To adapt to the dynamic market environment, a company's executive team decides to adopt a new organizational structure. There are various options on the table. The project managers currently employed by the company are concerned that their level of authority will be impacted.
What level of authority will the project managers have in each type of organizational structure should it be selected by the executive team?
Functional
Little or none
Weak matrix
Low
Balance matrix
Low to moderate
Strong matrix
Moderate to high
Project oriented
High to almost total
A project manager facilitates a meeting with the project team to discuss the best technical approach to produce a complex project deliverable. A senior developer disagrees with the solution suggested by the rest of the team members, and the argument becomes heated. The project manager steps in to suggest various alternatives to resolve the conflict.
Withdraw/avoid
Postpone the issue for potentially resolving it later
Smooth/accommodate
Focus on those points that the team members agree on
Compromise/reconcile
Suggest an idea that would partially satisfy everybody
Force/direct
Support the solution suggested by the senior developer
Collaborate/problem solve
Continue the discussion until a win-win solution is found
A project manager reviews the burndown chart that shows the progress the agile team made so far in completing the user stories in their current sprint. The horizontal axis shows the number of days in the sprint. The vertical axis shows the number of hours estimated by the team to complete the user stories in the sprint backlog
Based on this chart, what should the project manager recommend ?
Keep user stories as is
Add user stories
Re-prioritize user stories
Remove user stories
On October 3rd (represented by the red line on the Gantt chart below), the project sponsor asks you to provide a progress report including the CPI for a project status meeting the following morning. You update the project schedule management tool, which produces the following chart. The method used to determine the earned value is based on percent complete.
What are the project's current CPl and status?
The CPl is $650, and the project is running under planned costs
The CPI is 0.83, and the project is running over budget
The CPl is 1.21, and the project is running under planned costs
The CPl is 1.0, and the project is on budget
Several issues have been surfaced by the agile team members during a sprint retrospective. The scrum master wants to ensure that going forward appropriate actions are taken to address the problems.
What actions are best for the scrum master to plan to address the issues should they arise again?
Unclear Requirements
Request that the product owner grooms the backlog
Team struggles with obstacle
Help clear the impediments to progress
Work is not complete
Assist the team to create a definition of done
Technical debt
Suggest that the team uses refactoring in every iteration
Unclear working agreements for team
Facilitate the development of a team charter