1.
At a critical design review meeting for a large project, several important issues surface. After hearing about a major technical problem, one of the subcontractor's engineers mentions that he experienced a similar situation on another project; he has some ideas on how to solve the current problem. What type of power is the engineer using?
a)
Manipulative
b)
Referent
c)
Formal
d)
Expert
2.
A team member asks to tell you something in confidence. He advises you that he has been performing illegal activities within the company for the last year. He is feeling guilty about it and is telling you in order to receive advice as to what he should do. What should you do?
a)
Tell the employee to inform his manager.
b)
Confirm that the activities are really illegal.
c)
Inform your manager of the illegal activities.
d)
Ask for full details.
3.
Which of the following best describes a control chart?
a)
A chart showing the upper and lower control limits
b)
A chart showing potential causes of issues
c)
A chart showing project activities and their schedule
d)
A chart showing loops between activities
4.
Which part of the risk management process receives input from risk owners?
a)
Perform Qualitative Risk Analysis
b)
Perform Quantitative Risk Analysis
c)
Identify Risks
d)
Plan Risk Responses
5.
The project manager has discovered a team member has gold plated the work done in an activity. In order to discover this, the project manager must have been performing:
a)
Cost management
b)
Time management
c)
Scope management
d)
Staffing management
6.
Which motivational theory defines the hierarchy of needs?
a)
Herzberg
b)
McGregor
c)
Maslow
d)
Deming
7.
The team is in the midst of planning efforts for a software modification project that will impact several departments of the organization. It is anticipated that the resulting software will be rolled out to all of the departments simultaneously, so the team wants to be sure to catch any issues as early in the development process as possible. The project manager has encouraged them to pay special attention to managing quality on the project. All of the following are tools of Plan Quality Management except:
a)
Logical data model
b)
Benchmarking
c)
Cost of quality
d)
Process analysis
8.
The product is being built iteratively on a new technology platform. When the project manager asks the team members about the quality of the early product increments, they say "They're fine." How can the project manager verify that the new technology is supporting the quality objectives of the project?
a)
Ask the product owner how well the technology is delivering business value.
b)
Ask the team to present performance testing results showing the actual vs. expected measures.
c)
Bring in an auditor to assess the quality.
d)
Present the quality management plan to the team's coach and ask if the technology is supporting the plan.
9.
A project has a team member assigned to the project full time. What is the most likely effect on the project if that resource completes her activity sooner than planned?
a)
Subsequent activity will be delayed
b)
Changes to the risk response plan
c)
Wasted cost
d)
Lower quality deliverables
10.
A project manager is working with a seller on a project that is time-sensitive due to government regulations requiring the project to be completed by a certain date. She learns one of the sellers has bribed a subcontractor to work on this project instead of fulfilling previous commitments to other projects. What should she do?
a)
She should report the offense to management and the project managers of the affected projects.
b)
She should report this to other subcontractors.
c)
She should resign from the project so as to remove herself from this type of activity, but keep her discovery to herself rather than cause problems.
d)
She should not do anything because this is the vendor's problem. The project manager herself didn't do anything wrong.
11.
As the project manager, you are preparing your quality management plan. You are looking for a tool that can demonstrate the relationship between events and their resulting effects. You want to use this tool to depict the events that cause a negative effect on quality. Which of the following is the best choice for accomplishing your objective?
a)
Pareto diagram
b)
Control chart
c)
Scatter diagram
d)
Why-why diagram
12.
Payment for any decision made or encouraged by a foreign official with respect to whether a company will be awarded a project is best described as:
a)
A sunk cost
b)
A common practice
c)
A bribe
d)
A progress fee
13.
You are working on all of the elements of the resource management plan. The project requires a large number of people to complete the work and you have learned from past projects the importance of having clarity on who project team members report to within the project. The balance of work and available time are considerations. You need to make certain the right resources are available when needed and can complete the work. It is also important that each team member is clear on their responsibilities and roles on the project. A resource histogram helps by documenting which two data points?
a)
Resource and usage
b)
Resource and duration estimate
c)
Activity and resource
d)
Resource and calendar date
14.
The project manager leads many efforts on a project, including managing risk, quality, stakeholders, scope and cost, etc. There can be disagreement about which of these efforts requires the most focus to ensure project success. Among all of these competing efforts, what should the project manager focus on most?
a)
Scope
b)
Quality
c)
Risk
d)
Stakeholders
15.
Your project schedule is tight and in danger of falling behind when two team members start disrupting status meetings by arguing with each other. As project manager, what is the best thing you can do?
a)
Separate the two until the project is back on track.
b)
Discuss the problem with the two team members.
c)
Tell each team member they will not receive a recommendation from you if they continue arguing.
d)
Meet with both team members and their manager to determine the source of conflict.
16.
The project manager has noticed there have been a lot of changes on the project. This was not considered to be a problem until one day he discovers he cannot determine how many scope changes are currently being reviewed. This problem indicates an error in which of the following?
a)
Change control system and project scope management plan
b)
A poor change configuration system and benefit analysis
c)
Lack of a change control board and constrained optimization
d)
Plan purchases and acquisitions and requirements gathering
17.
All of the following are forms of power derived from the project manager's position except:
a)
Formal
b)
Expert
c)
Reward
d)
Penalty
18.
Which motivational theorist says that what motivates people is the work itself, including such things as responsibility, self-actualization, and professional growth?
a)
Herzberg
b)
Maslow
c)
McGregor
d)
Deming
19.
Two people on the project team have come to you with the discovery that they have been independently working on the same effort. You investigate further to find that they are right; they have been duplicating work. This situation can be best characterized as a lack of:
a)
Sponsor direction
b)
A good work breakdown structure
c)
Effective status meetings
d)
A matrix organization
20.
As a project manager, you are unable to allocate as much time to interact with your stakeholders as you would like. Which of the following stakeholders will you make it a priority to get to know?
a)
The department employee who is unfamiliar with the product of the project, but open to the positive impacts he believes the product will have on his work environment
b)
The project sponsor, with whom you have successfully worked on many projects
c)
The stakeholder who is an expert on the product of the project, but is not interested in implementing it in his department
d)
The manager of the department that will use the product of the project, who is known to be resistant to change
21.
Project A has a net present value (NPV) of US $30,000 and project B has an NPV of US $50,000, what is the opportunity cost to the organization if project B is selected?
a)
50000
b)
23000
c)
20000
d)
30000
22.
You are taking over a project and determine the following: Activity B has an early finish (EF) of day 3, a late finish (LF) of day 6, and an early start (ES) of day 2. Activity L is being done by a hard-to-get resource. The cost performance index (CPI) is 1.1 and the schedule performance index (SPI) is 0.8. Based on this information what would you be more concerned about?
a)
Resources
b)
Cost
c)
Float
d)
Schedule
23.
The project has just entered a key phase of development process when the lead developer walks into the project manager’s office. He regretfully tells the project manager that he is leaving the company, effective today, due to a family emergency. The project manager takes time to express his concern for the team member’s family. After the team member leaves, the project manager makes a short phone call, and arranges for a replacement developer to start work on the project the following week. This is an example of:
a)
Management by objectives
b)
Creating a workaround
c)
Project team optimization
d)
Implementing a risk response
24.
You have just been assigned as project manager for a large telecommunications project. This one-year project is about halfway done. The project team consists of 5 sellers and 20 of your company's employees. You want to understand who is responsible for doing what on the project. Where would you find this information?
a)
Project organizational chart
b)
Bar chart
c)
Responsibility assignment matrix
d)
Resource histogram
25.
It is time to start planning the next phase of the research and development project that you are managing. The risks are high because the results of testing will be critical to the upcoming go/no-go decision. Communication between the departments doing the work will be more difficult as there will be several contracts to be planned and negotiated. Your planning efforts will be documented in a series of management plans. Which of the following does a resource management plan include?
a)
The responsible organization for each work package
b)
How resources will be acquired
c)
What resources will be used on the project
d)
How resources will be optimized
26.
All of the following statements about workarounds are correct except:
a)
They are unplanned responses to risks.
b)
They are responses only to risks that were identified in project planning.
c)
They may result in a project change request.
d)
They make use of the project management plan.
27.
Four stakeholders have noted that major change is required on the contract. A project manager is documenting the change request when he receives a call from the seller informing him the seller's supplier has notified them of a price increase effective the next day. The seller is therefore asking for the change to become official right away. Generally, the project manager should:
a)
Get the change signed by the procurement manager.
b)
Ask for an extension of time to finish.
c)
Finish creating and then sign and send the change order.
d)
Report the issue to the change control boar
28.
The project manager on a multinational website implementation project is at a party and talks to friends who will be heavy users of this new website when the project is complete and the site is rolled out. They describe some annoying aspects of the current website. The project manager takes this feedback to the sponsor, and encourages design and scope changes. Which of the following best describes what the project manager has done?
a)
Scope validation
b)
Integrated change control
c)
Scope planning
d)
Stakeholder analysis
29.
The buyer has received the final deliverables and has formally accepted them. The procurement closure activities have been completed when a procurement audit identifies a failure. The project is considered to be:
a)
Still in closure until the problem is resolved
b)
Incomplete until the problem is resolved
c)
Incomplete until formal acceptance is accomplished
d)
Complete
30.
After the contract has been signed for the upgrade of 8,000 workstations, a project manager is assigned. The procurement manager is relatively new and has less project-related knowledge than the project manager. The cost analyst works from home, and his price estimates are based on the details outlined in the contract. The project manager thinks there was a flaw in the logic determining the number of workstations that can be upgraded via remote electronic software distribution. Which of the following is the best thing for the project manager to do?
a)
Meet with the appropriate project team members to choose the best solution.
b)
Meet with the cost analyst and the procurement manager to determine how they can amend the contract to accurately reflect the work that will have to be done.
c)
Determine if the contingency budget will cover the additional cost of a more expensive implementation.
d)
Meet with the seller to adjust the contract for the change.
