippines (NSCP)
National Standard Plumbing Code (NSPC)
National Service Training Program (NSTP)
National Building Code of the Philippines (NBCP)
Type of construction wherein WOOD CONSTRUCTION WITH PROTECTIVE FIRE-RESISTANT MATERIALS rating has been utilized.
Type IV
Type I
Type II
Type III
Type of construction wherein STEEL, IRON, CONCRETE, OR MASONRY CONSTRUCTION has been utilized.
Type V
Type IV
Type III
Type II
A form given by the contractor of the building project certifying that the project construction has been completed and ready for client turnover.
Building Permit
Certificate of Completion
Certificate of Occupancy
Logbook
This certifies that the completed building work is suitable for occupation.
Certificate of Use
Certificate of Occupancy
Certificate of Completion
Building Permit
The acronym NSCP means?
National Soil Conservation Program
National Structural Code of the Philippines
National Society of Compliance Professionals
National System Code of the Philippines
For a three-storey residential house, what should be the minimum ceiling height of the ground floor? (in meters)
2.00 meters
2.70 meters
2.40 meters
2.10 meters
For a four-storey residential house, what should be the minimum ceiling heights of the second floor? (in meters)
2.00 meters
2.40 meters
2.10 meters
2.70 meters
Buildings and Structures constructed before the approval of the code shall be affected by the National Building Code of the Philippines and will adhere to the strict compliance of conforming to the code.
TRUE
FALSE
The measurement of site occupancy is taken at the ground floor level including all courts, yards, and light wells.
TRUE
FALSE
1 year is allotted to the building official for the occupancy permit to be released once all papers for the building and inspection have been approved.
TRUE
FALSE
Structural Analysis is an optional document as part of the application for building permit.
TRUE
FALSE
3m offset is required as per indicated in the National Building Code.
TRUE
FALSE
The minimum requirement for the stair width is 700m clear.
TRUE
FALSE
In the consideration of the building courts, the court must be connected to an alley with a minimum width of 1.5m
TRUE
FALSE
The headroom is the clear distance from the finish floor line to the ceiling, if there is no existing soffit of the beam exposed.
TRUE
FALSE
The minimum dimension of the kitchen is 3m^2 with minimum width of 1.2m
TRUE
FALSE
The minimum width of the bathroom floor is 1m
TRUE
FALSE
Minimum horizontal dimension of court shall not be taken less than (a) meters
Habitable rooms provided with artificial ventilation shall have ceiling heights not less than (a) meters measure from floor to ceiling.
For a four-storey residential house with roofdeck, the minimum ceiling height of the fourth floor is (a) meters.
For rooms with natural ventilation, the minimum ceiling height is (a) meters.
For a five-storey residential house with roofdeck, the minimum size of a typical room is (a) meters
For a bungalow house, the minimum size of a typical kitchen is (a) .
Give 5 types of Construction
Give 7 documents needed in the application of the building permit.
Give 8 classification of occupancy with title name.
Type of construction wherein buildings shall be FIRE-RESISTIVE.
Type III
Type VI
Type V
Type IV
Type of construction wherein buildings shall be a WOOD CONSTRUCTION.
Type IV
Type III
Type I
Type II
Type of construction wherein buildings shall be of MASONRY AND WOOD CONSTRUCTION.
Type III
Type II
Type I
Type IV
Enumerate the 5 General design requirements.
Enumerate the 10 Classification of Occupancy.