31.
Your project is the first one in your organization to try an agile approach, and it has been a struggle to get agile methods to work. The team members aren't attending the daily standups and the backlog always seems to be out of date. At a retrospective, a team member suggests that process tailoring would help. Should you encourage the team to do that?
a)
Maybe, but you need more data to figure out which agile practices to change.
b)
No, these types of problems won't be solved by tailoring the practices.
c)
Maybe, it depends on whether you can get buy-in from the rest of the team and the product owner.
d)
Yes, tailoring the agile practices will help them work more smoothly.
32.
At the end of each sprint, the project manager reviews the latest update of the team's risk burndown chart. What should the project manager be looking for or monitoring?
a)
That the cumulative project risk severity is going down over time.
b)
That the number of defects corrected is increasing.
c)
That risky user stories are being complete
d)
That the team's time spent on risk assessment is going down.
33.
The project has had some problems, but now seems under control. In the last few months almost all the reserve has been used and most of the negative impacts of events that had been predicted have occurred. There are only four activities left, and two of them are on the critical path. Management now informs the project manager that it would be in the performing organization's best interest to finish the project two weeks earlier than scheduled in order to receive an additional profit. In response, the project manager sends out a request for a proposal for some work that the team was going to do, hoping to find another company that might be able to do the work faster. The project manager can best be said to be attempting to work with:
a)
Scope validation
b)
Reserves
c)
Opportunities
d)
Threats
34.
Which of the following statements about a RACI matrix is true?
a)
A RACI matrix identifies the one person accountable for each individual activity or work package.
b)
A RACI matrix is a type of context diagram that illustrates the levels of authority on the project.
c)
A RACI matrix groups stakeholders by directions of influence.
d)
A RACI matrix compares the current and desired levels of engagement of project resources.
35.
To help the project team function more efficiently on complex and interrelated activities, the project manager decides to use a war room. What does this mean?
a)
The tools needed to accomplish the work are kept in one place with easy access by the team from various locations.
b)
The project's entire senior management team is located in one area
c)
All the project records are kept in many locations.
d)
The entire team is located in one area
36.
The project manager is planning their first agile project. The team members have been assigned, but most of them aren't familiar with agile practices or the agile mindset. How should the project manager help the team transition to agile?
a)
Ask for an agile coach to guide the team members for the first few iterations.
b)
Provide training for all team members on how to use agile practices.
c)
Ask that the team members be reassigned so that everyone will have agile experience.
d)
Arrange for all team members attend a class on the agile principles and mindset.
37.
The Validate Scope process is different than the Control Quality process in that:
a)
Control Quality is considered part of Plan Quality Management, while Validate Scope is not.
b)
Scope validation is provided to the project management team, while quality control is provided to the project.
c)
Control Quality focuses on the quality of the project, while Validate Scope focuses on customer acceptance.
d)
Validate Scope is performed during project executing, and Control Quality is done throughout the project.
38.
Your organization is approached by company A to produce certain software. In the middle of the project, a competitor of company A asks your organization to produce similar software for them. What should you do?
a)
Do not do the new project since it is a conflict of interest.
b)
Do the project using some of the material created for company
c)
Do the project with all new work.
d)
Review the intellectual property clause for the first project to help determine the approach to take.
39.
Your company uses both predictive and adaptive approaches depending on the needs of each project. Your next project involves updating the company's website to conform to new federal regulations. Which option should you choose, and why?
a)
Predictive, because there isn't much technical or scope uncertainty for this project.
b)
Any approach would work; just ask the development team what they are most comfortable with.
c)
Hybrid, because both agile and predictive approaches would add value to this project.
d)
Agile, because that approach works best in a digital project environment.
40.
The project manager is trying to settle a dispute between two team members. One says the systems should be integrated before testing, and the other maintains each system should be tested before integration. The project involves over 30 people, and 12 systems need to be integrateThe sponsor is demanding that integration happens on time. What is the best statement the project manager can make to resolve the conflict?
a)
Let's do limited testing before integration and finish testing after integration.
b)
Let's deal with this again next week after we all calm down.
c)
Let's calm down and get the job done.
d)
Do it my way.
41.
You have developed a schedule model and a schedule change control system. You are almost prepared to seek approval for the schedule baseline. You need to complete the final schedule planning activities and review the schedule change control system one additional time before seeking approval. Which of the following would you not include in the schedule change control system?
a)
Paperwork necessary for making changes
b)
Approval levels necessary for authorizing changes
c)
Limitations on the scope of changes
d)
Tracking systems
42.
Company management is presented with the following information on the payback period for several possible projects. Which project is the best choice?
a)
Project B with a payback period of 9 months
b)
Project C with a payback period of 12 months
c)
Project A with a payback period of 6 months
d)
Project D with a payback period of 18 months
43.
The project sponsor, Derick, asks you to drop by and give him an update on the agile project you are managing. He wants to know how much work is left to do and when the solution will be ready for release. You are busy working on a deadline and need to get the information quickly. What's the best way to do this?
a)
Sprint out the action points from the last product demo, with notes about what has already been accomplished
b)
Email Derick the team’s latest roadmap and status reports to go over in the meeting.
c)
Take a picture of the team’s burnup chart with your cell phone.
d)
Write down some notes to summarize the information shown on the team’s Kanban board
44.
The human resources department wants to hire a new project manager from within the company. They can choose from the following candidates: Candidate A has good management knowledge, has always been recognized for her leadership and organization skills, and wants challenges and advancement. Candidate B has good project management knowledge, and the organization has invested in his training and does not want to lose that investment. Candidate C has solid technical knowledge, has been with the organization for seven years, and always exceeds expectations on her evaluations; in addition, there are no more promotion levels within her job areCandidate D has general management, project management, and technical skills. Who is the best candidate?
a)
Candidate D
b)
Candidate C
c)
Candidate B
d)
Candidate A
45.
A new mobile app will be developed and delivered incrementally. There is significant uncertainty about the requirements and the project manager wants to make sure all key stakeholders are engaged in product visioning and scoping. What is the first thing the project manager should do?
a)
Get resources committed from each group to help develop the product increments.
b)
Get buy in from all stakeholders on the expected business value of the product.
c)
Get detailed estimates from all development teams for the cost of building the product.
d)
Determine the materials needed to build the product and contact vendors.
46.
Information including desired levels of engagement for stakeholders, and how particular stakeholders will be involved in the project, is included in the:
a)
Communications management plan
b)
Responsibility assignment matrix
c)
Resource management plan
d)
Stakeholder engagement plan
47.
The project manager receives a frantic call from a team lead on the project. The team is assembling the final deliverable, and they are missing an essential component. The project manager remembers placing the order from an international company, and had confirmed it was included in a shipment with other materials from that supplier. What he was not aware of is that this deliverable had to be reworked due to an excessive variance discovered in the Control Quality process, and all of that component was used in the first production of the deliverable. Which of the following processes could have prevented this problem from occurring?
a)
Identify Risks
b)
Control Resources
c)
Manage Quality
d)
Manage Communications
48.
During every project team meeting, the project manager asks each team member to describe the work they are doing, and the project manager assigns new activities to team members. The length of these meetings has increased because there are many different activities to assign. This could be happening for all the following reasons except:
a)
Lack of team involvement in project planning
b)
Lack of a WBS
c)
Lack of a responsibility assignment matrix
d)
Lack of resource leveling
49.
Your next project will have many stakeholders scattered throughout the headquarters office. You are considering adding some agile practices to improve their engagement by making the project information more visible. What would be the best option?
a)
Invite the stakeholders to the weekly scrum of scrums meetings.
b)
Open the team's daily standup meetings to any stakeholders who wish to participate.
c)
Ask the stakeholders to bring their issues to the iteration retrospectives.
d)
Post the team's Kanban and burnup charts on a whiteboard in their team room.
50.
You've been assigned to take over managing a project that should be half complete according to the schedule. After an extensive evaluation, you discover the project is running far behind schedule, and the project will probably take twice the time originally estimated by the previous project manager. However, the sponsor has been told the project is on schedule. What is the best course of action?
a)
Report your assessment to the sponsor.
b)
Move forward with the schedule as planned by the previous project manager, and report at the first missed milestone.
c)
Try to restructure the schedule to meet the project deadline.
d)
Turn the project back to the previous project manager.
51.
During the implementation of a contingency plan, a team member notices the plan worked only marginally. There are three similar contingency plans developed for other risks that have not yet happened. He should recommend which of the following?
a)
A workaround
b)
A project change request
c)
A new risk rating matrix
d)
A risk responsibility chart review
52.
Your project no longer ties into the company's objectives. What is the best thing to do?
a)
Change the target opportunity cost.
b)
Decrease the cost.
c)
Change the CPI.
d)
Extend the schedule.
53.
The obstacle to team building in a matrix organization is that the:
a)
Team organization is technically focused
b)
Teams are too large and therefore very hard to handle
c)
Team members are borrowed resources and can be hard to motivate
d)
Teams are too centralized
54.
You are asked to prepare a budget for completing a project that was started last year and then shelved for six months. All the following would be included in the project budget except:
a)
Sunk costs
b)
Fixed costs
c)
Direct costs
d)
Variable costs
55.
The organization is transitioning to agile development practices. In the past, project managers reported earned value measures to show project progress. Why might a project manager decide not to report earned value for her agile project?
a)
Earned value is a trailing metric that can't predict completion dates.
b)
Earned value doesn't show whether the team is delivering the needed business value.
c)
Earned value doesn't take into account team velocity, which is an key metric on agile projects.
d)
Earned value can't be presented in a visual format, as agile recommends.
56.
The project manager has many roles and responsibilities in leading and directing throughout the change-driven project life cycle. How can your role as the project manager best be described during the executing process of the project?
a)
Coordinator
b)
Director
c)
Expediter
d)
Integrator
57.
The seller on your retooling project has not performed. Although you have provided detailed requirements and a clear statement of work, too many of the delivered components have been defective and it has become clear that the seller will not be able to improve their performance. You are terminating the contract. Which of the following is the best thing to do?
a)
Meet with the seller, explain the problem, and obtain the seller's agreement on termination.
b)
Report the seller to the state agency in charge of the inspection.
c)
Begin procurement closure.
d)
Review change requests.
58.
The project manager has just been assigned to a new project and has been given the approved project charter. The first thing the project manager must do is:
a)
Analyze project risk.
b)
Create a project scope statement.
c)
Confirm which stakeholders had input to the scope.
d)
Begin work on a project management plan.
59.
The project is facing the following risks: 20 percent chance a part is not available, creating an additional fee of US $30,000; 10 percent chance the team requires additional training for a cost of US $12,000; 25 percent chance the second planned quality test costing the US $8,000 is unnecessary. What is the expected monetary value of these risks?
a)
42000
b)
5200
c)
50000
d)
7200
60.
The organization is experiencing extreme financial pressure because of international market fluctuation. The distribution system project that you are managing has been placed on high-priority status, as it is expected to help the organization better manage the cost of business in these uncertain times. The current SPI is 0.98. The sponsor's annual goals are tied to the completion of the project. Each phase of the project must be closed and the deliverables accepted before the next phase can be started. As you start working on the next phase, what are you expected to produce regarding resource management?
a)
Roles and responsibilities, resource management plan, and resource availability
b)
Project management plan updates, resource management plan, and project organization charts
c)
Roles and responsibilities, project organization charts, and a team charter
d)
Project organization charts, physical resource assignments, and roles and responsibilities
61.
The project manager you are mentoring comes to you for help because he is about to face his first procurement audit. You might explain that he should not worry about such an audit because it:
a)
Identifies successes and failures that warrant transfer to other procurements
b)
Makes sure the seller is following the contract
c)
Makes sure costs are in line with the project budget
d)
Makes sure the work is within the budget and schedule
62.
You are a project manager on a US $5,000,000 software development project. While working with your project team to develop a network diagram, you notice a series of activities that can be worked in parallel but must finish in a specific sequence. What type of activity sequencing method is required for these activities?
a)
Arrow diagramming method
b)
Critical path method
c)
Operational diagramming method
d)
Precedence diagramming method
63.
During completion of the project, you notice a deliverable, integral to the project, has not been received. The seller says the work is not part of the contract. You remember discussing it during negotiations and even coming to an agreement, but you cannot find it in the contract. Which of the following best describes this situation?
a)
The deliverable may be described in the specifications and not the contract.
b)
The seller is required to complete the deliverable based on a verbal agreement.
c)
The deliverable is required to be complete
d)
A change to the contract is required in order to get the deliverable.
64.
The product owner asks for your help with one of the developers on the team. This developer's code regularly includes extra components beyond what was agreed upon in the iteration planning sessions. The product owner says that when she asked for rework to remove the extra components in the demo meetings, he argued that they are important and need to stay. The other team members haven't said anything. So far the product owner has let this slide since sometimes the developer's ideas do add value. But she is hoping you can influence him to be more flexible. What should you do?
a)
Talk with the team member alone and relay the product owner's concerns, asking how he plans to address them.
b)
Reward the developer for his innovative ideas but also ask him to document the feedback he has been getting from the product owner.
c)
Attend the next demo, and if this issue arises, engage other team members in discussing whether the code reflects what was planned
d)
Explain to the product owner that the developer is probably correct, since the team members understand the technical details of the software best.
65.
The security design for a hybrid software project was assigned to the architecture team rather than the development team that is actually building the software. Now the architecture team has missed several target completion dates. The development team can't finalize the product features without the security component. A new project manager has now been assigned. What should the new project manager do?
a)
Locate a security design expert and have them assigned full-time to the project until that work is complete
b)
Speak to the architecture team's manager to learn the source of the delay and what they are doing to resolve it.
c)
Recommend that the project be put on hold and the development team assigned to other work until the security design is done.
d)
Speak to the sponsor and inform her of the reason for the delay.
66.
The agile product development team is building a new customer facing mobile feature: in store checkout. While reading the monthly corporate newsletter, the project manager learns that stores in one geographic region have temporarily closed. How should the project manager respond?
a)
Monitor the situation in the next month's newsletter.
b)
No immediate response is needed, many stores are still open and need the new feature.
c)
Recommend to the sponsor that the project be put on hold until the stores reopen.
d)
Contact the stores' operations manager(s) to discuss the closings and re-evaluate the in-store checkout feature's value.
67.
Resource assigned to your project contacts you, trying to get off the team. He knows an important project in his department is going to be approved and will take place at the same time as yours. He wants to work on the other project. Under the circumstances, what is the best thing to do?
a)
Keep him if he is a valuable resource.
b)
Talk to the functional manager about releasing him from the team.
c)
Release him after he finds a suitable replacement.
d)
Wait to see if the other project is approve
68.
The project team is working on an important and complex project that requires a lot of coordination. The organizational benefits must be tracked and measured during the project, and the business value delivered must be quantified at the end of each iteration. The risk reassessments have generated some change requests that have been approved. The quality control department has announced that all project teams that deliver product increments under the defect tolerance rates will be rewarded. There are also incentives for risk management on the project. Under these circumstances, the best strategy is to:
a)
Gain extra assistance from management.
b)
Hire a contractor.
c)
Colocate the team.
d)
Hold more meetings to get the word out.
69.
Which of the following would be the most appropriate thing to do in the executing process group?
a)
Implement project process improvements.
b)
Look for newly arising risks during a review.
c)
Obtain additional funding when needed
d)
Identify and analyze trends.
70.
The manager of an agile project, what can you do to help the team be more productive?
a)
Guide the team's approach to the work to help them accomplish the project goals.
b)
Evaluate and streamline the process for obtaining audit approvals.
c)
Set clear expectations for roles and responsibilities on the project.
d)
Attend and actively participate in all the team's meetings.
71.
What does a resource histogram show that a responsibility assignment matrix does not?
a)
Interrelationships
b)
Time
c)
The person in charge of each activity
d)
Activities
72.
Conflict on projects is usually caused by:
a)
Schedules, project priorities, resources, and technical opinions
b)
Schedules, cost, priorities, and resources
c)
Schedules, personality, priorities, and resources
d)
Schedules, personality, priorities, and technical opinions
73.
You are assigned to manage a new project and realize that the stakeholders don't have a shared understanding of the solution requirements. How can you create this?
a)
Bring all stakeholders together to create a product roadmap and then decompose it into a user story backlog
b)
Invite all interested stakeholders to participate in the team's reviews and retrospectives.
c)
Ask the product owner to detail all the features and their functionality to distribute to all stakeholders.
d)
Make sure that the development team posts their workflow and progress in an easily accessible location.
74.
During a team meeting, a team member asks about the measurements that will be used on the project to assess performance. The team member feels that some of the measures related to activities assigned to him are not valid measurements. The project is most likely to be in what part of the project management process?
a)
Initiating
b)
Closing
c)
Monitoring and controlling
d)
Executing
75.
You and your team are working on developing an orientation program for new hires at a financial management company. The program is made up of modules covering topics ranging from company history and mission to specific company policies regarding attendance and employee evaluation. Midway through your project, you are informed that the human resources department wants to add a module addressing working virtually. The organization has recently begun offering this option to a small group of employees and expects to extend the opportunity to more departments in the near future. You realize that this change in the project introduces a number of new stakeholders whose needs must be incorporated into the product of the project. As soon as you are made aware of their interest and potential impact on the project, you and the team perform stakeholder analysis activities to ensure that these stakeholders are incorporated into the project plans. When new stakeholders are identified after project planning is completed, which components of the project management plan are most likely to be changed?
a)
Scope, communications, and procurement management
b)
Scope, schedule, and requirements management
c)
Communications, schedule, and cost management
d)
Requirements, communications, and risk management
76.
The approximate resource costs necessary for completing project activities are compiled during which project management process?
a)
Cost Aggregation
b)
Estimate Costs
c)
Forecasting
d)
Funding Limit Reconciliation
77.
The development team on your project tells you that they can't make any further progress since they aren't sure what to work on next. What should you tell them to do?
a)
Build the increment that will deliver the most value next.
b)
Follow the sequence for executing the work outlined in the project plan.
c)
Work on the story that will burn down risk as quickly as possible.
d)
Request that the product owner prioritize the backlog more clearly.
78.
The project contracts include purchase orders, fixed price incentive fee contracts, and time and material contracts, based on the need and length of the work. Several sellers have completed their statements of work, and you are working on calculating their incentives. Three items from the issue log have been assigned to a team member. However, no action has been taken by the agreed-upon due date. After three calls to the team member, the work is finally completeYou need to analyze some of the work performance data for the project. The customer has been very impressed with the quality of work performed by a couple of the sellers and thinks that they should be recommended to the organization's preferred list. Which of the following is the best preventive action to take now?
a)
Remove the team member who was late in completing their action items from the team if possible.
b)
Meet with the team member to uncover the reasons why there were problems.
c)
Add additional reserves to the budget based on the length of each contract.
d)
Investigate the financial stability of the sellers before adding them to the preferred seller list.
79.
On the agile project you are managing, you are also serving as the development team's coach. When the team created their team norms, they agreed to keep their working room quiet from 1:00 pm to 3:00 pm each day. There are two small conference rooms nearby for meetings or conversations during this time. At first, the quiet period was respected, but over time the team stopped observing it. Lately, you notice that some of the team members have been complaining to each other that they can't concentrate on their work, and this seems to be affecting their morale. What should you do?
a)
Don't do anything; this is an internal issue for the team members to resolve on their own.
b)
Put up signs to remind people to hold any conversations during quiet time in a conference room.
c)
Hold a team meeting to remind everyone of the team norms and get an agreement to respect them.
d)
Facilitate a team meeting to address the situation and come up with a collective solution.
80.
The two-year project involved several procurements. Many departments within the organization were stakeholders and therefore the project manager spent a long time dealing with conflicting requirements before a final scope statement was created. As interim deliverables were produced, there was often controversy as to whether the deliverables fulfilled the requirements. Several change orders were approved through integrated change control and implemented by the team. Eventually, the product was accepted by all stakeholder groups, and the project moved into closing. It is important to collect project records at the end of the project to:
a)
Support the risks on the project.
b)
Document decisions made on the project.
c)
Support cost decisions.
d)
Recall what happened on the project.
81.
The degree to which a particular stakeholder may be able to positively or negatively affect a project is their:
a)
Level of interest
b)
Level of commitment
c)
Level of engagement
d)
Level of influence
82.
All technical work is completed on the project. Which of the following remains to be done?
a)
Plan Risk Responses
b)
Validate Scope
c)
Complete lessons learned
d)
Create a staffing management plan
83.
Your agile team is struggling to build an application on a new technology platform, and they have decided to dedicate an upcoming one-week sprint to a technical spike. However, while observing their daily standup you hear a team member point out that the spike might not work since they can't control the settings of the test environment. The problem is that they are sharing it with two other teams. What should you do?
a)
Negotiate with the managers of the other teams to get exclusive use of the test environment for one week.
b)
Document the specific problem that is holding up progress, estimate how much time is being wasted, and report it to the PMO.
c)
Report the problem to the PMO in your monthly report for the next executive briefing.
d)
Research the viability of setting up a new test environment for the team before the spike is scheduled to start.
84.
All of the following are true except:
a)
The project manager needs to determine the skills of the stakeholders.
b)
The stakeholder engagement plan is part of the project management plan.
c)
The stakeholders' impact on the project must be assessed
d)
The stakeholders do not have a role in determining the project management plan unless they are part of the project team.
85.
The team members assigned to your new agile project are working from two locations. One group consists of corporate employees in the headquarters office; the other group is offshore and has been contracted for six months. On this team, there is a 10-hour time zone difference and different native languages (although the team members are expected to communicate with each other in English). How can you best coordinate the work?
a)
Ask the people in each location to hold a regular daily standup for their group.
b)
Invite the coach of the offshore group to attend the daily standup at headquarters via video conference.
c)
Schedule a regular daily standup at a mutually convenient time using a conference call number.
d)
Leave it up to the team members to determine how to best communicate with each other.
86.
You will be managing a small project to add a few features to an existing software package that is connected to your online ordering system. The project has a budget and timeline that are more than ample to complete the features within the given constraints, but the change control board members are known to be conservative. Which of the following is the best method to control changes on this project?
a)
Look for sources of changes.
b)
Document the changes quickly when they occur.
c)
Direct all changes to the change control boar
d)
Prevent changes from being made.
87.
While performing quality planning for the design and manufacture of a new medical device, the team has identified the need to keep variances to a minimum because the end product must be of the highest quality possible. They are researching the practices of comparable projects for ideas on how to achieve this requirement. The team is using which of the following techniques?
a)
Cost-benefit analysis
b)
Design for X
c)
Benchmarking
d)
Pareto analysis
88.
project manager is in a meeting with the customer when the customer starts to yell about the fact that a change she requested will result in a delay to the project schedule. Interestingly, yelling is not a common practice in the client's culture. The project manager starts to explain why the change affected the schedule when the project manager's supervisor stops the meeting and asks the project manager to step outside the room with him. Which of the following would best describe what is going on?
a)
There was an inadequate change control system.
b)
There was an inadequate agenda for the meeting.
c)
The project manager did not properly interpret the customer's communication.
d)
The project manager did not inform the supervisor before the meeting.
89.
When is the earliest time administrative closure should be completed?
a)
At the end of each project phase
b)
Whenever a new project manager takes over a project
c)
At the end of the project
d)
Whenever a deliverable is complete
90.
The project manager must publish a project schedule. Activities, start/end times, and resources are identified. What should the project manager do next?
a)
Confirm the availability of the resources.
b)
Refine the project management plan to reflect more accurate costing information.
c)
Distribute the project schedule according to the communications management plan.
d)
Publish a bar chart illustrating the timeline.
91.
A retail chain has a long history of hiring contractors to design and build new stores for them as they expand around the world. An engineer within that organization has just been promoted to project manager. He is studying the science of project management and is getting confused with terms. You are asked to mentor him. He asks you, "Which should I expect to occur more frequently on a typical project, project closure or procurement closure?" Which of the following is the best answer?
a)
Since all the work is always done under contract, project closure occurs more often.
b)
Every time we close out a contract, we close out a project.
c)
All projects are different and there is no real answer to this question.
d)
Since there are typically many contracts in one project, procurement closure occurs more frequently.
92.
The project manager has been working on a project for six months with the same team, yet the team still shows a lack of support for the project. The best thing the project manager can do to obtain the team's support for the project is to:
a)
Talk to each team member's manager with the team member present.
b)
Find someone else to be project manager.
c)
Tell the team members he needs their support, and ask the team members why they do not support the project.
d)
Reevaluate the effectiveness of the reward system in place.
93.
You are the project manager at a software development company, leading a project to develop an innovative application for a client. The project has followed a strict software engineering process. The requirements have been specified in detail, resulting in extensive functional and technical specification documents. Your project team member delivers an interim project deliverable to the buyer. However, the buyer refuses the deliverable, stating it does not meet the requirement on page 300 of the technical specifications. You review the document and find that you agree. What is the best thing to do?
a)
Explain that the contract is wrong and should be changed
b)
Review the requirements, and meet with the responsible team member to review the WBS dictionary.
c)
Issue a change order.
d)
Call a meeting of the team to review the requirement on page 300.
94.
You are working on an 18-month project with a small, colocated team. The project sponsor and senior management are in another city and have requested weekly updates. The customer requires monthly meetings. Because the team members are busy with the project executing work, they would like to reduce the frequency of meetings. Which of the following best describes how status meetings should be managed on this project?
a)
During project executing, you do not need to hold status meetings as long as you send the key stakeholders a status report every week.
b)
The frequency and level of meetings, as well as the format and type of information to be exchanged, should be defined in the project's communications management plan during project planning.
c)
Once a month the entire team, including senior management, should meet with the customer. You should discuss the details of the previous month's issues and the current status.
d)
During project executing, it is only necessary for the project manager to meet with the customer once a month to fulfill the contractual obligation. Provide the customer with the status report, and copy this report to key stakeholders.
95.
You know that some groups within your organization are going to provide input to requirements that may impact your ability to develop a realistic schedule. Managing stakeholder expectations is always important, but achieving stakeholder satisfaction will be more critical with some groups than with others. All the following are parts of the team's stakeholder management effort except:
a)
Determining stakeholders' needs
b)
Managing stakeholders' expectations
c)
Giving stakeholders added value
d)
Identifying stakeholders
96.
While visiting the country where a new branch office is being built, you are told you must pay a US $5,000 fee to the government permit officer to obtain the facility permit required by law to start construction. The construction company tells you this is standard practice and is required by law. If you don't pay the fee, the project could be delayed, which would cost your company money. You have not worked in the country before. You do not speak the official language of the country and are communicating in a shared third language. What should you do?
a)
Have the construction company pay the fee.
b)
Refuse to pay the fee.
c)
Pay the fee.
d)
Have the customer pay the fee.
97.
You estimate there is a 30% chance that your Scrum project will end up needing to create a more advanced filtration unit than originally anticipateThe new unit will require a $210,000 investment and will also delay the delivery of the solution by 4 to 6 weeks. The team members tell you they can't think of any way to completely eliminate this risk. What should you do?
a)
Consult with subject matter experts who can identify and implement strategies for reducing or mitigating this risk.
b)
Request that $210,000 in contingency funds be added to the project budget.
c)
Ask the team to prioritize the development of the filtration system to find out as soon as possible whether it will be needed
d)
Escalate this issue to the engineering department and ask the team to continue working on aspects of the project that aren't affected by it.
98.
The manager of an agile project is explaining to the team how much work has been planned for the next iteration so they can schedule the tasks required to complete it. How would you describe this scenario?
a)
The product owner should be providing that direction, not the project manager.
b)
The project manager doesn't understand the agile planning process.
c)
The scope for each iteration should have been planned up front.
d)
The iteration planning process is proceeding normally.
99.
Senior management has been extremely impressed by a new team member on the software development project. The team member has enthusiastically and efficiently completed his assigned activities. He has also demonstrated courtesy, respect, and consideration to everyone around him. For these reasons, management is planning to promote the team member to a business analyst position that is currently open on the project. The halo effect refers to the tendency to:
a)
Move people into project management because they have had project management training.
b)
Hire the best.
c)
Move people into new roles or new technical fields because they are good in their current technical fields.
d)
Promote from within.
100.
You have just been assigned as project manager for a large manufacturing project. This one-year project is about halfway done. It involves five different sellers and 20 members of your company on the project team. You want to quickly review where the project now stands. Which of the following reports would be the most helpful in finding such information?
a)
Progress
b)
Forecast
c)
Communications
d)
Work status
101.
The first phase of your project has come to an enWhat is the most important thing to ensure is done before beginning the next phase?
a)
Confirm that the phase has reached its objectives, and have its deliverables formally accepted
b)
Check the project's progress compared to its baselines.
c)
Recommend corrective action to bring the project results in line with project expectations.
d)
Verify that the resources are available for the next phase.
102.
Many employees within your organization are working on a long-term project to build a major bridge in the city. This project is scheduled for completion in nine months. In the meantime, the organization accepts another contract to improve a stretch of road in the commercial district of an outlying suburb which must be completed within the next six months. You are assigned to manage this new project, and find that most of the human resources preassigned to your team have little experience. Which of the following will be most critical to ensure the success of your new project?
a)
Include your team members in developing a conflict management plan.
b)
Emphasize the importance of completing the work within schedule and budget.
c)
Collect and analyze performance data
d)
Develop a resource histogram.
103.
The project manager works with the appropriate team members to estimate the time needed to complete each of the activities on the project. The project manager will eventually create the final schedule as part of establishing project baselines. Which of the following best explains why the project manager needs the team's agreement on the schedule?
a)
To get a better cost estimate
b)
To improve communications
c)
To enhance team buy-in and loyalty
d)
To ensure activities can be completed as scheduled
104.
During the Conduct Procurements process, your objective is to obtain the best price possible. You have a variety of tools at your disposal and you have already decided which tools you will use in the seller selection process. You are working with an experienced team, and someone on the team has worked before with at least one of the potential sellers. Moreover, the potential sellers have varying reputations in the industry. The tool that you will most heavily rely upon will be aNo:
a)
Screening system
b)
Weighting system
c)
Summary of past performance history
d)
Independent estimate
105.
The project manager, you have had to develop skills to help you successfully plan and manage projects. Which skills would best help you encourage project teams to reach levels of high cooperation and achievement, promote a positive relationship with sellers on a project, and involve stakeholders appropriately through all aspects of the project?
a)
Networking, communication models, and SWOT
b)
Communication methods, team building, and claims administration
c)
Active listening, negotiating, and political awareness
d)
Sensitivity analysis, active listening, and leadership
106.
In your project, the team is using the scrum approach to build an application that includes a new database. During the project several sprint goals aren't met because the database tasks weren't completeThe data architect is assigned to two other projects. What is the underlying problem here?
a)
The organization didn't send the team members to a training course on database design.
b)
The team doesn't include all the skills needed to create working software.
c)
You didn't get the data architect's functional manager to commit him to the needed sprints.
d)
You didn't plan for a contract data architect to be assigned to the project.
107.
Which motivational theory uses the concepts of esteem and self-actualization?
a)
Maslow
b)
Deming
c)
Herzberg
d)
McGregor
108.
The project manager has been overwhelmed with problems on his project. He would like to identify the root cause of the problems in order to determine where to focus his attention. Which of the following tools would be best for the project manager to use?
a)
Conflict resolution techniques
b)
A fishbone diagram
c)
Logical data model
d)
Trend analysis
109.
You are the project manager for a large project under contract with the government. The contract for this two-year, multimillion-dollar project was signed six months ago. You were not involved in contract negotiations or in setting up procedures for managing changes, but now you are swamped with changes from the customer and from people inside your organization. Who is normally responsible for formally reviewing major changes to the project/contract?
a)
Senior management
b)
The project manager
c)
The change control board
d)
The procurement/legal department
110.
Control chart helps the project manager:
a)
Focus on stimulating thinking
b)
Analyze the cause of a quality problem
c)
Focus on the most critical issues to improve quality
d)
Determine if a process is functioning within established metrics
111.
During project executing, the team member who is most experienced in the programming work required for the project informs you that he has accepted a new position at another company, and has given his two weeks’ notice. This is a major problem that was not included in the risk register. What should you do first?
a)
Look for any unexpected effects of the problem.
b)
Reevaluate the Identify Risks process.
c)
Create a workaround
d)
Tell management.
112.
An agile team is building a training safety video based on current government regulations. The project manager knows that the regulation is likely to change before the release date. How should the project manager address this change?
a)
Monitor regulatory discussions to get a headstart on the upcoming regulation changes.
b)
Verify the team is building the product in increments which could be adapted at the last minute if necessary.
c)
Plan for the second release to include regulation changes and new features.
d)
Ignore it during the current release, without knowing what the regulation change is, it can't be planned for.
113.
The project team has been working on the deliverables. There have been several deliverables that have been accepted, and some refinement of the deliverables and acceptance criteria for others, due to feedback from the customer. You have been active in reviewing the work of sellers to the contracts and evaluating the work performance data to see if there are trends that need to be addressed. In which project management process group are you likely to do more directing?
a)
Monitoring and controlling
b)
Planning
c)
Executing
d)
Initiating
114.
Which motivational theory uses the concept of Theory Y?
a)
Herzberg
b)
Maslow
c)
McGregor
d)
Deming
115.
During a team meeting, the team has been arguing about the method of integration for over 20 minutes without getting anywhere. The project manager reschedules the issue for the next team meeting. This is an example of:
a)
Forcing
b)
Compromising
c)
Smoothing
d)
Withdrawal
116.
The project cost performance index (CPI) is 1.02, the benefit-cost ratio (BCR) is 1.7, and the latest round of performance reviews identified a few required adjustments. The project team was colocated in a new building when the project started. Everyone commented on how excited they were to have all the new facilities. The sponsor is providing adequate support for the project and few unidentified risks have occurred. In an attempt to improve performance, the project manager spends part of the project budget on new chairs for the team members and adds the term "senior" to each team member's job title. Which of the following is the most correct thing that can be said of this project or the project manager?
a)
The project is slowly spending more money than it should The project manager should begin to watch costs more carefully.
b)
The performance review should be handled better to find more adjustments.
c)
The project manager should use good judgment to determine which variances are important.
d)
The project manager misunderstood Herzberg's theory.
117.
You are planning a series of projects to build a new website. The site will be built in stages, and each stage will be a separate project. You understand your project's needs will change as the project progresses from defining to designing. A team meeting during project executing is the best format to:
a)
Authorize changes to the project.
b)
Make changes to the project.
c)
Determine project status.
d)
Communicate.
118.
After extended meetings with various stakeholder groups, you have ended up with many conflicting requirements. You have used your interpersonal skills to facilitate some resolution, but eventually determine that you will use voting to finalize the prioritization of requirements. All of the following describe approaches to decision-making using the voting technique except:
a)
Consensus
b)
Plurality
c)
Majority
d)
Unanimity
119.
Project setup costs are an example of:
a)
Overhead costs
b)
Variable costs
c)
Fixed costs
d)
Opportunity costs
120.
Which of the following is the most appropriate thing to do in the planning process group?
a)
Determine high-level stakeholders.
b)
Hold a meeting of all parties to make certain everyone is familiar with the details of the project.
c)
Manage Quality.
d)
Implement approved process improvements.
121.
You need to procure services for an upcoming project to assess the need for and carry out cleaning and maintenance of three large office buildings your company has acquired. The seller will first make needed repairs and improvements, and then clean the offices and public spaces within the buildings. Once this project is completed, the seller may be awarded the contract for ongoing maintenance and repair, depending upon their performance during the project. You want to be sure that by the time of the bidder conference, you have given every prospective seller an equal opportunity to be prepared for the conference. Which of the following is the best thing to do at a bidder conference?
a)
Make sure the sellers ask all their questions.
b)
Answer sellers' questions.
c)
Meet the sellers' teams.
d)
Make sure the sellers have all the procurement documents.
122.
Which of the following needs to be completed before resources can be finalized for the project?
a)
Bar chart
b)
Work breakdown structure
c)
Estimates
d)
Validate Scope
123.
The sponsor has identified four key stakeholders as potential product owners, and asks the project manager to choose the one that would be best for the project. The project manager has met with each of these stakeholders to assess their potential for the product owner role. Which stakeholder should the project manager choose?
a)
Stakeholder D (Jose) is a user representative who knows the day-to-day operations of the business well and can explain why certain product features are critical. He tends to be quiet during meetings.
b)
Stakeholder A (Nima) is an experienced business expert. She has specific expectations and opinions, as well as a forceful personality. She manages two groups of employees who will be using the new product.
c)
Stakeholder C (Travis) is a director in the business areHe has extensive business knowledge and authority. Since he is too busy to attend every working session himself, his business analyst will attend and report back to him.
d)
Stakeholder B (Dagmar) is a newer business expert. She is very smart, learns quickly, and is eager to help the project. She also has time available to participate. The team members like her, and she tends to have a calming influence.
124.
The development team can make changes to a customer-facing website in every iteration, and the project manager is evaluating how often to deliver incremental changes to the customer. How should that decision be made?
a)
The team should plan to implement a change whenever it will provide a significant improvement to the customer experience.
b)
The product owner should bundle the user stories for complex changes by iteration so the team can isolate the causes of defects.
c)
The team should consider the number of customers affected by a change and the amount of time needed to test it.
d)
The product owner should evaluate the user disruption introduced by a change against the additional value it adds.
125.
The project is slightly behind schedule. Things would be worse, except for the fact that the project manager makes daily follow-up calls to each of the team leaders to remind them of his expectations and to receive updates on their progress. Without this level of involvement, deadlines were missed and the project manager believed the project success was in jeopardy. Having to constantly push the team to perform is an example of a lack of:
a)
Project continuity
b)
Team accord
c)
Team buy-in
d)
Management support
126.
To justify adopting agile, senior management in your organization has asked you to lead a pilot project to prove the value of the new approach. What areas should you focus on (or ask your team to focus on) to best assure management that the new approach will generate high business value?
a)
Preparing a clear project charter and a thorough risk analysis
b)
Mapping the benefits achieved to the original objectives during project closing.
c)
Writing relevant user stories and thoughtfully prioritizing the backlog items.
d)
Carefully selecting the most skilled and knowledgeable team members.
127.
You have accepted a position at a company where you will manage a group of projects in a coordinated way. This organization specifically hired you to start a project management office to help it develop a more structured approach to project management. What should you do first?
a)
Study the history of the organization.
b)
Meet with key stakeholders to better understand the organization and projects.
c)
Get your job description changed to either project management or project management office work, but not both.
d)
Focus on communications with your manager and other senior managers.
128.
Major project with an estimated cost of US $22 million has completed the second phase gate. Two team members are having a disagreement in choosing the potential sellers of a project component, and the project manager has offered to help. The project manager suggests a compromise. Who should decide on the best course of action?
a)
Customer
b)
Project manager
c)
Team members
d)
Management
129.
You believe that the project you have undertaken is relatively straightforward, with less risk than most other projects you have worked on. Therefore, you do not spend a long time on risk identification. While preparing your risk responses, you identify secondary risks that could result in serious consequences later in the project. What should you do?
a)
Add a 10 percent contingency to the project budget and notify the customer.
b)
Add reserves to the project to accommodate the new risks and notify management.
c)
Document the new risks and calculate the expected monetary value based on the probability and impact of the occurrences.
d)
Determine the risk events and the associated costs, then add the cost to the project budget as a reserve.
130.
You are a project manager leading a cross-functional project team in a weak matrix environment. None of your project team members report to you functionally, and you do not have the ability to directly reward their performance. The project is difficult, involving tight schedule constraints and challenging quality standards. Which of the following types of project management power will likely be the most effective in this situation?
a)
Penalty
b)
Expert
c)
Formal
d)
Referent
131.
Virtual team has been assigned to build a new product that has a tight deadline. The team members are working on different continents. Two expert engineers on the team have provided an initial design that will be refined by the team and evolve based on product owner feedback. Since the project manager has a limited budget, what would be the best use of her funds?
a)
License an always-on video conferencing link so team members can work face-to-face.
b)
Bring all the team members to a week-long, in-person workshop to allow them to meet and kick off the work.
c)
License a shareable product backlog repository where the team members can adjust the stories and view the priorities.
d)
License a collaborative diagramming tool where team members can share their blueprints, drawings, and feedback.
132.
The QA lead on an agile project is explaining to you, the project manager, that she has found a way to shorten the "testing cycle time." What is she trying to do?
a)
Reduce the duration of all the testing iterations
b)
Decrease the time required to build and test a user story.
c)
Speed up the time required to complete a deliverable, from eliciting requirements to deployment.
d)
Shorten the time required for a work item to complete the testing phase
133.
The project manager for a large international bank has a project team that just implemented an electronic funds project involving four large vendors. The project manager struggled through every part of the procurement process since the bank had a weak internal procurement department. What would be the most appropriate thing to do to ensure the problems are resolved for future projects?
a)
Document the problems in the company's issue log.
b)
Conduct a procurement audit.
c)
Document all the issues in a memo, and schedule a meeting with the head of the procurement office.
d)
Include an agenda item in the project closure to discuss these issues in a nonthreatening manner.
134.
The development team on your project is new to agile. They are about two months into the project and have been doing well getting familar with agile practices. However, in the last two sprints they've started having problems. Each time, they committed to deliver a large user story, but didn't get all the work done. Now they are frustrated and looking for a way to improve. They are using three-week sprints and are thinking of extending them to four weeks. Since you have more experience with agile projects, they are asking for your input. What should you do?
a)
Tell the product owner that the planned features are too ambitious and need to be scaled back.
b)
Support their conclusion that it would be best to extend their sprints to four weeks.
c)
Email them an article about story slicing and the value of small stories.
d)
Meet with them to get a better understanding of why they aren't able to complete the stories.
135.
On your project, two scrum teams and two support teams are working together to build the solution on a new technology platform. After hearing about significant rework and delays on one of the scrum teams you determine that the problem is poor communication between the teams. What should you do to fix this?
a)
Ask a member of each team to attend a weekly scrum of scrums meeting to coordinate the work.
b)
Ask the support team managers to send a weekly email to the scrum teams listing the updates made to the platform.
c)
Ask the two scrum masters to meet with the support team managers on a regular basis.
d)
Ask the support teams to attend the scrum teams' daily scrums and explain their updates.
136.
The project manager is meeting with a team member and says, "I know you want to be involved in meetings with the customer. Because of your performance on the project so far, I have rearranged things so you can have that opportunity." This is an example of:
a)
Reward power
b)
Team performance assessment
c)
Project performance appraisals
d)
Team building
137.
Conduct Procurements is a part of which process group?
a)
Planning
b)
Initiating
c)
Monitoring and controlling
d)
Executing
138.
Project team member has completed his work on the project. The team member has let you know that because of the skills he has learned on the project, he will be applying for a new job, and would like you to provide a written reference for him. The team member received special training to do work he was assigned to complete, and you know the only reason the functional manager agreed to pay for a portion of the training was that she expected the team member to use the new skills in maintaining the project deliverables once the project is complete. Which of the following must you do?
a)
Update the employee's records with the new skills acquire
b)
Provide the team member with documentation of the training he receive
c)
Refuse to provide a reference.
d)
Consult with the functional manager.
139.
Project manager has just found out that a large subcontractor for her project is consistently late delivering work. The project team member responsible for this part of the project does not get along with the subcontractor. To resolve the problem, the project manager says, "You both will have to give up something to solve this problem." What conflict resolution method is she using?
a)
Compromising
b)
Communicating
c)
Collaborating
d)
Smoothing
140.
Progressive elaboration means:
a)
Distinct processes are developed for each project.
b)
Implementation of the project must progress strictly according to the initial project management plan.
c)
Project management plans must be elaborate in order to be effective.
d)
Project processes are iterated as more information is uncovered throughout the project life cycle.
141.
Four stakeholders are the key to your project’s success. Which elicitation technique should the product owner use for each one? Dave is an introvert who is an expert in the business areMarsha is very experienced but not very organizeSandra is the most efficient worker in the business areFelix knows quite a bit about the competition.
a)
Marsha – Mind mapping, Dave – Interview; Felix – Benchmarking; Sandra – Observation
b)
Dave – Interview; Sandra – Benchmarking; Marsha – Interview; Felix – Observation
c)
Sandra – Mind mapping, Sandra – Interview; Dave – Benchmarking; Felix – Observation
d)
Sandra – Observation, Sandra – Interview; Dave – Benchmarking; Felix – Mind mapping
142.
The project manager is looking at the project's resource needs and lessons learned from past projects. This information causes the project manager to be concerned about her ability to acquire enough resources for the project in six months. Which of the following would be the least effective preventive action?
a)
Make sure functional managers have a copy of the resource histogram.
b)
Ask functional managers for their opinions.
c)
Show the sponsor the data, and explain the project manager's concern.
d)
Determine metrics to use as an early warning sign that resources will not be available.
143.
There are three sponsors for the project. They are all very concerned about cost, and how and when the project will contribute to meeting the strategic objectives of the organization. There have been some tense discussions that required you to use your negotiating, facilitation, and conflict management skills. The most common source of conflict on projects is:
a)
Cost
b)
Priorities
c)
Personality
d)
Schedules
144.
Which of the following is a common problem in the Close Project or Phase process?
a)
Completing a project charter
b)
Completing the quality assurance plan
c)
Retaining resources to complete the project
d)
Obtaining scope validation
145.
Project manager has a very large project budget, but the team lacks experience and adequate management support. Under these circumstances, what is the most effective way to get the work completed?
a)
Inform the team they do not need to worry because the project manager will provide the technical expertise.
b)
Inform the team members that they will be fired if they do not perform.
c)
Provide bonuses for meeting specific quality measures.
d)
Spend some of the project budget taking the team members' managers to lunch and discuss the benefits of the project.
146.
You've been assigned to a project that aims to develop an innovative digital device for a consumer products company. The company has asked you to use an agile approach to product development. The product owner has worked on agile projects before and is excited to work with you. What should you do first?
a)
Ask for an existing cross-functional team to be dedicated 100% to the project.
b)
Develop the budget for the project based on the project charter.
c)
Get specific product requirements from a customer focus group.
d)
Lay out a product roadmap that shows the features and releases.
147.
The iteration planning sessions for your project have been running five or six hours long. You have started catering lunch for the participants to make those meetings more tolerable, but the team members still dread them, even with the free lunch. What should you do?
a)
Suggest that the team focus their next retrospective on improving iteration planning.
b)
To break up the long meetings and make them more inviting, start taking the team out to lunch.
c)
Shorten the meetings by reducing the number of people who are attending and participating.
d)
Work with the product owner to make sure the backlog is clearly prioritized before the meetings.
148.
The project manager is assigned to a new project and is supplied with a pre-selected team. What is the first thing the project manager should find out about the team?
a)
Each team member's project activities
b)
Each team member's history with the organization
c)
What each team member wants to get out of the project
d)
Each team member's role in the project management plan
149.
Before beginning to execute the project, the project manager gets agreement from team members on how weekly project status updates will be distributed and gets the commitment of team members to review these status reports and other project communications. About midway through the project, the project manager learns most members of the project team are not reviewing the weekly project updates. What should the project manager do?
a)
Create a signature log so team members can indicate when they have read the project updates.
b)
Improve the layout of the weekly project updates to encourage reading by team members.
c)
Revise the communications management plan to meet the informational needs of the stakeholders.
d)
Require the reading of the project updates in order to receive any rewards on the project.
150.
A hybrid team working on a product for a plastics manufacturing firm has decided to use the following agile activities. What is the focus of each one?
a)
Sprint review – Confirmation of current iteration; Release planning – Create a roadmap; Retrospective – Review and reflect; Sprint planning – Reassign incomplete work
b)
Sprint review – Confirmation of current iteration; Release planning – Create a roadmap; Release planning – review and reflect; retrospective – reassign incomplete work
c)
Release planning - reassign incomplete work; Retrospective – Create a roadmap; Sprint review - Confirmation of current iteration; Sprint planning – review and reflect
d)
Release planning - Review and reflect; Retrospective – Create a roadmap; Sprint review - Confirmation of current iteration; Sprint planning – Reassign incomplete work
151.
On your way into an upcoming meeting, you need to get a quick update on how much work your Scrum team has gotten done in the last two sprints. What is the best way to get that information?
a)
Skim the team's last two weekly status reports.
b)
Take a quick look at the team's Kanban boar
c)
Check the velocity chart in the team's workroom.
d)
Ask the team's Scrum Master to give you a quick update.
152.
You are working to develop a project charter for a proposed project. You need enough high-level information regarding the project to assess whether it is feasible within the given constraints. You will not do any detailed planning until you know your project has been selected over the many others your organization is considering. What is the cost of choosing one project and giving up another called?
a)
Fixed cost
b)
Net present value (NPV)
c)
Sunk cost
d)
Opportunity cost
153.
If the team is creating more efficient processes and eliminating waste on the project, they are involved in:
a)
Controlling quality
b)
Enhancing scope
c)
Gold plating
d)
Continuous improvement
154.
All of the following are parts of the Close Project or Phase process except:
a)
Transfer information from one phase to the next phase
b)
Regression analysis
c)
Validate Scope
d)
Record the reasons for termination
155.
While creating the agenda for a status meeting with the team, a project manager receives input from one team member that an item should be addeAnother team member says the team is not ready to resolve the item during the meeting. After much discussion, the project manager decides to put the item on the agenda as an initial discussion item only. Which conflict resolution technique is the project manager using?
a)
Smoothing
b)
Collaborating
c)
Withdrawal
d)
Compromise
156.
At a critical milestone in a development project, it is determined that implementation is two months behind schedule. The project manager is concerned the root cause is lack of conformance to requirements in the design of the new billing system. More extensive measurements are taken to see if this is, in fact, the problem. Such measurements are:
a)
An example of Control Quality
b)
Part of the Perform Integrated Change Control process
c)
Not needed; the schedule should be compressed
d)
Not going to show why the schedule is delayed
157.
The principal use of a Pareto diagram is to:
a)
Help predict future problems
b)
Focus attention on the most critical issues
c)
Quantify risks
d)
Improve risk management
158.
As the manager of an agile project, you read online that a competitor is about to release a new device that offers the same innovative functionality that your team is working on. What should you do?
a)
Tell the product owner to immediately reprioritize the backlog.
b)
Do some research to determine whether the team’s product will still have a unique angle.
c)
Recommend to the project sponsor that the project be canceled
d)
Ask the product owner if this news changes the viability of the project.
159.
Your business analyst estimates there is a 25% chance that new regulations will be passed to tighten the testing requirements for the product your agile project is developing. This would require adding two additional rounds of testing, with a potential cost of $750,000 each. You've asked the team if there is anything they could do to avoid or mitigate this risk, but they don't have any suggestions. As the project manager, what should you do?
a)
Hold a workshop with the product owner, the team, and key subject matter experts to identify risk mitigation options and turn them into user stories for the backlog.
b)
Ask the development team to do more research and come up with some risk reduction options for you to consider.
c)
Use the business analyst's data to recommend to senior management that the project charter be re-evaluate
d)
Since nothing has happened yet, tell the team to keep working toward their existing release roadmap; wait to respond until the regulations are actually passe
160.
Partway through your project, you determine that a “gulf of evaluation” has occurred. What is the best course of action to address this?
a)
Document this in the issue log.
b)
Revisit the Plan Stakeholder Engagement process.
c)
Recreate the stakeholder assessment matrix
d)
Revise the project stakeholder strategy.
161.
The stakeholders have been identified and analyzed. The deliverables have been broken down to a manageable size. The stakeholders are working on evaluating the probability and impact of all the risks identified. In which project management process group is the project manager likely to do more coaching?
a)
Executing
b)
Planning
c)
Monitoring and controlling
d)
Initiating
162.
Your company puts a new product into the marketplace without any reports of problems. However, your internal research indicates there is a possibility of a malfunction that could cause serious injuries. You estimate that modifications to eliminate this possibility would cost the US $20,000,000. What should you do?
a)
Recall all existing products.
b)
Wait until an injury to verify the impact.
c)
Obtain insurance to cover the anticipated damages.
d)
Make the necessary modifications to the products in production.
163.
After each iteration, the team posts a new feature burndown chart to show their progress. The project manager reviews that chart to prepare his report to the sponsor. At the end of iteration 6.2, the features remaining and the features completed lines are both rising. What will the project manager report to the sponsor?
a)
The team's story point estimates for this set of features were not accurate.
b)
The product owner has added new requirements, and the cost of the product may go up.
c)
The team wasn't able to complete all the stories selected for this iteration, so an additional iteration has been schedule
d)
The team's velocity was lower than average for this iteration.
164.
You have been planning a project that will result in many changes to your company's business model. The team that will execute the project management plan has been identified, and you expect to get approval to kick off the project soon. You've just learned that your project will impact the work of 600 administrative-level employees who are otherwise not involved in any aspect of your project. What is the best thing to do?
a)
Create a stakeholder engagement assessment matrix.
b)
Modify your stakeholder engagement plan to include information sessions for the 600 people.
c)
Add the 600 people to the stakeholder register and interview them to assess what their needs are.
d)
Get the stakeholders' sign-off that the requirements have been finalized
165.
Your project has been tasked with developing an innovative new type of dental implant. The product owner has explained to the team the problem the business is trying to solve, but she hasn't clearly explained exactly what the device should look like or how it should work. The team is wondering how to proceed, and they have come to you for guidance. What should you tell them to do?
a)
Try the most promising approaches in short iterations and learn as you go.
b)
Ask the product owner for more detailed information about the product.
c)
Follow the project plan as closely as possible.
d)
Perform a risk-based spike.
166.
Team members are arguing about the location of specification limits on a control chart. The discussion is becoming heated when the project manager walks in and says, "It seems that the real problem here is that we do not have enough information about the customer's specifications. Let's do (this)." This is an example of:
a)
Asserting the project manager's authority
b)
Problem-solving
c)
Compromising
d)
Withdrawal
167.
A successful project manager is required to use knowledge, skills, and abilities in a number of different areas of expertise. Planning ability is very important, as is the ability to execute, manage, and control the project according to the project management plan. Which area of expertise is most important for a project manager?
a)
Technical expertise
b)
Communication
c)
Team building
d)
Project control
168.
In planning an upcoming agile project, the project manager estimates there is a 10% chance that virtual servers will need to be added to the cluster to handle the increased processing loaThe IT department will absorb the cost of adding the virtual servers. However, upgrading the server cluster is likely to delay the delivery of the solution by two weeks, which could have a potential impact of $600,000. What should the project manager do?
a)
Notify the product owner about this risk and wait for direction about how to procee
b)
Add a three week contingency to the project schedule to cover this risk
c)
Work with the team to write a risk mitigation user story that can be added to the backlog in case this risk occurs.
d)
Ask the team to do a spike at the start of the project to test whether the server cluster will need to be upgraded
169.
You are the project manager working on a complex structural engineering project. Not an engineer yourself, you will require the assistance of several subject matter experts during the procurement process. In addition to the subject matter experts, the organization has a procurement department that will provide resources for the procurement process on this project. Which of the following best describes the project manager's role in the procurement process?
a)
The project manager should be the negotiator.
b)
The project manager has only minor involvement.
c)
The project manager should provide an understanding of the risks of the project.
d)
The project manager should tell the procurement manager how the procurement process should be handle
170.
After a product visioning session and the drafting of a product roadmap, the project manager submits an estimated budget for her agile project. Why is she confident that her budget is accurate?
a)
A similar product was developed last year, and the project manager based her budget on those actual costs.
b)
The expenses will be low since the project team will consist of internal employees.
c)
The features for each release have been selected and estimated by the development team.
d)
A stable agile team has been selected and a six-month timebox has been agreed to.
171.
The organization has four projects from which to choose one. Project A is being done over a six-year period and has a net present value (NPV) of US $70,000. Project B is being done over a three-year period and has an NPV of US $30,000. Project C is being done over a five-year period and has an NPV of US $40,000. Project D is being done over a one-year period and has an NPV of US $60,000. Which project should they choose?
a)
Project B
b)
Project D
c)
Project C
d)
Project A
172.
Your agile project is developing a digital device that will be used by surgeons in the operating room. The development team is quite experienced, but they haven't worked on a product that will be used in the operating room environment before. What would you recommend they do to better understand what surgeons are looking for in this setting?
a)
Prepare some mockup product prototypes and ask for feedback from a small group of surgeons
b)
Write use cases for the different ways the product might be used, both within and outside of the operating room
c)
Research the technical requirements that apply to products used in an operating room
d)
Create some personas to work through what surgeons need and value in this environment
173.
Different stakeholders bring different types of involvement to a project. Match the involvement with their impact.
a)
Knowledgeable – Approves priorities; Authority – Creates backlog; influential – Steers unofficial impact; Interested – Brings energy to project;
b)
Interested – Brings energy to project; Knowledgeable – Creates backlog; Authority – Approves priorities; influential – Steers unofficial impact.
c)
Interested – Brings energy to project; Knowledgeable – Creates backlog; Authority – Steers unofficial impact; influential –Approves priorities
d)
Interested – Brings energy to project; Knowledgeable – – Steers unofficial impact; Authority - Creates backlog; influential –Approves priorities
174.
Project manager works in a company that has a matrix organizational structure. A server administrator is assigned to the project manager's project team. The server administrator is not taking direction from the project manager, and the delay in the server administrator's activities is causing a negative variance to the schedule. The server administrator works for the director of server administration. Who is primarily responsible for solving this problem?
a)
The server administrator
b)
The sponsor
c)
The director of server administration
d)
The project manager
175.
At the start of the new project, a project manager spends time identifying organizational process assets that will be helpful in planning efforts. Organizational process assets may include all the following except:
a)
Risk identification checklists
b)
Policies and procedures
c)
Lessons learned
d)
Legal restrictions
176.
new regulation is passed that requires the sales team to report the funding sources of potential clients. The compliance officer describes the required system changes to senior management, and they decide to initiate a project to update the software that runs the sales application. But when the project manager informs the sales team about the proposed details of how the system is changing, they say this is unnecessary extra work that will interfere with their productivity. What should the project manager do?
a)
Schedule a meeting with the compliance officer and the sales team to choose the product owner.
b)
Inform the sponsor that the sales team isn't cooperating with the project.
c)
Schedule a meeting for the compliance officer to explain the new regulatory requirements to the sales team.
d)
Prioritize making the reporting procedure as automated as possible so the sales team won't complain too much.
177.
Your project has been running for about two months, and the team has been holding an iteration planning meeting every two weeks. The planning meetings for the iterations have been running between 4 and 6 hours long. However, you notice that the meeting for the current iteration only took two hours. What should you do?
a)
Review the iteration backlog to see if it includes the same number of stories as the previous iterations.
b)
Ask the product owner for an explanation of the sudden change in planning time.
c)
Attend the iteration demo to see how much work was completed and whether the product increment is accepte
d)
Ask the team about the difference to find out whether they have figured out a way to streamline their planning process.
178.
As the project manager, what would be the best way to maximize the value delivered by your agile project?
a)
Ensure that the product owner is available to interact with the team daily.
b)
Keep the team fully informed about any changes that might affect their work.
c)
Make sure the development team consists of functional specialists.
d)
Carefully review each product increment and provide prompt, actionable feedback.
179.
You have been assigned to manage a project to develop centralized administration of employee benefits for a large company with locations throughout the country. Currently, this is handled by each location within their human resource department. The charter requires you to form your team with representatives of at least half of the locations, to take advantage of their expertise in the various approaches, and to develop a solution using a combination of the best practices. Which of the following terms best describes the form your project team will take?
a)
Virtual
b)
Partnership
c)
Part-time
d)
Dedicated
180.
Strategic benefit delivery and cost-benefit optimization in a short period of time are of critical importance to key stakeholders. Many of the project management team and project team members are from different areas of the organization and work in different physical locations. Receiving input from customers on a frequent basis is a part of the organizational approach to projects. You recommend to management that the team for this project is colocated because colocation can help with:
a)
Decreasing project time
b)
Building the team
c)
Bringing customers together
d)
Decreasing project rental costs
181.
An output of the Close Project or Phase process is the creation of:
a)
Project archives
b)
A project charter
c)
A project management plan
d)
A risk management plan
182.
A project has just started the second phase, in which work packages are being createA new team member has completed his work packages for this phase, and has asked the project manager to validate the scope of his work packages. The team member is anxious to have the customer see his work packages. The project manager, although confident in this new team member, wants the team member to gain confidence after the customer sees his work packages. When should the Validate Scope process be done?
a)
At the beginning of the project
b)
At the end of each phase of the project
c)
During the planning processes
d)
At the end of the project
183.
The original scope baseline for your project is largely intact, although a number of small changes have led to the redefinition of a few of the product components. A team member determines the scope for her activity is no longer valiShe comes to you for advice on making a change. To which of the following documents should you refer to make this change?
a)
The cost management plan
b)
The project management information system
c)
The scope management plan
d)
The work authorization system
184.
Co-located team of employees is assigned to work with a remote team of contractors in another country. Language and time zone differences are making their collaboration difficult. What should the project manager do?
a)
Assign different features to each team so they can work independently.
b)
Acquire an online collaboration tool to allow the teams to work more closely together.
c)
Arrange for one of the teams to relocate for six months to the other team's location.
d)
Set up a 24-hour video conference call in each of the team rooms.
185.
Which of the following is the primary output of the Develop Team process?
a)
Resource calendars
b)
Updated issue log
c)
Resource management plan
d)
Team performance assessment
186.
While creating a WBS and activity list for the development of a new smart phone application for fantasy football players, the project team had the input of several experts from the IT department. Those experts have been temporarily reassigned to another project but are expected to be available when executing on this project begins. During the Define Activities process, the team discovers they do not know enough to define the activities for 30 percent of the work packages. What would be the best course of action?
a)
Include this problem as part of risk identification.
b)
Continue on to the Sequence Activities process and define the activities at a later date.
c)
Redo the Define Scope process.
d)
Review the project charter with the sponsor and the team.
187.
Management wants the project completed in 40 days. The cost performance index (CPI) is 1.1, the project critical path duration is 38 days with a standard deviation of two days. What is the maximum project float?
a)
Zero days
b)
Four days
c)
Two days
d)
One day
188.
Project manager had a complex problem to solve and facilitated a team decision about what needed to be done. A few months later, the problem resurfaceWhat did the project manager most likely not do?
a)
Perform proper risk analysis.
b)
Have the project sponsor validate the decision.
c)
Use an Ishikawa diagram.
d)
Confirm the decision solved the problem.
189.
Your project team has been asked to develop a mobile app for customers. Rather than spending months surveying customers about what features they want to see, management has assigned a product owner from marketing and asked them to work with your development team to quickly build a first release and see how well it is adopteThey are not sure of the payback but are willing to invest in trying out the concept and assessing the results. What is the biggest risk to this project?
a)
Few customers use the app.
b)
The app only provides a few valuable features.
c)
The app is so popular that immediate cloud storage upgrades are required to handle the volume.
d)
The app is poorly reviewed, which decreases customer satisfaction with the company.
190.
For the last three months, a customer has been from two to four days late with her approvals on deliverables. After analyzing the situation, the project manager decides withdrawal is the best conflict resolution technique to use. Which of the following reflects withdrawal?
a)
Inform the customer that late approvals are not a problem, but ask him or her to try to get them in on time in the future.
b)
Postpone a decision.
c)
Call the customer and demand that you receive the approvals today.
d)
Meet with the customer to determine a new due date for approvals.
191.
Sustainable development project has been assigned to you. The project work will be completed in several countries. The sponsors are asking how you will account for costs. Many of the anticipated costs are from different sources than what the funding organization is used to paying. The discussion has become heated on some issues. There's one issue that has come up several times that must be clarified: payment for routine government action by a foreign official is:
a)
A bribe
b)
Not payable upon violation of government law
c)
Allowed only if they process the project schedule
d)
Allowed
192.
New project manager is walking you through the schedule she has created for her project. She asks you about the duration of a particular milestone, so she knows how to properly schedule it. What will you tell her about a milestone's duration?
a)
It has no duration.
b)
It is shorter than the activity it represents.
c)
It is the same length as the activity it represents.
d)
It is shorter than the duration of the longest activity.
193.
The project you are managing is following the lean approach to developing software for automated loading vehicles. Which effort should you ask the team to prioritize for this project?
a)
Use emotional intelligence to elicit stakeholder requirements.
b)
Shorten the time it takes to deploy a new feature after it’s identified
c)
Research innovative new features.
d)
Develop prototypes of new features for technical review.
194.
You are managing an agile project to develop in-cab dispatch software for a trucking company. A week before a pilot with a small group of beta test drivers, the ticket printing functionality required for Department of Transportation regulations isn’t working. As the project manager, what should you do?
a)
Delay the pilot until the ticket printing functionality is ready.
b)
Facilitate a meeting with the team and the product owner to help them come to a decision.
c)
Ask the drivers to create paper tickets, as they have done in the past.
d)
Gather data to inform the product owner so that he can make a decision.
195.
“What information needs to be collected when” is part of which of the following?
a)
Earned Value Communication
b)
Plan Communications Management
c)
Formal reporting
d)
Manage Stakeholder Analysis
196.
Which of the following is the best way to resolve conflict?
a)
Smoothing
b)
Collaborating
c)
Withdrawal
d)
Forcing
197.
"Do the work because I have been put in charge!" is an example of what type of power?
a)
Formal
b)
Expert
c)
Penalty
d)
Effective
198.
You are managing an agile project to develop an online course in teaching English as a second language. As planning begins, the subject matter experts have lots of creative ideas for complex interactive games and simulated real-world scenarios, but the developers say that most of these ideas aren't feasible within the project constraints. Both sides look to you to resolve this impasse. What do you say?
a)
The team needs more detailed information about exactly what they need to build
b)
The team just needs the final content, they don’t have time to experiment with all these crazy ideas.
c)
We'll select the most promising ideas to build first, then we’ll proceed from there.
d)
We need to narrow down the ideas and focus on those that we already know are workable.
199.
The project has been going relatively well even though there have been some problems with resource availability and the project scope has changed more than was expected. The project is now completing one of its phases. Of all decisions the sponsor must consider during an end-of-phase review meeting, the most difficult is:
a)
Decreasing the scope to maintain the budget
b)
Authorizing scope change for the next phase
c)
Authorizing budget increases for the next phase based on scope changes
d)
Canceling the project
200.
Your company uses both predictive and adaptive approaches depending on the needs of each project. Your next project involves creating a cutting-edge new device and trying to get it to market before your competition, who are also racing to get to market first. Which option should you choose?
a)
Kanban, because its iterative approach works best for high-criticality projects.
b)
Agile, because its approach allows a working device to be built quickly, with maximum flexibility.
c)
Hybrid, because a combination of methods will best draw upon the strengths of your organization.
d)
Predictive, because detailed planning is essential for time-critical projects.